MahaRERA Application

General Information

Other Than Individual

Organization

PADMADISHA PARADISE
Partnership
NA
Do you have any Past Experience ?
No

Address Details

8A FLAT NO. 001
ASHOK NAGAR CHS LTD
KALYAN ROAD
ASHOK NAGAR
POST DANDEKARWADI
MAHARASHTRA
Konkan
Thane
Bhiwandi
Bhiwandi (M Corp.)
421302

Organization Contact Details

02522248845
www.padmadishaparadise.com

Past Experience Details

Member Information

Member Name Designation Photo
KRISHNA RAJAYYA GAJANGI Authorized Signatory View Photo
DILEEP BUDHAJI DHUMAL Partner View Photo

Project

PADMADISHA PARADISE
On-Going Project
16/12/2016
31/12/2018
No
Residential
No
133/1P, 133/2P, 134/12P, 135/6P
SURVEY NO 135 -PART5
SURBEY NO 135 - PART3
18METER PROPOSED ROAD
EXISTING ROAD
MAHARASHTRA
Konkan
Thane
Bhiwandi
Bhiwandi (M Corp.)
421302
5883
3
3
0
791.58

FSI Details

0
8704.27
8704.27

Bank Details

AXIS BANK LTD
UTIB0000591

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 47 21 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 WORK COMPLETED
Energy management : YES 100 WORK COMPLETED
Fire Protection And Fire Safety Requirements : YES 100 WORK COMPLETED
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 WORK COMPLETED
Aggregate area of recreational Open Space : YES 100 WORK COMPLETED
Open Parking : YES 100 WORK COMPLETED
Water Supply : YES 100 WORK COMPLETED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 WORK COMPLETED
Storm Water Drains : YES 100 WORK COMPLETED
Landscaping & Tree Planting : YES 100 WORK COMPLETED
Street Lighting : YES 100 WORK COMPLETED
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 PADMADISHA PARADISE WING A 31/12/2018 0 1 0 13 1 32 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 62.53 12 12
2 2 BHK 62.86 12 11
3 2 BHK 60.40 24 22
4 2 BHK 62.99 24 16
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 PADMADISHA PARADISE WING B 0 1 0 13 1 30 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 48.11 8 6
2 1 BHK 53.03 8 5
3 2 BHK 63.99 24 24
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 PADMADISHA PARADISE WING C 0 1 0 9 1 18 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 49.24 8 8
2 1 BHK 51.10 16 13
3 1 BHK 48.11 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SANJAY BALU PATIL NA
SHAUKAT GANNI KHAN NA Contractor
ALIM A K FOUZIAS NA Architect
MAJID DHOKLE NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other