MahaRERA Application

General Information

Other Than Individual

Organization

ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

CTS NO. 2254
1 MODI BAUG, COMMERCIAL BUILDING
GANESHKHIND ROAD
SHIVAJI NAGAR
NEAR AGRICULTURE COLLEGE
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411016

Organization Contact Details

02071017101
www.rohanbuilders.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Rohan Kritika D E K WingsResidentialNA3619S NO 117 A 1 117 B PARVATI PUNE 411009538A3942017-06-302017-04-28
2Rohan Kritika F G H I J WingResidentialNA7008S NO 117 A1 117 B PARVATI PUNE 411009CTS 538 A51872016-06-302017-03-30
3ROHAN LEHER 2 WINGS K L M N OResidentialNA1520BANER PUNE 411045S NO 53/5 ,53/6 ,54/1 ,54/12 BANER5502016-12-312017-03-31

Member Information

Member Name Designation Photo
SANJAY LUNKAD Authorized Signatory View Photo

Project

ROHAN ABHILASHA BUILDING D
On-Going Project
31/12/2021
30/06/2022
Yes
Residential
No
GAT NO 1458 1459 1460 P 1461 1462 1463 1464 1465 WAGHOLI
18 MTR ROAD
BLDG C
BLDG B
BLDG F
MAHARASHTRA
Pune
Pune
Haveli
WAGHOLI
412207
7617.09
5
5
0
11790.73

FSI Details

1340
26875.99
28215.99

Bank Details

ICICI BANK LTD
ICIC0000039

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 444 5 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 70 ENTIRE PROJECT
Water Conservation, Rain water Harvesting : YES 70 ENTIRE PROJECT
Energy management : YES 60 ENTIRE PROJECT
Fire Protection And Fire Safety Requirements : YES 60 ENTIRE PROJECT
Electrical Meter Room, Sub-Station, Receiving Station : YES 60 ENTIRE PROJECT
Sewerage line chamber STP : YES 0 BUILDING D
Strom water drains : YES 0 BUILDING D
Water supply : YES 0 BUILDING D
Aggregate area of recreational Open Space : YES 40 ENTIRE PROJECT
Open Parking : NO 0 NA
Water Supply : YES 60 ENTIRE PROJECT
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 60 ENTIRE PROJECT
Storm Water Drains : YES 60 ENTIRE PROJECT
Landscaping & Tree Planting : YES 60 ENTIRE PROJECT
Street Lighting : YES 50 ENTIRE PROJECT
Community Buildings : YES 50 CLUB HOUSE FOR ENTIRE PROJECT
Treatment And Disposal Of Sewage And Sullage Water : YES 70 ENTIRE PROJECT
Solid Waste Management And Disposal : YES 60 ENTIRE PROJECT

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 ROHAN ABHILASHA BUILDING D WING D1 31/12/2021 0 1 1 12 1 0 88
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 39.03 1 0
2 2 BHK 48.05 2 0
3 2 BHK 48.96 8 4
4 2 BHK 48.66 2 2
5 2 BHK 48.97 4 1
6 2 BHK 48.99 2 0
7 2 BHK 49.25 16 6
8 2 BHK 49.58 10 4
9 2 BHK 50.14 2 0
10 2 BHK 50.47 1 0
11 2 BHK 50.63 5 0
12 2 BHK 50.95 2 0
13 2 BHK 51.1 10 2
14 2 BHK 51.25 12 0
15 2 BHK 52.24 1 0
16 2 BHK 54.35 11 0
17 2 BHK 54.62 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 ROHAN ABHILASHA BUILDING D WING D2 31/12/2021 0 1 1 12 1 0 89
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 39.87 1 0
2 2 BHK 43.1 1 0
3 2 BHK 52.96 4 2
4 2 BHK 53.54 20 13
5 2 BHK 53.55 4 1
6 2 BHK 53.89 3 1
7 2 BHK 53.98 16 5
8 2 BHK 55.13 4 0
9 2 BHK 55.17 1 1
10 2 BHK 55.29 10 0
11 2 BHK 55.43 5 1
12 2 BHK 55.69 1 0
13 2 BHK 55.84 2 0
14 2 BHK 56.19 2 0
15 2 BHK 56.28 16 1
16 2 BHK 56.95 1 0
17 2 BHK 59.25 5 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 ROHAN ABHILASHA BUILDING D WING D3 31/12/2021 0 1 1 12 1 0 89
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 34.67 1 0
2 1 BHK 39.77 1 0
3 2 BHK 47.11 29 0
4 2 BHK 54.23 10 0
5 2 BHK 42.63 1 0
6 2 BHK 48.95 10 2
7 2 BHK 49.2 4 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 81.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 ROHAN ABHILASHA BUILDING D WING D4 0 1 1 12 1 0 89
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 36.99 1 0
2 1 BHK 30.62 1 0
3 2 BHK 45.5 4 0
4 2 BHK 46.77 33 0
5 2 BHK 47.11 27 0
6 2 BHK 49.68 2 0
7 2 BHK 50.14 8 0
8 2 BHK 42.63 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 60
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 36
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 ROHAN ABHILASHA BUILDING D WING D5 31/12/2021 0 1 1 12 1 0 89
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 38.38 1 0
2 1 BHK 41.45 1 0
3 3 BHK 75.73 24 7
4 3 BHK 76.62 16 0
5 3 BHK 77.44 2 0
6 3 BHK 75.6 8 3
7 3 BHK 75.68 1 0
8 3 BHK 76.38 8 3
9 3 BHK 76.46 4 0
10 3 BHK 77.34 23 9
11 3 BHK 77.75 8 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Prakash Kulkarni NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other