MahaRERA Application

General Information

Other Than Individual

Organization

Xrbia Abode Developers Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

1 St Floor
Mantri House 929
F C Road
Shivajinagar
Dnyaneshwar Paduka Chowk
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004

Organization Contact Details

02066858888
www.xbia.com

Past Experience Details

Member Information

Member Name Designation Photo
Manojkumar Murlidhar Kamble Authorized Signatory View Photo
Hitendra Hari Patil Authorized Signatory View Photo

Project

Xrbia Abode
On-Going Project
31/03/2021
31/03/2021
No
Others
Yes
Gat No 240 Part
Gat No 240 Part and Gat No 192
Gat No 175 and Road
Gat No 240 and Gat No 178
Gat No 240 Part
MAHARASHTRA
Pune
Pune
Mawal
Jambhul
410507
33136
11
11
0
3307

FSI Details

1735.28
35419
37154.28

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement Office Number Other Details
Xrbia Abode Miracle Shelters LLP Others Revenue Share 02025424450 Address : Behere Arcade ,Office No 3B ,Prabhat Road ,S No 114B ,Prabhat Road ,Division :Pune ,District :Pune ,Taluka :Pune City ,Village :Pune (M Corp.) ,411004 ,27

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 45 0 60

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 10 Internal Roads in Trimix. Common for Larger Layout
Water Supply : YES 0 Common for Larger Layout
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Common for Larger Layout
Storm Water Drains : YES 0 Common for Larger Layout
Landscaping & Tree Planting : YES 0 Common for Larger Layout
Street Lighting : YES 0 Common for Larger Layout
Water Conservation, Rain water Harvesting : YES 0 Common for Larger Layout
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 Common for Larger Layout
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Common for Larger Layout
Aggregate area of recreational Open Space : YES 0 3307 sq mtr Common for Larger Layout
Open Parking : NO 0 NA
Community Buildings : YES 0 Common for Larger Layout
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Common for Larger Layout
Solid Waste Management And Disposal : YES 0 Common for Larger Layout

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Xrbia Abode A1 31/03/2021 0 1 0 8 1 0 6
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 20.61 14 13
2 1 BHK 22.67 84 79
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 48
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 2
11 Overall Percentage of Completion of the work done For the entire Building /Wing 64
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Xrbia Abode B1 31/03/2021 0 1 0 8 1 0 6
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 25.94 42 42
2 1 BHK 26.11 56 54
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 56
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 55
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 2
11 Overall Percentage of Completion of the work done For the entire Building /Wing 65.3
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Xrbia Abode B2 31/03/2021 0 1 0 8 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 9.65 7 3
2 1 RK 13.38 16 6
3 SHOP 18.70 2 0
4 1 RK 13.67 145 61
5 1 RK 15.77 22 20
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 17
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 6
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 32.3
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Xrbia Abode B3 31/03/2021 0 1 0 8 1 0 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 15.39 1 1
2 1 RK 10.47 7 7
3 1 RL 15.77 9 9
4 1 RK 13.64 119 106
5 1 RK 13.37 14 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 22
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 17
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 36
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

4
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47.9
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 Xrbia Abode C1 31/03/2021 0 1 0 8 1 0 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 37.83 1 0
2 2 BHK 38.05 3 0
3 2 BHK 31.95 16 11
4 2 BHK 35.02 14 12
5 2 BHK 35.24 26 19
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 3
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 7
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 Xrbia Abode D1 31/03/2021 0 1 0 8 1 0 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 9.64 7 7
2 1 RK 13.38 14 14
3 1 RK 13.67 147 145
4 1 RK 15.77 12 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 33
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 17
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 28
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

18
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 Xrbia Abode D2 31/03/2021 0 1 0 8 1 0 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 13.38 14 14
2 1 RK 9.64 7 7
3 1 RK 15.77 12 12
4 1 RK 13.67 147 145
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 24
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 17
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 28
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

7
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 Xrbia Abode E1 31/03/2021 0 1 0 8 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 44.07 8 4
2 2 BHK 48.42 1 0
3 2 BHK 48.69 3 0
4 SHOP 56 1 0
5 SHOP 43.21 1 0
6 SHOP 18.11 1 0
7 SHOP 56.01 1 0
8 2 BHK 38.91 18 12
9 2 BHK 44.05 14 10
10 2 BHK 38.09 16 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 28
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 17
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 32
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

13
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 Xrbia Abode F1 31/03/2021 0 1 0 8 1 0 3
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 42.47 24 23
2 3 BHK 49.51 3 0
3 SHOP 61.77 2 0
4 3 BHK 41.15 16 11
5 3 BHK 44.28 16 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 63
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 3
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 36.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 Xrbia Abode G1 31/03/2021 0 1 0 8 1 0 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 19.52 91 79
2 1 BHK 22.00 21 18
3 1 BHK 23.59 15 14
4 1 BHK 24 23 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 88
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 1
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 7
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 Xrbia Abode G2 31/03/2021 0 1 0 8 1 0 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 23.59 15 14
2 1 BHK 24.00 23 21
3 1 BHK 22 21 21
4 1 BHK 19.52 91 87
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 34
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 17
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 29
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

17
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.7

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Lashkaria Infrastructure Development NA Contractor
Swaminath Swami NA Architect
S R Consultants NA Structural Engineer
S.S.Patane And Associates NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Building Plan Approval (IOD)
Copy of Layout Approval (in case of layout)
Copy of the legal title report
Proforma of the allotment letter and agreement for sale
Details of encumbrances
Other
Other
Declaration in FORM B
Commencement Certificates
Status of Conveyance
Certificates of Architect (Form 4)
Certificates of CA (Form 5)
Status of Formation of Legal Entity (Society/Co Op etc.)