MahaRERA Application

General Information

Other Than Individual

Organization

SIDDHIVINAYAK HOMES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

PLOT NO 35, SECTOR 5
SIDDHIVINAYAK HOMES
NEAR ADHIRAJ GARDENS
KHARGHAR
OPP. GANESH MANDIR
MAHARASHTRA
Konkan
Raigarh
Panvel
Kharghar
410210

Organization Contact Details

02227451946
www.siddhivinayakhomes.co.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Orchid ResidencyResidentialNA5940Survey No 1-6 1-10 1-12 Village Harigram PanvelNA71662015-03-312015-07-31
2Siddhivinayak OrchidResidentialNA1439.40Plot no - 14 Sector 20 Kalamboli141482014-03-312014-09-30

Member Information

Member Name Designation Photo
VAIBHAV PURUSHOTTAM AGRAWAL Partner View Photo
GAURAV PURUSHOTTAM AGRAWAL Partner View Photo
SAURABH PURUSHOTTAM AGRAWAL Partner View Photo
GAURAV PURUSHOTTAM AGRAWAL Authorized Signatory View Photo

Project

SIDDHIVINAYAK MAHIMA
On-Going Project
31/12/2020
31/12/2020
No
Residential
No
32/9A, 32/9B
Survey No 32 Hissa No 10
Survey No 31
Survey No 38
Survey No 30
MAHARASHTRA
Konkan
Raigarh
Panvel
Koyana Velhe
Koyana Velhe
Koyana Velhe
410208
9599
5
5
0
960.9

FSI Details

10000
9599
19599.00

Bank Details

DCB BANK LTD
DCBL0000084

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 60 60 30

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Shall be provided by Promoter
Water Conservation, Rain water Harvesting : YES 0 Shall be provided by Promoter
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Shall be provided by Promoter
Aggregate area of recreational Open Space : YES 0 Shall be provided by Promoter
Open Parking : NO 0 NA
Water Supply : YES 0 Shall be provided by PMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Shall be provided by Promoter
Storm Water Drains : YES 10 Shall be provided by Promoter
Landscaping & Tree Planting : YES 0 Shall be provided by Promoter
Street Lighting : YES 0 Shall be provided by Promoter
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 SIDDHIVINAYAK MAHIMA BUILDING NO 1, A and B WING 31/12/2020 0 1 0 5 1 0 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 30.49 16 16
2 Residential 30.05 4 3
3 Residential 42.31 4 4
4 Residential 47.68 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 SIDDHIVINAYAK MAHIMA BUILDING NO 2, C and D WING 31/12/2020 0 1 0 5 1 0 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 42.31 8 7
2 Residential 44.39 4 4
3 Residential 30.49 20 20
4 Residential 30.56 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 32
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 SIDDHIVINAYAK MAHIMA BUILDING NO 3, E and F WING 31/12/2020 0 1 0 5 1 0 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 30.80 3 3
2 Residential 32.05 3 3
3 Residential 48.02 4 3
4 Residential 48.86 4 4
5 Residential 48.00 7 6
6 Residential 49.00 3 2
7 Residential 47.68 2 1
8 Residential 48.12 5 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 28
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 SIDDHIVINAYAK MAHIMA BUILDING NO 4, G, H, I and J WING 31/12/2020 0 1 0 5 1 0 18
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 30.02 24 24
2 Residential 31.12 8 8
3 Residential 30.85 48 47
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 30
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 33
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 SIDDHIVINAYAK MAHIMA BUILDING NO 5, K, L and M WING 31/12/2020 0 1 0 5 1 0 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 30.62 4 4
2 Residential 30.79 4 4
3 Residential 45.70 4 4
4 Residential 48.35 4 4
5 Residential 30.49 16 16
6 Residential 32.12 8 8
7 Residential 44.21 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 28

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
HDFC DEVELOPERS LIMITED A51900000930 Real Estate Agent
SPACE INDIA BUILDERS & DEVELOPERS A52000003144 Real Estate Agent
SUMIT RAJENDRA ANAND A51700003280 Real Estate Agent
ROMIT RAJENDRA ANAND A51700003371 Real Estate Agent
Jayesh Shah NA Contractor
Meenakshi Shrivastav NA Architect
Rajesh Bulsara NA Architect
S V PATEL NA Structural Engineer
MANDAR S PADHYE NA Other

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Commencement Certificates
Copy of the legal title report
Building Plan Approval (IOD)
Copy of Layout Approval (in case of layout)
Details of encumbrances
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Details of encumbrances
Status of Conveyance
Certificates of Architect (Form 4)
Other
Status of Formation of Legal Entity (Society/Co Op etc.)