Past Experience Details

Project

NARAYAN OCTAVE
On-Going Project
31/03/2017
31/12/2018
No
Residential
Yes
408
GUT NO 2435
AMENITY SPACE
GUT NO 408 PART
GUT NO 408 PART
MAHARASHTRA
Pune
Pune
Khed
Nanekarwadi (CT)
410501
5069.18
2
2
0
596.37

FSI Details

0
6577.31
6577.31

Bank Details

ORIENTAL BANK OF COMMERCE
ORBC0101209

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
NARAYAN OCTAVE BABAJI BABURAO PAVLE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
NARAYAN OCTAVE VISHNU GANPAT PHARTALE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
NARAYAN OCTAVE SURESH VISHNU PHARTALE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 58 42 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Internal Cement roads
Water Conservation, Rain water Harvesting : YES 100 Rain Water Harvesting As per Norms
Energy management : YES 100 SOLAR WATER HEATING SYSTEM
Fire Protection And Fire Safety Requirements : YES 100 Fire Protection As per Fire Department Norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 DP Installation
Aggregate area of recreational Open Space : YES 100 Open Space
Open Parking : YES 100 As per Available
Water Supply : YES 100 water supply from MJP
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 STP and Drainage Line
Storm Water Drains : NO 0 NA
Landscaping & Tree Planting : YES 100 Tree Plantation and Landscaping
Street Lighting : YES 100 Street Lights Internal Project Only
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 STP
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 NARAYAN OCTAVE A BUILDING 0 1 0 8 1 20 42
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 30.23 4 4
2 1 BHK 31.00 4 4
3 1 BHK 31.82 8 8
4 1 BHK 32.42 3 3
5 1 BHK 32.44 1 1
6 1 BHK 32.83 8 8
7 1 BHK 24.30 4 4
8 1 BHK 27.16 4 4
9 1 BHK 27.49 4 4
10 1 BHK 27.50 4 4
11 1 BHK 28.92 3 3
12 1 BHK 28.93 1 1
13 1 BHK 29.47 4 4
14 1 BHK 29.47 4 4
15 1 BHK 32.97 4 4
16 1 BHK 33.26 8 8
17 1 BHK 35.56 4 4
18 1 BHK 35.82 4 4
19 2 BHK 45.42 8 8
20 2 BHK 45.73 4 4
21 2 BHK 45.74 4 3
22 2 BHK 47.42 3 3
23 2 BHK 47.68 3 3
24 2 BHK 47.74 8 8
25 2 BHK 47.86 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 NARAYAN OCTAVE B BUILDING 0 1 0 8 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 32.04 1 0
2 1 BHK 32.30 1 0
3 1 BHK 32.54 1 0
4 1 BHK 32.74 1 1
5 1 BHK 32.95 1 0
6 1 BHK 33.92 1 1
7 2 BHK 43.24 3 1
8 2 BHK 43.29 4 0
9 2 BHK 43.57 3 3
10 2 BHK 43.61 3 0
11 2 BHK 45.67 6 1
12 2 BHK 46.80 3 0
13 2 BHK 46.81 1 0
14 2 BHK 47.07 3 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
NITIN WAGHMARE NA Architect
VIKAS MAHADEORAO WAGHMARE NA Structural Engineer
SANTOSH GANGADHAR TOTE NA Contractor

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other