MahaRERA Application

General Information

Other Than Individual

Organization

BHAGWATI DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

1306
REAL TECH PARK
PLOT NO.39/2, SECTOR-30A
VASHI
OPP. VASHI RAILWAY STATION
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02227816115

Past Experience Details

Member Information

Member Name Designation Photo
BHOGILAL MAVJI VORA Authorized Signatory View Photo
MANJI KARMAN PATEL Partner View Photo
JIGNA BHOGILAL VORA Partner View Photo

Project

BHAGWATI GREENS 1
On-Going Project
30/09/2019
31/12/2019
No
Others
No
PLOT NO.6,SECTOR-23,KHARGHAR,NAVI MUMBAI.
PLOT NO 5
PLOT NO 2A AND ISCON TEMPLE
PLOT NO 3
40 MTR WIDE ROAD
MAHARASHTRA
Konkan
Raigarh
Panvel
Kharghar
410210
8799.60
5
5
0
4715.30

FSI Details

5.65
13193.74
13199.39

Bank Details

YES BANK LTD
YESB0000062

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 260 142 40

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 IN LATER SCOPE OF WORK
Energy management : YES 0 IN LATER SCOPE OF WORK
Fire Protection And Fire Safety Requirements : YES 0 IN LATER SCOPE OF WORK
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 IN LATER SCOPE OF WORK
Aggregate area of recreational Open Space : YES 0 IN LATER SCOPE OF WORK
Open Parking : YES 40 NA
Water Supply : YES 0 TEMPORARY CIDCO WATER CONNECTION IN PLACE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 10 AS PER APPROVED PLANS
Storm Water Drains : YES 0 IN LATER SCOPE OF WORK
Landscaping & Tree Planting : YES 0 IN LATER SCOPE OF WORK
Street Lighting : NO 0 NA
Community Buildings : YES 0 CLUBHOUSE ON 3RD FLOOR PODIUM PROPOSED
Treatment And Disposal Of Sewage And Sullage Water : YES 0 AS PER APPROVED PLANS
Solid Waste Management And Disposal : YES 0 PROVISION FOR OWC

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 BHAGWATI GREENS 1 SHOPPING 0 1 0 2 1 0 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE 9 102.98 1 0
2 TYPE 10 97.34 1 0
3 TYPE 11 91.72 1 1
4 TYPE 12 79.22 1 1
5 TYPE 1 110.02 1 1
6 TYPE 2 116.1 1 1
7 TYPE 3 110.48 1 1
8 TYPE 4 104.84 1 1
9 TYPE 5 92.64 1 0
10 TYPE 6 87.02 1 0
11 TYPE 7 112.6 1 1
12 TYPE 8 108.6 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 43
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 BHAGWATI GREENS 1 WING A 0 1 3 25 1 0 72
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE 1 68.62 24 17
2 TYPE 2 70.87 24 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 25
4 Stilt Floor 25
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 BHAGWATI GREENS 1 WING B 0 1 3 25 1 0 48
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE 1 46.44 48 22
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 25
4 Stilt Floor 25
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 BHAGWATI GREENS 1 WING C 0 1 3 25 1 0 48
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE 1 46.44 48 26
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 25
4 Stilt Floor 25
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 BHAGWATI GREENS 1 WING D 0 1 3 25 1 0 72
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE 1 70.87 24 10
2 TYPE 2 68.62 24 18
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 25
4 Stilt Floor 25
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Shaji Narayanan Paittal A51700005995 Real Estate Agent
Smitha Shaji Balakrishnan A51700006440 Real Estate Agent
Elint Realty LLP A51700000063 Real Estate Agent
Vikas Ramnet Sharma A51700008768 Real Estate Agent
Sainath Pawar A51800012369 Real Estate Agent
SOYUZ TALIB ARCHITECTS PVT LTD NA Architect
STRUCTURAL CONCEPT DESIGNS PVT LTD NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Proforma of the allotment letter and agreement for sale
Declaration in FORM B
Declaration in FORM B
Declaration in FORM B
Commencement Certificates
Commencement Certificates
Commencement Certificates
Commencement Certificates
Commencement Certificates
Commencement Certificates
Commencement Certificates
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Conveyance
Certificates of Architect (Form 4)
Other
Status of Formation of Legal Entity (Society/Co Op etc.)