MahaRERA Application

General Information

Other Than Individual

Organization

KARMAA BUILDERS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

KARMAA BUILDERS
ADITYA HEIGHTS
HOLKAR ROAD
MUMBAI NAKA
NEXT TO SUYASH HOSPITAL
MAHARASHTRA
Nashik
Nashik
Nashik
Nashik (M Corp.)
422005

Organization Contact Details

02265278921
www.karmaagroup.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1KARMAA HEIGHTSResidentialNA4490KARMAA HEIGHTS TAPOVAN ROAD BEHIND CHINTAMANI PLAZA NASHIK 4220114453842009-01-102009-02-20
2KARMAA RESIDENCYResidentialNA3104KARMAA RESIDENCY BEHIND HOTEL SAI PALACE OFF MUMBAI AGRA HIGHWAY NASHIK 4220099062882014-01-102014-02-13

Member Information

Member Name Designation Photo
CHANDRA VINOD TALWAR Partner View Photo
Vinod Madanlal Talwar Partner View Photo
YASH VINOD TALWAR Partner View Photo
ADITYA VINOD TALWAR Authorized Signatory View Photo

Project

KARMAA PINNACLE
On-Going Project
01/07/2019
01/07/2019
No
Residential
No
860/2/3
Colony Road
Plot No 4
Colony Road
30Meter Road
MAHARASHTRA
Nashik
Nashik
Nashik
Nashik Road
Ashoka Marg
Nashik Road
422011
936
1
1
0
0

FSI Details

319
2489
2808.00

Bank Details

STATE BANK OF INDIA
SBIN0014885

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 15 4 70

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 Run Off Water Collection pits in Storm water drain
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 According to Municipal bylaws and Fire NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Electrical Meter Cabinet will be provided
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 Around the building
Water Supply : YES 0 Municipal water supply application after OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 I.C. and Lines to the Chambers will be provided
Storm Water Drains : YES 0 Storm water drains around the building
Landscaping & Tree Planting : YES 0 Trees will be planted according to municipal laws
Street Lighting : YES 0 Compound lighting will be provided
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 KARMAA PINNACLE Karmaa Pinnacle B Wing 01/07/2019 1 1 0 9 0 17 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 40.74 3 3
2 Shop 42.97 1 1
3 Shop 22.32 1 1
4 Shop 27.72 1 1
5 Shop 23.04 1 1
6 Shop 26.72 1 1
7 Shop 32.60 1 1
8 Office 34.50 3 3
9 Office 37.11 1 1
10 Office 17.52 1 1
11 Office 21.97 1 1
12 Office 23.04 1 1
13 2BHK 47.97 1 1
14 2BHK 48.13 1 1
15 2BHK 60.60 2 2
16 Office 18.92 1 1
17 Office 48.70 1 1
18 2BHK 48.30 12 8
19 2BHK 59.00 12 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 45

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Rasik Bothara NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Declaration in FORM B
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Other
Copy of Layout Approval (in case of layout)
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Other
Other
Other
Details of encumbrances
Details of encumbrances
Details of encumbrances
Details of encumbrances
Details of encumbrances
Proforma of the allotment letter and agreement for sale
Commencement Certificates
Status of Conveyance
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)