MahaRERA Application

General Information

Other Than Individual

Organization

SATISH BORA AND ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

2
RACHANA AVENUE
FC ROAD
DECCAN
GOOD LUCK CHOWK
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411004

Organization Contact Details

02025512172

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1CRYSTAL HEIGHTSResidentialNA3500S NO. 176S NO 176, PART2682013-08-312013-07-01

Member Information

Member Name Designation Photo
PANKAJ BORA Authorized Signatory View Photo
SATISH KANTILAL BORA Partner View Photo

Project

LIBERO
On-Going Project
31/12/2015
31/12/2025
Yes
Residential
No
S NO 84
S NO 84
S NO 86
S NO 83
S NO 85
MAHARASHTRA
Pune
Pune
Haveli
Warje
WARJE
WARJE
411058
5252.34
4
3
1
830

FSI Details

9288.30
7417.13
16705.43

Bank Details

JANATA SAHAKARI BANK LIMITED
JSBP0000008

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 270 29 90

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 NO FOOTHPATH
Water Conservation, Rain water Harvesting : YES 100 AS REMARK MENTIONED IN RAIN WATER HARVESTING NOC
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 95 AS REMARK MENTIONED IN FIRE NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 AS PER NORMS
Aggregate area of recreational Open Space : YES 100 NA
Open Parking : YES 100 NA
Water Supply : YES 0 AS PER PMC NORMS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS REMARK MENTIONED IN DRAINAGE NOC
Storm Water Drains : YES 100 AS REMARK MENTIONED IN DRAINAGE NOC
Landscaping & Tree Planting : YES 100 AS REMARK MENTIONED IN GARDEN NOC
Street Lighting : YES 100 AS PER CONSULTANTS DRAWINGS
Community Buildings : YES 100 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 NA
Solid Waste Management And Disposal : YES 100 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 LIBERO WING H 31/12/2025 1 0 1 15 0 10 90
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 66.24 2 2
2 2 BHK 66.56 1 1
3 2 BHK 61.39 19 2
4 2 BHK 65 1 1
5 2 BHK 65.03 1 1
6 2 BHK 63.78 14 0
7 2 BHK 66 1 1
8 2 BHK NOT SANCTIONED 63.78 12 0
9 2 BHK NOT SANCTIONED 61.39 16 0
10 2 BHK NOT SANCTIONED 59.45 6 0
11 2 BHK 65.86 1 1
12 2 BHK 63.35 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 74
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.2
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 LIBERO WING I 31/12/2025 1 0 1 15 0 10 61
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 65.03 1 1
2 2 BHK 68.28 3 3
3 2 BHK 65.96 2 2
4 2 BHK 68.29 1 1
5 2 BHK 61.38 18 0
6 2 BHK 67.82 3 3
7 2 BHK NOT SANCTIONED 61.38 20 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 74
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.2
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 LIBERO WING J 31/12/2025 1 0 1 15 0 11 99
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 67.82 1 1
2 2 BHK NOT SANCTIONED 59.45 6 0
3 2 BHK 66.24 4 4
4 2 BHK 65.03 1 1
5 2 BHK 67.24 1 1
6 2 BHK 65.8 2 2
7 2 BHK 66.7 1 1
8 2 BHK NOT SANCTIONED 61.39 16 0
9 2 BHK NOT SANCTIONED 63.78 12 0
10 2 BHK 61.39 19 2
11 2 BHK 63.78 13 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 74
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 82.2
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 LIBERO WING G 0 1 0 14 0 20 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK NOT SANCTIONED 79.86 11 0
2 3 BHK NOT SANCTIONED 83.09 13 0
3 3 BHK NOT SANCTIONED 86.58 13 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
HANSAL PARIKH NA Structural Engineer
CHINMAY Y KALE NA Architect

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
LIBERO BOMBAY HIGH COURT AT MUMBAI CIVIL WPST/5852/2018 Civil No Writ Petition 2018 PRE ADMISSION
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other