MAHA-RERA Application

General Information

Other Than Individual

Organization

KARDA CONSTRUCTIONS LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

2ND FLOOR
GULMOHAR STATUS
DR MUNJE ROAD
SAMARTH NAGAR
ABOVE BUSINESS BANK
MAHARASHTRA
Nashik
Nashik
Nashik
Nashik
422005

Organization Contact Details

02532465436
www.kardaconstrutcion.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Hari Sankul - IIResidentialNA5600Near Ashoka Universal School Behind Fame Multiplex Ashoka Marg Nashik-422006S NO 860/1/33932011-12-252012-05-29
2Hari Aangan IIResidentialNA1350Hari Aangan D Building Jachak Mala Jay Bhavani Road Deolali Nasik-422401S NO 53/5D1242013-04-022013-05-07
3Hari Vandan - IIResidentialNA2340Near Aarambh Mahavidyalaya Sane Guruji Nagar Jail Road Nasik Road - 422101S NO 119A/119B/4/21282012-08-162012-10-31
4Hari NiwasResidentialCommercial & Residential5400Behind Muktidham Near Hotel Orange Tree Datta Mandir Road Nashik Road Nashik - 422101S NO 9/1 to 18/15, 9/1 to 18/163932011-07-202011-09-06
5Hari Sneh - IResidentialNA2620.73Behind Ashoka Universal School Near I.T. Park Nasik-422 011S NO 3/2C/2/B Plot No 1,2,3,41502012-08-102012-09-04
6Hari Sneh - IIResidentialNA1572.04Behind Ashoka Universal School Near I.T. Park Nasik-422011S NO3/2C/2/B Plot No 5,6,83502015-05-202015-06-01
7Hari ShrushtiResidentialNA7100Opp. IT Park Wadala Road Indira Nagar Nashik-422214110/5B/2/1,2,3,411202015-07-312015-08-15
8Hari SparshResidentialNA8000Barnes School Road Deolali Camp Nashik-422502S NO 305/1A/2B/1 , and S No 305/1A/2B/28762014-01-052014-04-28
9Hari Om IResidentialNA8800Near Guru Govind Singh Polytechnic College Indira Nagar Nashik-422009S NO 97 ,Plot NO 1,252162013-10-012013-11-16
10Hari SankalpResidentialNA3153.73Near Serene Meadows Gangapur Road Nasik-422013S No 41/1/1,2,3,4,5,6 Hissa no 32372012-10-202012-11-05
11Hari AmrutResidentialNA2383.3Lokhande Mala Old Saikheda Road Jail Road Nashik Road Nashik-42221448-2/33692014-07-052014-07-21
12Hari KunjResidentialNA1646.73Jai Bhavani Road Nasik Road Nasik-422101S No 52/6,8 Plot No 2,31362012-09-302012-10-31

Member Information

Member Name Designation Photo
NARESH JAGUMAL KARDA Managing Director View Photo
MANOHAR JAGUMAL KARDA Authorized Signatory View Photo

Project

HARI BHAKTI
On-Going Project
31/12/2020
31/12/2020
No
Others
Yes
Survey No 37/1B and 37/1C
12 M Wide DP Road
CTS No 6857 Part and S No 30
ADJ CTS NO 6889 AND S NO 37 1 C CTS NO 6858
APP LAYOUT NO LND FINAL 13 AND 18 M Wide DP Rd
MAHARASHTRA
Nashik
Nashik
Nashik
Deolali (CB)
422101
5066.17
3
3
0
507

FSI Details

2991.83
5408.17
8400.00

Co-Promoter Details

Project Name Promoter Name Co-Promoter Type Type of Agreement/ Arrangement Office Number Other Details
HARI BHAKTI Giriraj Developers Partnership Area Share NA Address : Anand Plaza ,203 ,Nasik Poona Rd ,- ,Near Vidyut Bhavan ,Division :Nashik ,District :Nashik ,Taluka :Nashik ,Village :Nashik ,422101 ,27
Project Name Promoter Name Co-Promoter Type Type of Agreement/ Arrangement Office Number Other Details
HARI BHAKTI Narendra Janardan Gadekar Individual Area Share NA Address : Gurujyot Society ,A5/6 ,Dattamandir Rd ,Nashik Road ,Surana Hospital ,Division :Nashik ,District :Nashik ,Taluka :Nashik ,Village :Nashik ,422101 ,27
Project Name Promoter Name Co-Promoter Type Type of Agreement/ Arrangement Office Number Other Details
HARI BHAKTI Anjali Janardhan Gadekar Individual Area Share NA Address : Sumangal Veena CHS ,D 202 ,Veena Nagar ,Mulund West ,LBS road ,Division :Konkan ,District :Mumbai City ,Taluka :Mumbai City ,Village :Mumbai City ,400080 ,27
Project Name Promoter Name Co-Promoter Type Type of Agreement/ Arrangement Office Number Other Details
HARI BHAKTI Sangita Janardhan Gadekar Individual Area Share NA Address : Sacred Heart Town ,I 8 ,Shivarkar Road ,Wanwadi ,- ,Division :Pune ,District :Pune ,Taluka :Haveli ,Village :wanwadi ,411040 ,27
Project Name Promoter Name Co-Promoter Type Type of Agreement/ Arrangement Office Number Other Details
HARI BHAKTI Sarlabai Janardhan Gadekar Individual Area Share NA Address : Gurujyot Soc ,A5/6 ,Dattamandir Road ,Nashik Road ,Surana Hospital ,Division :Nashik ,District :Nashik ,Taluka :Nashik ,Village :Nashik ,422101 ,27
Project Name Promoter Name Co-Promoter Type Type of Agreement/ Arrangement Office Number Other Details
HARI BHAKTI Suvarna Janardhan Gadekar Individual Area Share NA Address : Jai Shankar Building ,11 ,Muktidham Mandir ,Gaikwad Mala ,Nashik Road ,Division :Nashik ,District :Nashik ,Taluka :Nashik ,Village :Nashik ,422101 ,27

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 51 0 10

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Supply : YES 0 To be obtained from NMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Septic Tank with Saok Pit
Storm Water Drains : YES 0 As per approved plan
Landscaping & Tree Planting : YES 0 As per approved plan
Street Lighting : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : NO 0 NA
Aggregate area of recreational Open Space : YES 0 As per approved plan
Open Parking : YES 0 As per approved plan
Community Buildings : YES 0 As per approved plan
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 Recharge Pit with Borewell
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 As per provisional fire NOC

Building Details

Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 HARI BHAKTI A 1 1 0 4 1 22 15
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 HALL 1 159.41 1 1
2 OFFICE1 43.63 10 0
3 OFFICE2 42.21 1 0
4 OFFICE3 23.14 3 0
5 OFFICE4 38.95 1 0
6 SHOP1 42.18 1 0
7 SHOP2 23.23 3 0
8 SHOP3 39.45 1 0
9 HALL2 148.35 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 30
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 HARI BHAKTI B 0 1 0 13 1 17 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 57.95 22 5
2 2BHK 57.52 20 0
3 2BHK 97.61 1 0
4 2BHK 98.12 1 0
5 2BHK 69.26 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 20
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 12
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 HARI BHAKTI C 0 1 0 13 1 13 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 75.83 20 4
2 3BHK 75.95 4 0
3 3BHK 74.31 24 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Rasik Bothara NA Architect
R G Birla NA Structural Engineer
Vasant Bhagat NA Other

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Declaration in FORM B
Building Plan Approval (IOD)
Proforma of the allotment letter and agreement for sale
Commencement Certificates
Other