MahaRERA Application

General Information

Other Than Individual

Organization

Jayshree Builders
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1st Floor
Jugalbaug Compound
LBS Marg
Thane
Opposite ST Workshop
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400601

Organization Contact Details

02225437305
www.mehtagroup.net.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1AMRUT HEAVENResidentialNA4940AMRUT HEAVEN GODREJ HILL KHADAKPADA KALYAN-421301SURVEY NO 4 1 AND 1 1142522011-12-312012-06-30

Member Information

Member Name Designation Photo
Ramesh Amrutlal Mehta Partner View Photo
Jayshree Ramesh Mehta Partner View Photo
Mallika Deepak Mehta Partner View Photo
Alpa Ketan Mehta Partner View Photo
Deepak Ramesh Mehta Authorized Signatory View Photo

Project

LILIUM
On-Going Project
31/12/2020
31/03/2021
No
Residential
No
CTS NO 171 B AND 171 C FINAL PLOT NO 82
LILA NURSERY
KHATAU APARTMENT
NALA
SARSWATI ROAD
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
SARASWATI ROAD
SARASWAT COLONY
400054
1148
1
1
0
174.38

FSI Details

1573.24
1836.32
3409.56

Bank Details

HDFC BANK LTD
HDFC0000146

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 28 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 Yet To Start
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 10 UG FIRE TANK DONE
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Yet To Start
Gymnasium : YES 0 At the completion of the project
Society Office 200 SqFt : YES 0 At the Completion of the project
Aggregate area of recreational Open Space : YES 0 Yet To Start
Open Parking : YES 0 Yet To Start
Water Supply : YES 10 UNDERGROUND WATER TANK DONE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Yet To Start
Storm Water Drains : YES 0 Yet To Start
Landscaping & Tree Planting : YES 0 Yet To Start
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 LILIUM LILIUM 31/12/2020 1 1 0 16 1 0 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 87.9 1 0
2 4BHK 125.09 1 0
3 4BHK 125.83 4 0
4 4BHK 130.3 2 0
5 3BHK 90.12 1 0
6 2BHK 91.32 1 0
7 3BHK 89.3 4 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 61
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 15
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 61
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 43.7

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AMIT MALWADE NA Architect
Epicons Consultants Private Limited NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other