MahaRERA Application

General Information

Other Than Individual

Organization

Mas Creations
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

Plot No 84
C/o Chandan Chaya
Sector 18, PCNTDA
Mahatma Phule Nagar
Near Jijamata park
MAHARASHTRA
Pune
Pune
Shirur
Chinchani
411019

Organization Contact Details

02046703164

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Ambia, in Mahavirs NATURAResidentialNA791.03Survey No 99 MIDC Road Vadgaon Ta- Maval991162011-10-312012-03-31
2Terrain in Mahavirs NATURAResidentialNA1521Survey No 99 MIDC Road Vadgaon Ta Maval Dist Pune991322011-10-312012-03-31

Member Information

Member Name Designation Photo
Minesh Navinchandra Doshi Partner View Photo
Ashok Premchand Bansal Partner View Photo
Sumerchand Tilakchand Agarwal Partner View Photo
Minesh Navinchandra Doshi Authorized Signatory View Photo

Project

Mahavirs NATURA
On-Going Project
31/10/2016
31/12/2018
No
Residential
No
99
Remaining Part of Survey No 99
Remaining Part of Survey No 99
Survey No 100
18 mtrs DP Road
MAHARASHTRA
Pune
Pune
Mawal
Wadagaon (CT)
412106
3969
2
2
0
1174.10

FSI Details

2399.84
9721.49
12121.33

Bank Details

HDFC Bank Ltd
HDFC0001795

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 45 20 84.

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Concrete Road
Water Conservation, Rain water Harvesting : YES 80 Pending for D1 Building
Energy management : YES 80 Pending for D1 Building
Fire Protection And Fire Safety Requirements : YES 100 Done
Electrical Meter Room, Sub-Station, Receiving Station : YES 70 Done except D1 Building
Aggregate area of recreational Open Space : YES 60 Partly Done
Open Parking : YES 70 Partly Done
Water Supply : YES 100 WTP Installed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 STP is Operational
Storm Water Drains : YES 100 Done
Landscaping & Tree Planting : YES 100 Done
Street Lighting : YES 100 Done
Community Buildings : YES 10 Work in Progress
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Done
Solid Waste Management And Disposal : YES 0 Yet to implement

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Mahavirs NATURA STREAM C1 0 1 0 6 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 34.8 9 9
2 1BHK 33.57 9 9
3 1BHK 30.35 5 5
4 1BHK 33.72 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Mahavirs NATURA SPACIA D1 0 1 0 12 1 62 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 32.40 1 1
2 1BHK 32.42 1 1
3 1BHK 33.61 1 1
4 1BHK 33.05 1 0
5 2BHK 48.84 9 4
6 2BHK 49.73 1 0
7 2BHK 50 1 0
8 3BHK 58.74 1 1
9 3BHK 59.30 1 1
10 3BHK 59.55 1 1
11 3BHK 64.57 1 1
12 SHOP1 26.10 1 0
13 SHOP2 25.82 1 0
14 SHOP3 25.92 1 0
15 1BHK 35.14 1 0
16 1BHK 34.77 1 0
17 2BHK 41.92 1 0
18 2BHK 42.61 1 0
19 2BHK 42.73 9 4
20 2BHK 43.27 8 4
21 2BHK 46.52 23 7
22 2BHK 47.10 11 3
23 2BHK 47.41 8 3
24 2BHK 47.71 3 0
25 2BHK 47.82 9 2
26 2BHK 48.19 9 4
27 2BHK 48.57 7 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

30
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 55

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Ganesh B Deshmukh NA Engineer
Niranjan B Chougule NA Engineer
Ar Yusuf DEVASWALA NA Architect
SOFT CORNER MARKETING SERVICES A51700000654 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other