MahaRERA Application

General Information

Other Than Individual

Organization

RSN BALAJI REALTORS P LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

101 1ST FLOOR
VAIBHAV HEIGHTS B WINGS
SHIVAJI NAGAR
VAKOLA
NEAR JAIN TEMPLE
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400055

Organization Contact Details

02226691324

Past Experience Details

Member Information

Member Name Designation Photo
MITHALAL MOOLCHAND JAIN Managing Director View Photo
KAMLESH MITHALAL JAIN Authorized Signatory View Photo

Project

VAIBHAV HEIGHTS
On-Going Project
31/12/2017
31/12/2018
31/12/2019
No
Residential
No
3929 TO 3949
ROAD
D P ROAD
CTS NO 3928
CTS NO 7627
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
SHIVAJI NAGAR ROAD
NEAR JAIN MANDIR
400055
1387.48
2
2
0
202.42

FSI Details

521
3588.85
4109.85

Bank Details

BANK OF BARODA
BARB0SANWES

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 39 18 23

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 WIP
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 90 WIP
Electrical Meter Room, Sub-Station, Receiving Station : YES 80 WIP
Aggregate area of recreational Open Space : YES 0 AS PER APPROVED PLAN
Open Parking : NO 0 NA
Water Supply : YES 60 WIP
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 90 WIP
Storm Water Drains : YES 60 WIP
Landscaping & Tree Planting : YES 0 WIP
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 VAIBHAV HEIGHTS A WING CHOKSI APARTMENT 31/12/2018 0 1 0 15 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 MULTIPURPOSEROOM 24.75 4 4
2 MULTIPURPOSEROOM 16.46 30 27
3 MULTIPURPOSEROOM 28.94 8 6
4 MULTIPURPOSEROOM 19.07 16 14
5 MULTIPURPOSEROOM 21.86 11 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 81
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 VAIBHAV HEIGHTS B WING VAIBHAV HEIGHTS 31/12/2019 0 1 0 14 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 46.25 11 6
2 SHOP NO 1 24.09 1 1
3 SHOP NO 2 24.09 1 1
4 3 BHK 85.70 1 0
5 2 BHK 61.46 24 15
6 SHOP NO 3 23.37 1 1
7 SHOP NO 4 21.84 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
H B GAUD & SONS NA Contractor
SYNERGY ARCHITECH NA Architect
FRAMES NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other