MahaRERA Application

General Information

Other Than Individual

Organization

HIMALAYA BUILDERS AND DEVELOPERS LLP
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

215
COMMODITY EXCHANGE BUILDING
SECTOR-19
VASHI
VASHI
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

09588129999

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1HIMALAYA COMPLEX BUILDING 7 WING 29 30 31 32ResidentialNA3387.34VILLAGE PASHANE SURVEY NO 148 3A AND 167 VANGANI WEST148/ 3A AND 1674602017-07-312017-04-01
2HIMALAYA COMPLEXResidentialNA3807.83VILLAGE PASHANE SURVEY NO 148 3A AND 167 VANGANI WEST148/ 3A AND 1675722017-07-312017-07-20

Member Information

Member Name Designation Photo
RAJU LAXMAN KOKARE Partner View Photo
JOSEPH PETER SUDHAKAR Authorized Signatory View Photo
JOSEPH PETER SUDHAKAR Partner View Photo
SAMBHAJI ANANTA VEHALE Partner View Photo

Project

HIMALAYA COMPLEX
On-Going Project
31/03/2018
30/09/2018
No
Residential
No
148 3A AND 167
PRAVIN WAGHE SURVEY NO 168 1A 2A 3A
SANDEEP VISHE SURVEY NO 148 A
SANJAY PHARAD SURVEY NO 148 3B
SANDEEP VISHE SURVEY NO 168
MAHARASHTRA
Konkan
Raigarh
Karjat
Pashane
410101
2048.77
4
4
0
1370

FSI Details

0
2048.77
2048.77

Bank Details

AXIS BANK LTD
UTIB0001840

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 22 0 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 WORK DONE
Water Conservation, Rain water Harvesting : NO 0 NA
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 90 IN PROCESS
Aggregate area of recreational Open Space : YES 100 WORK DONE
Open Parking : NO 0 NA
Water Supply : YES 100 WORK DONE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 WORK DONE
Storm Water Drains : YES 100 WORK DONE
Landscaping & Tree Planting : YES 100 WORK DONE
Street Lighting : YES 100 WORK DONE
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 HIMALAYA COMPLEX HIMALAYA COMPLEX WING 6 30/09/2018 0 1 0 3 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK SIZE 2 32.67 1 1
2 1 BHK SIZE 4 35.19 4 4
3 1 BHK SIZE 5 35.61 2 2
4 1 RK SIZE 1 20.26 1 1
5 1RKSIZE2 22.30 3 3
6 1RKSIZE3 23.14 2 2
7 1 BHK SIZE 3 33.08 1 0
8 2 BHK SIZE 1 40.71 1 1
9 1 BHK SIZE 1 30.11 1 0
10 2 BHK SIZE 2 47.47 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 HIMALAYA COMPLEX HIMALAYA COMPLEX WING 8 30/09/2018 0 1 0 3 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK SIZE 1 20.45 2 2
2 1 RK SIZE 2 22.58 4 4
3 1 AND HALF BHK SIZE2 36.47 4 4
4 1 AND HALF BHK SIZE1 31.45 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 HIMALAYA COMPLEX HIMALAYA COMPLEX WING 9 30/09/2018 0 1 0 4 1 0 8
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 22.58 3 3
2 1 BHK 31.41 3 3
3 1 AND HALF BHK SIZE2 37.92 3 2
4 1 AND HALF BHK SIZE1 36.48 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 HIMALAYA COMPLEX HIMALAYA COMPLEX WING 10 30/09/2018 0 1 0 4 1 0 14
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK SIZE 2 32.67 3 3
2 1 BHK SIZE 1 35.55 3 1
3 1 RK SIZE 1 20.45 3 3
4 2BHK 43.22 3 2
5 1 BHK SIZE 3 38.73 3 3
6 1 RK SIZE 2 23.40 6 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AMAR BRIJLAL SINGH NA Contractor
RUSHEEKESH DJAMDHARE NA Contractor
DASHRATH VEHELE NA Contractor
CHANDRAPRATAP R PAL NA Contractor
GIRISH CHANDRA SINGH NA Contractor
RAMAVTAR CHANDU YADAV NA Contractor
B A C PLANNERS AND ENGINEERS PVT LTD NA Architect
B H RATHOD NA Structural Engineer
C M LAD AND ASSOCIATES NA

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other