MahaRERA Application

General Information

Other Than Individual

Organization

Godrej Redevelopers (Mumbai) Pvt. Ltd.
Company
NA
Do you have any Past Experience ?
No

Address Details

5th floor
Godrej One
Pirojshanagar
Vikhroli (East)
Eastern Express Highway
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400079

Organization Contact Details

02261198500

Past Experience Details

Member Information

Member Name Designation Photo
Neeraj Gupta Authorized Signatory View Photo
Sumit Agrawal Authorized Signatory View Photo

Project

Godrej Prime
On-Going Project
23/05/2021
31/05/2022
Yes
Residential
Yes
CTS Nos.53/pt and 52/pt
CTS No 57 and 58 and 12 mtr wide SN Rd no 4
CTS No 49 and 9 mtr wide road
CTS No 54 and 56 and 9 mtr wide road
CTS No 51 and 9 mtr wide SN Road no 3
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400071
15903.46
17
17
0
0

FSI Details

8346.96
66796.89
75143.85

Bank Details

Axis Bank Ltd
UTIB0000108

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement Office Number Other Details
Godrej Prime Godrej Properties Limited (Development Manager) Company Revenue Share 02261698500 Address : Godrej One ,5th floor ,Pirojshanagar ,Vikhroli (East) ,Eastern Express Highway ,Division :Konkan ,District :Mumbai Suburban ,Taluka :Kurla ,Village :Kurla ,400079 ,27
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement Office Number Other Details
Godrej Prime Sahakar Nagar Vibhag -2 Co-Op Hsg Soc Ltd Societies Revenue Share NA Address : C/o. Godrej Prime Site Office ,NA ,Road No 1 ,Sahakar Nagar No 1 ,Near Tilak Nagar Railway Station ,Division :Konkan ,District :Mumbai Suburban ,Taluka :Kurla ,Village :Kurla ,400071 ,27

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 980 625 68

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 By Developer
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 By Developer
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 By Developer
Club House : YES 0 By Developer
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 By Developer
Water Supply : YES 0 By MCGM
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 By Developer
Storm Water Drains : YES 0 By MCGM
Landscaping & Tree Planting : YES 0 By Developer
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 By Developer
Solid Waste Management And Disposal : YES 0 By Developer

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Godrej Prime S1 31/05/2022 2 1 0 14 1 0 132
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 69.45 28 24
2 3 BHK 92.34 28 28
3 3 BHK 98.78 26 26
4 2 BHK 72.65 28 27
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 84
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 48
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

17
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 46.9
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Godrej Prime S2 31/05/2022 2 1 0 15 1 1 85
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2.5 BHK 70.91 14 14
2 3.5 BHK 95.92 1 1
3 2 BHK 64.43 28 18
4 2 BHK 67.29 15 14
5 2.5 BHK 78.13 15 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 80
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 22
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 19
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Godrej Prime S3 31/05/2022 2 1 0 15 1 0 71
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 51.39 1 1
2 2 BHK 65.49 14 9
3 2 BHK 68.93 30 26
4 2 BHK 65.54 14 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 81
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 28
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 21
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 42.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Godrej Prime S4 31/05/2022 2 1 0 15 1 0 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 51.9 1 1
2 2BHK 65.38 28 18
3 2 BHK 68.94 30 26
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 82
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 69
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 24
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

3
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47.3
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 Godrej Prime S5 31/05/2022 2 1 0 15 1 0 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 51.39 1 1
2 2BHK 65.47 14 7
3 2BHK 65.49 14 7
4 2 BHK 68.94 30 24
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 82
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 69
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 24
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

3
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47.3
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 Godrej Prime S6 31/05/2022 2 1 0 15 1 0 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 67.42 1 1
2 2BHK 67.55 14 7
3 2.5 BHK 81.28 14 13
4 2 BHK 67 15 11
5 2 BHK 69.43 15 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 82
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47.2
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 Godrej Prime S7 31/05/2022 2 1 0 15 1 0 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 67.19 15 12
2 2BHK 67.55 15 8
3 2BHK 70.33 15 5
4 2.5 BHK 80.22 14 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 77
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

9
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 46.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 Godrej Prime S8 31/05/2022 2 1 0 15 1 0 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 51.9 1 1
2 2BHK 65.47 14 2
3 2 BHK 68.94 30 12
4 2 BHK 65.49 14 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 82
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 81
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 7
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 12
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 37.2
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 Godrej Prime Nova - S9 31/05/2022 2 1 0 15 1 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 53.71 1 0
2 2BHK 65.49 13 2
3 2BHK 65.47 13 4
4 2BHK 68.94 28 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 81
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 81
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 6
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 12
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 37
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 Godrej Prime T1 31/05/2022 1 1 1 14 1 3 34
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 45.95 14 12
2 1BHK 46.08 14 14
3 1BHK 56.52 13 12
4 1BHK 56.6 14 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 95
2 X number of Basement(s) and Plinth 71
3 X number of Podiums 100
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 59
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

48
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 59.3
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 Godrej Prime T2 1 1 1 14 1 1 36
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.44 14 12
2 2BHK 63.69 14 13
3 2BHK 63.77 13 12
4 1 BHK 39.47 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 95
2 X number of Basement(s) and Plinth 71
3 X number of Podiums 100
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 59
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

48
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 59.3
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
12 Godrej Prime T3 1 1 1 14 1 0 36
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.54 14 14
2 1BHK 40.47 14 13
3 2BHK 63.69 14 13
4 2BHK 63.78 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 95
2 X number of Basement(s) and Plinth 71
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 67
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

54
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 61.2
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
13 Godrej Prime T4 1 1 1 14 1 0 36
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.56 14 13
2 1BHK 40.49 14 12
3 2BHK 63.69 14 13
4 2BHK 64.19 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 71
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 67
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

54
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 61.7
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
14 Godrej Prime T5 1 1 1 14 1 0 36
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.53 14 12
2 1BHK 39.92 14 13
3 2BHK 63.69 14 13
4 2BHK 64.19 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 85
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 93
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 86
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 34
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

78
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 21
11 Overall Percentage of Completion of the work done For the entire Building /Wing 73.7
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
15 Godrej Prime T6 1 1 1 14 1 0 36
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.79 14 13
2 1BHK 39.85 14 12
3 2BHK 64.2 13 12
4 2BHK 64.42 14 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 85
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 93
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 34
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

82
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 21
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
16 Godrej Prime T7 1 1 1 14 1 5 31
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.5 14 13
2 1BHK 39.57 14 12
3 2BHK 63.69 14 13
4 2BHK 64.19 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 85
3 X number of Podiums 100
4 Stilt Floor 65
5 X number of Slabs of Super Structure 93
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 76
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 34
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

82
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 21
11 Overall Percentage of Completion of the work done For the entire Building /Wing 69.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
17 Godrej Prime T8 1 1 1 14 1 5 31
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.41 13 12
2 1BHK 39.44 15 13
3 2BHK 63.7 14 13
4 2BHK 63.8 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 85
3 X number of Podiums 100
4 Stilt Floor 75
5 X number of Slabs of Super Structure 93
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 73
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 33
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

87
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 31
11 Overall Percentage of Completion of the work done For the entire Building /Wing 71.7

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
FANM Property Services Pvt Ltd A52000000045 Real Estate Agent
SYNERGY INFRACON A51900000176 Real Estate Agent
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
HDFC Realty Limited A51900000107 Real Estate Agent
ANMOL BALAJI BROKING A51800000364 Real Estate Agent
Nitesh Jaikishan Changani A51900000918 Real Estate Agent
ASHISH KUMAR JHA A51800000901 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
Acquest Property and Hospitality Services Pvt. Ltc. A51800000384 Real Estate Agent
Mumbai Property Exchange Pvt Ltd A51900000211 Real Estate Agent
Nikhil Lalit Parekh A51900000040 Real Estate Agent
PROPERTYPISTOL REALTY PRIVATE LIMITED A51700000043 Real Estate Agent
RAMESH GUJJA A51800000610 Real Estate Agent
Rioga Premium Real Estate Advisory LLP A51800000974 Real Estate Agent
AMOL SURESH PAGARE a51700002679 Real Estate Agent
Gaurav Gaurang Saha a51900009312 Real Estate Agent
Asset India Realty a51700003799 Real Estate Agent
Manisha Lifespaces Consulting Pvt. Ltd. a51800008040 Real Estate Agent
HALLMARK HOMES a51900006069 Real Estate Agent
Blunest Technologies Pvt Ltd A51900004449 Real Estate Agent
CHIRAG GOVIND PANCHAL A51800002304 Real Estate Agent
INIVESH REAL ESTATE INVESTMENT ADVISORS LLP A51800003600 Real Estate Agent
QUICK HOMES PROPERTY ADVISORY A51800005188 Real Estate Agent
SUDHIR SAHU A51800008377 Real Estate Agent
PAWAN MAHAKANT THAKUR A51900000119 Real Estate Agent
MAHAVIR PRASAD TOSHNIWAL A51700003016 Real Estate Agent
Mayuresh Joyaji Tawade A51900002243 Real Estate Agent
Manasvi Properties A51800006556 Real Estate Agent
Fortune Financial Services(India)Limited A51900004280 Real Estate Agent
BDL Estate and Property A51900002831 Real Estate Agent
Dream Homes Realty A51700000406 Real Estate Agent
TERRAA PROPEX PRIVATE LIMITED A51900000455 Real Estate Agent
RAJANI PROPERTY CONSULTANTS A51900001345 Real Estate Agent
New Project Deals A51900003045 Real Estate Agent
OK Sir E-Commerce Pvt. Ltd. A51900000943 Real Estate Agent
PROPERTY ADDRESS A51900006765 Real Estate Agent
ANJANEYA SPACES LLP A51900006346 Real Estate Agent
PANKAJ SHIVKUMAR DEMBLA A51900003761 Real Estate Agent
GLOBAL GROUP A52000006598 Real Estate Agent
SUMED SHIVAJI JADHAV A51700001185 Real Estate Agent
VINOD DATTATREAY POL A51700006099 Real Estate Agent
Gaurav Kishorkant Vajaria A51700001595 Real Estate Agent
BARCODE REALTY A51700006225 Real Estate Agent
MS PROPERTY SOLUTION A51700009898 Real Estate Agent
DT REALTORS A51700008479 Real Estate Agent
DEEPU J SHETTY A51700001868 Real Estate Agent
Amit M Gala A51900000588 Real Estate Agent
Urbo Ventures Private Limited A51900004952 Real Estate Agent
Amol Anant Bhadange A51800005251 Real Estate Agent
ASHOK PRITAM GIRI A51800006927 Real Estate Agent
RUSHABH GULABCHAND GUDHKA A51700005533 Real Estate Agent
AMIT SURENDRA SINGH A51700004191 Real Estate Agent
SUNDAR JAGANNATH BANAVALIKAR A51700000591 Real Estate Agent
mohammad JAVED A51700003077 Real Estate Agent
DELIGHT NEST REALITY & PROPERTY A51700006872 Real Estate Agent
Amarjeet Kaur Jaggi A51700009469 Real Estate Agent
VINEET KUMAR KUSHWAHA A51700000467 Real Estate Agent
Kalpesh Gajra A51700010482 Real Estate Agent
JUGAL THAKKAR A51700012865 Real Estate Agent
Prashant Maruti Kedare A52000002662 Real Estate Agent
PROPERTY MEGAMART REALTY PVT LTD A51700001247 Real Estate Agent
Gaurang Lakhotia A51900009055 Real Estate Agent
OMPRAKASH MEJURAM GAUD A99000002531 Real Estate Agent
PROPFINDER INDIA PRIVATE LIMITED A52100004005 Real Estate Agent
QUICK HOMES PROPERTY ADVISORY A51800005188 Real Estate Agent
Rudram Realty A51900003315 Real Estate Agent
GHARONDAA ADVISORS PRIVATE LIMITED A51900009920 Real Estate Agent
Horizon Financial & Properties Advisers LLP A51800001892 Real Estate Agent
JAIDEV REAL ESTATE AND PROPERTY CONSULTANTS A51900002856 Real Estate Agent
RAMESH DAGLYA A51900006558 Real Estate Agent
NARAYAN REALTORS A51800002095 Real Estate Agent
VIVEK SADASHIV CHITALE A51800000938 Real Estate Agent
XTREME PROPERTIES A51800006795 Real Estate Agent
Excellink Finservices PVT LTD A51700005686 Real Estate Agent
HCI EVENTS AND PROMOTIONS PRIVATE LIMITED A51700014175 Real Estate Agent
HOUSEZINN PROPERTIES PRIVATE LIMITED A51700003041 Real Estate Agent
INVESTOXPERT A52100014648 Real Estate Agent
Jain Realtors A51700005888 Real Estate Agent
MARKETING SPACE PRIVATE LIMITED A51700000595 Real Estate Agent
METRO PROPERTIES A51800000740 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
MySpace Realty A51800001885 Real Estate Agent
Mystic Realtors A52000007002 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Realtyezee Advisors LLP A51800008532 Real Estate Agent
Services For NRI Ltd A52100014855 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
Jaatvedas Construction Co Pvt Ltd NA Contractor
SNB Infrastructure NA Contractor
P G Patki Architects NA Architect
Raje Structural Consultants Pvt Ltd NA Structural Engineer
Pankaj Dharkar and Associates NA Other
Cushman & Wakefield NA Other
Arcadis NA Other
Pravin Electricals NA Other
Safe Treat Engineers & Contractors Pvt Ltd NA Other
Godrej Properties Limited NA Other
Gagangiri Buildcon Private Limited NA Other

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Godrej Prime Bombay High Court 408 Civil No Writ Petition 2017 Hearing on the Precipe for detagging of the case
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Proforma of the allotment letter and agreement for sale
Declaration in FORM B
Copy of Layout Approval (in case of layout)
Commencement Certificates
Commencement Certificates
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates
Commencement Certificates
Commencement Certificates
Commencement Certificates
Commencement Certificates
Commencement Certificates
Status of Conveyance
Certificates of Architect (Form 4)
Other
Status of Formation of Legal Entity (Society/Co Op etc.)