MahaRERA Application

General Information

Other Than Individual

Organization

ASHA DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

PLOT NO. 40
KRISHNA REGENCY
SECTOR 30
VASHI
NEAR PUDHARI PRESS
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02227812423

Past Experience Details

Member Information

Member Name Designation Photo
SURINDER MITTAL Partner View Photo
ASHA MITTAL Partner View Photo

Project

KRISHNA ENCLAVE
On-Going Project
31/12/2005
01/08/2022
Yes
Residential
Yes
CTS No 190 to 426, 795 to 799
CTS NO 424
DP ROAD
CTS NO 423
VAKOLA PANKAJ CHS AND CTS NO 444 AND 445
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
Datta Mandir Road
Vakola
400055
14467.10
3
3
0
1039.97

FSI Details

7233.55
36167.75
43401.30

Bank Details

DHANLAXMI BANK LTD
DLXB0000199

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
KRISHNA ENCLAVE VILLAYATI RAM MITTAL Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Water Conservation, Rain water Harvesting : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Aggregate area of recreational Open Space : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Open Parking : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Water Supply : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Storm Water Drains : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Landscaping & Tree Planting : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Street Lighting : YES 67 WORK OF 3RD BUILDING IN PROGRESS
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 KRISHNA ENCLAVE KRISHNA GALAXY 0 1 0 12 1 41 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 BANK 107 1 0
2 NURSINGHOME 107 1 0
3 3BHK 80 12 11
4 DUPLEX 87 2 0
5 1BHK 39 68 67
6 2BHK 58 40 40
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 KRISHNA ENCLAVE KRISHNA REGENCY 01/08/2022 0 1 1 10 1 45 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 CONVINENTSHOPPING1 9.65 1 0
2 CONVINIENTSHOPPING2 9.49 1 0
3 CONVINIENTSHOPPING3 15.76 1 0
4 CONVINENTSHOPPING4 10.95 1 0
5 CONVINIENTSHOPPING5 11.7 1 0
6 CONVINENTSHOPPING6 15.31 1 0
7 CONVINENTSHOPPING7 16.04 1 0
8 CONVINENTSHOPPING8 15.36 1 0
9 CONVINENTSHOPPING9 18.27 1 0
10 CONVINENTSHOPPING10 17.71 1 0
11 SHOP 4.76 1 0
12 PC1 43.99 1 0
13 PC2 68.05 1 0
14 BANK 85.75 1 0
15 NURSINGHOME 92.78 1 0
16 A 106.89 8 3
17 B 99.47 7 6
18 C 39.74 14 13
19 E 65.8 7 5
20 F 69.15 16 7
21 G 99.47 1 1
22 J 65.8 1 0
23 I 65.97 2 0
24 H 39.74 2 0
25 D 65.97 28 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 KRISHNA ENCLAVE KRISHNA RESIDENCY 01/08/2022 2 1 2 17 1 80 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 61.3 180 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
VIVEK BHOLE NA Architect

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
KRISHNA ENCLAVE Bombay High Court 2497 Civil No Writ Petition 2004 Admitted Unready
NA
KRISHNA ENCLAVE Bombay High Court 753 Civil No Writ Petition 2016 Pre Admission
NA
KRISHNA ENCLAVE Bombay High Court 2037 Civil No Writ Petition 2016 Admitted Unready
NA
KRISHNA ENCLAVE Bombay High Court 2877 Civil No Suit 2007 Pre Admission
NA
KRISHNA ENCLAVE Bombay High Court 2506 Civil No Appeal 2009 Pending
NA
KRISHNA ENCLAVE Bombay High Court 5277 Civil No Writ Petition 2014 For Restoration
NA
KRISHNA ENCLAVE Bombay High Court 11583 Civil No Writ Petition 2014 Pre Admission
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout) and Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other