MahaRERA Application

General Information

Other Than Individual

Organization

PRIME CONSTRUCTION
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

133
AMAN RESIDENCY
TELANGI PACCHHA PETH
JOD BASAVANNA CHOWK
NEAR UPAHAR BEKARI
MAHARASHTRA
Pune
Solapur
Solapur North
Solapur (M Corp.)
413005

Organization Contact Details

02172729235

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1ASQA RESIDENCYResidentialNA229.53100 TELANGI PACCHHA PETH SOLAPUR10380/100112015-12-312015-09-30

Member Information

Member Name Designation Photo
FAROOQUE ISMAIL MUJAWAR Partner View Photo
RAJSHEKHAR PARANNA BHINGE Authorized Signatory View Photo
SADIQUE ISMAIL MUJAWAR Partner View Photo
ASHFAQUE ISMAIL MUJAWAR Partner View Photo

Project

PRIME RESIDENCY
On-Going Project
30/06/2018
30/06/2018
No
Residential
No
9911
CTS NO 9912
ROAD
ROAD
ROAD
MAHARASHTRA
Pune
Solapur
Solapur North
Solapur (M Corp.)
413002
253.3
1
1
0
0.00

FSI Details

0.00
541.17
541.17

Bank Details

AXIS BANK
UTIB0001723

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 2 0 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 WILL BE DONE AT THE TIME OF COMPLETION
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 WILL BE DONE AT THE TIME OF COMPLETION
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 WILL BE DONE AT THE TIME OF COMPLETION
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 AVAILABLE FROM MUNICIPAL CORPORATION AND BORE WELL
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AVAILABLE TO CORPORATION LINE
Storm Water Drains : NO 0 NA
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 PRIME RESIDENCY PRIME RESIDENCY 30/06/2018 1 1 0 6 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 OFFICE NO 102 29.79 1 0
2 OFFICE NO 103 23.20 1 0
3 OFFICE NO 104 20.35 1 0
4 FLAT NO 201 83.43 1 0
5 SHOP NO 1 13.47 1 1
6 SHOP NO 2 13.23 1 0
7 SHOP NO 3 25.53 1 0
8 FLAT NO 202 71.54 1 0
9 FLAT NO 301 82.44 1 1
10 FLAT NO 302 66.05 1 0
11 FLAT NO 401 82.23 1 1
12 FLAT NO 402 65.22 1 0
13 SHOP NO 4 22.02 1 0
14 HALL NO 101 49.23 1 0
15 FLAT NO 501 56.03 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
MUJAWAR CONSTRUCTION NA Contractor
IRFAAN MUSA SHAIKH NA Contractor
ELEMENT ARCHITECTS NA Architect
SAWALI CONSULTANT NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other