MahaRERA Application

General Information

Other Than Individual

Organization

Ankit Enterprises
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

2nd Floor
City Point
Dhole Patil Road
Pune
17 Boat Club Road
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411001

Organization Contact Details

02066226500

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Hills and Dales III ElburzResidentialNA128600S No 13 P 14 P 15 P 19 P Tal Haveli Dist PuneS No 13 P 14 P 15 P 19 P Tal Haveli Dist Pune61682011-07-312011-07-14
2Hills and Dales III AlluraResidentialNA128600S No 13 P 14 P 15 P 19 P Tal Haveli Dist PuneS No 13 P 14 P 15 P 19 P Tal Haveli Dist Pune11402014-01-312014-01-31
3Hills and Dales III GlamoreResidentialNA130100S No 13 P 14 P 15 P 19 P Tal Haveli Dist PuneS No 13 P 14 P 15 P 19 P Tal Haveli Dist Pune11402016-04-302016-04-26

Member Information

Member Name Designation Photo
Krushna Mahajan Authorized Signatory View Photo

Project

Centria
New Project
31/10/2021
Yes
Residential
No
13 Part, 14 Part, 15 Part, 19 Part
Survey No 19 Part
15 Mtr wide Road and S No 8 Part
Survey No 11 Part
Survey No 15 Part
MAHARASHTRA
Pune
Pune
Haveli
UNDRI
Undri
Pune
411060
5999.34
4
2
2
13887.81

FSI Details

0
20471.80
20471.80

Bank Details

ICICI Bank Limited
ICIC0000005

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 239 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Yet to be started
Water Conservation, Rain water Harvesting : YES 0 Yet to be started
Energy management : YES 0 Yet to be started
Fire Protection And Fire Safety Requirements : YES 0 Yet to be started
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Yet to be started
Aggregate area of recreational Open Space : YES 0 Yet to be started
Open Parking : YES 0 Yet to be started
Water Supply : YES 0 Yet to be started
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Yet to be started
Storm Water Drains : YES 0 Yet to be started
Landscaping & Tree Planting : YES 0 Yet to be started
Street Lighting : YES 0 Yet to be started
Community Buildings : YES 0 Yet to be started
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Yet to be started
Solid Waste Management And Disposal : YES 0 Yet to be started

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Centria Building P - Floor 01 to 10 31/10/2021 1 1 1 10 0 7 119
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 92.49 1 0
2 3 BHK 97.30 1 0
3 3 BHK 98.68 1 0
4 3 BHK 105.61 1 0
5 3 BHK 105.78 1 0
6 3 BHK 105.80 9 0
7 3 BHK 106.11 1 0
8 3 BHK 105.84 9 1
9 3 BHK 106.15 1 1
10 3 BHK 105.30 8 5
11 3 BHK 105.48 9 1
12 3 BHK 92.32 9 1
13 3 BHK 97.13 8 6
14 3 BHK 93.63 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 12
5 X number of Slabs of Super Structure 23
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 33.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Centria Building P - Proposed Floor 11 to 13 31/10/2021 0 0 0 3 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 98.68 1 0
2 3BHK 102.5 1 0
3 3BHK 105.3 2 0
4 3BHK 105.48 3 0
5 3BHK 105.8 3 0
6 3BHK 105.84 3 0
7 3BHK 105.93 3 0
8 3BHK 106 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 30
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Centria Building Q - Floor 01 to 10 31/10/2021 1 1 1 10 0 7 120
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 101.18 1 0
2 3 BHK 102.08 1 0
3 3 BHK 105.64 9 0
4 3 BHK 105.97 1 0
5 3 BHK 106.28 1 0
6 3 BHK 105.89 1 1
7 3 BHK 105.06 1 1
8 3 BHK 105.96 8 2
9 3 BHK 106.03 1 1
10 3 BHK 108.09 1 1
11 3 BHK 99.33 1 1
12 3 BHK 104.75 9 2
13 3 BHK 105.58 8 2
14 3 BHK 105.72 9 0
15 3 BHK 107.78 8 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 15
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Centria Building Q - Proposed Floor 11 to 13 31/10/2021 0 0 0 3 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 101.18 1 0
2 3BHK 102.08 1 0
3 3BHK 104.75 3 0
4 3BHK 105.64 3 0
5 3BHK 105.72 3 0
6 3BHK 105.96 2 0
7 3BHK 105.97 1 0
8 3BHK 105.78 2 0
9 3BHK 105.58 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 30

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
PROPBUYING REALTORS PVT LTD A52100000476 Real Estate Agent
Rohit Rajendra Sawant A52100000600 Real Estate Agent
Shakruddin Mujawar A52100000742 Real Estate Agent
Lalitkumar Chhaganlal Jain A52100001922 Real Estate Agent
Satish Mane NA Architect
JW Consultant LLP NA Structural Engineer
Anis Shergadwala A52100004465 Real Estate Agent
Makaan Hunt Pvt Ltd A52100000430 Real Estate Agent
Sunny Santosh Chinchane A52100014204 Real Estate Agent
Bindu Ludovico D Silva A52100000817 Real Estate Agent
HUSAIN KUTUBUDDIN KHUMANPURWALA A52100000789 Real Estate Agent
NITIN SHANKAR KADDE A52100000577 Real Estate Agent
Shabbir Nabilal Shaikh A52100001439 Real Estate Agent
Anupam Vinodkumar Gadodia A52100003713 Real Estate Agent
sayed Ali Arabian A52100001163 Real Estate Agent
SWAPNIL DEVIDAS BHAVSAR A52100004917 Real Estate Agent
Charudatta Satish Lakhamade A52100001152 Real Estate Agent
PROPERTY CHEF CONSULTING SERVICES A52100000044 Real Estate Agent
Saghher Jhalaani A52100002474 Real Estate Agent
Yezdi Sorabji Mogal A52100002499 Real Estate Agent
Relaint infraspace Realty A52100008910 Real Estate Agent
Addressofchoice Realty Pvt Ltd A52100000116 Real Estate Agent
Milan Madhukar Nikhal A52100003066 Real Estate Agent
PRASHANT SHAHURAO LANDE A52100008324 Real Estate Agent
amit bhutani A52100002436 Real Estate Agent
FLATONS ADVISORS A52100004415 Real Estate Agent
CHIRAG SHARAD SHAH A52100013950 Real Estate Agent
Farhan Chaudhary A52100000244 Real Estate Agent
MANMOHAN R VERMA A52100007469 Real Estate Agent
Avisek Mukherjee A52100009465 Real Estate Agent
SURESH ABHAYRAJ YADAV A52100001894 Real Estate Agent
RICHARD SUBHASH HASNALY A52100003512 Real Estate Agent
Pooja Saxena A52100003130 Real Estate Agent
Dhruba Prasad Gupta A52100010221 Real Estate Agent
Rohit Dilip Kawade A52100005606 Real Estate Agent
KUMAR GAURAV SINGH A52100013994 Real Estate Agent
Manan Rohit Raja A52100003147 Real Estate Agent
SMC REAL ESTATE ADVISORS PRIVATE LIMITED A51900000042 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Centria C J Sr Div Pune Gaware Court RCS No 1340 Civil No Suit 2016 Unready Board
NA
Centria CJSD Spl CS 1441/2018 Civil No Suit 2018 Issues
NA
Centria District Court Pune 88/2019 Others No Appeal 2019 Filing of say
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other