MahaRERA Application

General Information

Other Than Individual

Organization

SONAM BUILDERS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1ST FLOOR
SHANTI NIWAS
100 FEET ROAD
MIRA BHAYANDER EAST
SHRI MITHALAL JAIN BUNGLOW
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401105

Organization Contact Details

02228167480
www.sonambuilders.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1NEW GOLDEN NEST PHASE XVResidentialNA14350100 FT ROAD NEW GOLDEN NEST PH XV MIRA BHAYANDER ROAD EAST THANE PIN CODE 401105317/1,321/2,6,5,9,11,13,328/7,326/8, 327/20,23,330/2,322/1842802012-12-312013-05-23
2INDRAPRASTH WING AResidentialNA11116100 FEET ROAD GOLDEN NEST PHASE XVI NEAR JAIN MANDIR MIRA BHAYANDER EAST THANE 40110530/11,14,15,21,22,24,29/1,23/2,22/1,2,3,5,9, 20/611572017-03-312017-07-27
3INDRAPRASTH WING BResidentialNA11116100 FEET ROAD GOLDEN NEST XVI NEAR JAIN MANDIR MIRA BHAYANDER EAST THANE 40110530/11,14,15,21,22,24,29/1,23/2,22/1,2,3,5,9, 20/611542017-07-312017-07-27
4RENTAL BUILDING R2OthersRESIDENTIAL CUM COMMERCIAL - FREE SALE FLATS4747100 FEET ROAD NEW GOLDEN NEST OPP HANUMAN MANDIR BHAYANDER EAST THANE 40110530/11, 14,15,21,22,24, 29/1, 23/2, 22/1,2,3,5,9, 20/614692017-07-312017-07-27

Member Information

Member Name Designation Photo
BHARAT MITHALAL JAIN Partner View Photo
MITHALAL RATANCHAND JAIN Partner View Photo

Project

INDRAPRASTH WING C
On-Going Project
31/12/2019
30/09/2020
No
Residential
No
30/11,14,15,21,22,24,29/1,23/2,22/1,2,3,5,9,20/6
POOJA GARDEN
GOLDEN NEST PHASE VII VIII IX
GOLDEN NEST PHASE XI XII
GOLDEN NEST PHASE I
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
100 FEET ROAD
BHAYANDER
401105
11116
1
1
0
1358.93

FSI Details

10148
2577
12725.00

Bank Details

AXIS BANK
UTIB0003146

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 301 0 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 INTERNAL ROADS & FOOTPATH COMPLETED
Water Conservation, Rain water Harvesting : YES 100 WORK COMPLETED
Energy management : YES 100 WORK COMPLETED
Fire Protection And Fire Safety Requirements : YES 100 WORK COMPLETED
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 WORK COMPLETED
Aggregate area of recreational Open Space : YES 100 WORK COMPLETED
Open Parking : NO 0 NA
Water Supply : YES 100 WORK COMPLETED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 WORK COMPLETED
Storm Water Drains : YES 100 WORK COMPLETED
Landscaping & Tree Planting : YES 100 WORK COMPLETED
Street Lighting : YES 100 WORK COMPLETED
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 WORK COMPLETED
Solid Waste Management And Disposal : YES 100 WORK COMPLETED

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 INDRAPRASTH WING C C WING 2 1 2 0 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 77.89 80 0
2 2BHK 75.05 35 0
3 2BHK 72.03 2 2
4 3BHK 101.23 40 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 2
3 X number of Podiums 2
4 Stilt Floor 1
5 X number of Slabs of Super Structure 20
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 62.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
VIVEK BHOLE NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Architect’s Certificate on Completion of Project (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other