MahaRERA Application

General Information

Other Than Individual

Organization

SUYOG ANJANI AVISHKAR ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1205/3/3
Business embassy
Jungli maharaj road
Deccan
Bal gandharva statue
MAHARASHTRA
Pune
Pune
Haveli
Bhawarapur
411004

Organization Contact Details

02041305800
www.saaa.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Sai Avishkar Phase IResidentialNA15300Sr no 125 Near DSK vishwa Behind Omega Heritage Dhayri 44sr no 1255802015-06-012015-06-01

Member Information

Member Name Designation Photo
Jitendra Walchand Oswal Partner View Photo
Sanjay Kesrimal Oswal Partner View Photo
Kavish Rajoo Thakwani Authorized Signatory View Photo
Raju Thakwani Ramchandra Thakwani Authorized Signatory View Photo
Hemendra Keshavlal Shah Authorized Signatory View Photo
Chetan Purushottam Patel Authorized Signatory View Photo
Jimit Hemendra Shah Authorized Signatory View Photo

Project

sai avishkar
On-Going Project
30/12/2018
30/12/2018
Yes
Residential
No
125
90mtr wide road
SR NO - 126 AND 127
6 M WIDE ROAD
SR NO - 124
MAHARASHTRA
Pune
Pune
Haveli
Dhayari (Part)
Dhayari Phata
Dhayari
411044
15300
5
5
0
15300

FSI Details

0
4968.03
4968.03

Bank Details

HDFC Bank
HDFC0000060

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 66 18 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Balance will be completed
Water Conservation, Rain water Harvesting : YES 100 Completed
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 90 Balance Will be Completed
Aggregate area of recreational Open Space : YES 100 Garden and childrens play area completed
Open Parking : YES 95 Balance will be Completed
Water Supply : YES 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Completed
Storm Water Drains : YES 100 Completed
Landscaping & Tree Planting : YES 95 Garden and childrens play area completed
Street Lighting : YES 50 Balance will be completed
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Completed
Solid Waste Management And Disposal : YES 90 Balance Will be Completed on completion of Phase I

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 sai avishkar D 30/12/2018 0 2 0 6 0 0 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 32.76 1 0
2 1 BHK 32.78 5 3
3 1 BHK 32.41 2 0
4 1 BHK 33.34 1 0
5 1 BHK 32.92 1 0
6 1 BHK 32.78 3 0
7 1 BHK 32.75 4 3
8 1 BHK 32.6 7 3
9 RESIDENTIAL 785.28 24 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 sai avishkar E 30/12/2018 0 2 0 6 0 0 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 34.69 2 0
2 1 BHK 34.83 11 1
3 RESIDENTIAL 834.99 24 3
4 1 BHK 34.62 4 0
5 1 BHK 34.9 4 2
6 1 BHK 34.74 2 0
7 1 BHK 34.92 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 75
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 sai avishkar H 30/12/2018 0 2 0 6 0 0 14
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 53.72 2 0
2 3 BHK 66.01 2 2
3 2 BHK 53.33 1 0
4 2 BHK 56.26 1 0
5 2 BHK 53.75 1 1
6 3 BHK 66.54 1 1
7 3 BHK 66.65 1 1
8 3 BHK 66.73 2 1
9 2 BHK 55.39 1 0
10 3 BHK 64.02 1 0
11 2 BHK 53.31 2 1
12 3BHK 65.98 1 1
13 RESIDENTIAL 721.69 16 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 sai avishkar I 30/12/2018 0 2 0 6 0 0 15
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 52.42 2 1
2 2 BHK 50.73 2 2
3 2 BHK 53.35 2 0
4 2 BHK 50.51 2 0
5 2 BHK 50.48 2 1
6 2 BHK 53.31 1 0
7 2 BHK 50.85 1 1
8 2 BHK 50.45 2 0
9 2 BHK 50.51 2 0
10 RESIDENTIAL 821.06 16 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 sai avishkar J 30/12/2018 0 2 0 6 0 0 13
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 64.02 1 0
2 2 BHK 56.05 2 2
3 3 BHK 66.73 3 0
4 2 BHK 54.05 2 0
5 2 BHK 53.99 1 1
6 3 BHK 66.48 1 0
7 3 BHK 66.97 1 1
8 2 BHK 56.21 1 1
9 2 BHK 55.39 1 1
10 2 BHK 53.80 1 1
11 3 BHK 67.23 2 1
12 RESIDENTIAL 968.74 16 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AR SANDEEP HARDIKAR NA Architect
M/s. G. A. Bhilare Consultants Pvt. Ltd NA Structural Engineer

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
sai avishkar Malwankar 1054 Civil Yes Suit 2013 Final Argument

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other