MahaRERA Application

General Information

Other Than Individual

Organization

NAIKNAVARE PRIDE AOP
Others
AOP
Do you have any Past Experience ?
Yes

Address Details

1204/4
NAIKNAVARE DEVELOPERS PVT LTD
GHOLE ROAD
SHIVAJINAGAR
NEAR BAL GANDHARV RANG MANDIR
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004

Organization Contact Details

02041471111
www.naiknavare.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1IRENE TOWERSResidentialNA17932.11S NO 221 TO 223 PART BANER PUNES NO 221 TO 223 PART BANER PUNE62792012-01-312012-03-29

Other Organization Type Member Information

Name Member Type
NAIKNAVARE DEVELOPERS PVT LTD Company
M/s PRIDE BUILDERS Partnership

Project

THE SPIRES
On-Going Project
30/06/2018
31/12/2018
31/12/2019
Yes
Residential
No
S NO 221 TO 223
12 M WIDE MEANS OF ACCESS
HISSA NO 221 4
30 M WIDE DP ROAD
PARTITION WALL BETWEEN IRENE TOWERS AND THE SPIRES
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
AUNDH
AUNDH
411007
8172.30
3
3
0
817.23

FSI Details

538.63
16461.37
17000.00

Bank Details

HDFC BANK LTD
HDFC0000007

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 203 185 95

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 AS PER PLAN
Water Conservation, Rain water Harvesting : YES 0 AS PER PLAN
Energy management : YES 90 AS PER PLAN
Fire Protection And Fire Safety Requirements : YES 100 AS PER PLAN
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AS PER PLAN
Aggregate area of recreational Open Space : YES 0 AS PER PLAN
Open Parking : YES 100 AS PER PLAN
Water Supply : YES 100 AS PER PLAN
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS PER PLAN
Storm Water Drains : YES 100 AS PER PLAN
Landscaping & Tree Planting : YES 95 AS PER PLAN
Street Lighting : YES 100 AS PER PLAN
Community Buildings : YES 100 AS PER PLAN
Treatment And Disposal Of Sewage And Sullage Water : YES 100 AS PER PLAN
Solid Waste Management And Disposal : YES 100 AS PER PLAN

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 THE SPIRES A BUILDING 31/12/2018 2 1 1 19 1 07 98
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 5 BHK 350.56 01 01
2 5 BHK 362.01 01 01
3 PENT HOUSE 285.24 01 01
4 PENT HOUSE 290.96 01 01
5 6 BHK 358.92 02 2
6 4BHK 199.26 10 8
7 3 BHK 171.96 2 1
8 4 BHK 195.40 02 2
9 4 BHK 195.49 10 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 95
3 X number of Podiums 95
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 93
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 94.3
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 THE SPIRES B BUILDING 31/12/2018 02 01 01 19 01 07 105
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 4 BHK 219.50 02 0
2 PENT HOUSE 350.31 02 01
3 4 BHK 248.19 02 0
4 4 BHK 240.70 14 12
5 4 BHK 240.20 14 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 95
3 X number of Podiums 95
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 87
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 92.7
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 THE SPIRES CLUB HOUSE 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 CLUB HOUSE 224.10 01 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
GAURI NAIKNAVARE NA Architect
KRUPALI KADAM NA Engineer

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
THE SPIRES CIVIL JUDGE SENIOR DIVISION PUNE 1806 Civil No Suit 2009 PENDING
NA
THE SPIRES Civil Judge Senior Division Pune 949 Civil No Suit 2017 PENDING
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Architect’s Certificate on Completion of Project (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other
Other
Other
Other