MahaRERA Application

General Information

Other Than Individual

Organization

Sai Proviso Homes
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1201/1301
Bhumiraj Costarica
sector 18, plot no 1 & 2
Sanpada
Palm Beach road
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02266766676

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Galaxy NebulaResidentialNA2650.06Plot No. 220 and 221 Sector - 10 Kharghar Navi Mumbai.220 and 2212802013-06-302013-07-12
2Galaxy OrionCommercialNA2699.55Plot No. 50A Sector -35D Kharghar Navi Mumbai50A2932013-12-312013-07-25
3Galaxy CarinaOthersResidential cum Commercial 2781.79Plot No. 10 Sector 15 Kharghar Navi Mumbai101892015-12-312015-05-21
4Proviso HeightsOthersResidential cum Commercial3699.68Plot No.179 Sector 17 Ulwe17931352016-06-302016-05-31
5Proviso CornerOthersResidential cum Commercial1749.83Plot No.224 Sector 23 Ulwe2241622016-06-302016-08-22
6Proviso ComplexOthersResidential cum Commercial4770.91Plot no. 5 6 7 Sector 35E Kharghar Navi Mumbai5 6 7 31592014-09-302013-07-18

Member Information

Member Name Designation Photo
Sanjay Motilal Gawande Partner View Photo
Ruchin Gupta Authorized Signatory View Photo
Brij Mohan Achru Gupta Partner View Photo
Sai Skyway Realty LLP Partner View Photo
Sai Sapphire Builders and Developers LLP Partner View Photo

Project

Leisure Town Phase 1
On-Going Project
31/12/2020
31/12/2021
No
Residential
Yes
202/A, 202/B/1/1 to 7, 202/B/2, 202/B/3, 202/B/4
Sade Satra Nali Road
proposed RP road and Amanora Township
proposed RP road and Amanora Township
PMC Road
MAHARASHTRA
Pune
Pune
Haveli
Hadapsar
411028
20831.09
6
6
0
8502.47

FSI Details

3612
28438.59
32050.59

Bank Details

Kotak Mahindra Bank Ltd
KKBK0001752

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Leisure Town Phase 1 Tupe Developers Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 738 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 00 Not yet started
Water Conservation, Rain water Harvesting : YES 00 Not yet started
Energy management : YES 00 Not yet started
Fire Protection And Fire Safety Requirements : YES 50 Equipment installation pending
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 Meter Installation pending
Aggregate area of recreational Open Space : YES 00 Not yet started
Open Parking : NO 0 NA
Water Supply : YES 50 Borewell
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 00 Not yet started
Storm Water Drains : YES 00 Not yet started
Landscaping & Tree Planting : YES 00 Not yet started
Street Lighting : YES 00 Not yet started
Community Buildings : YES 85 Electrical and painting work is pending
Treatment And Disposal Of Sewage And Sullage Water : YES 00 Not yet started
Solid Waste Management And Disposal : YES 00 Not yet started

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Leisure Town Phase 1 A1 31/12/2021 0 1 0 12 1 0 122
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 bhk 51.28 19 19
2 3 bhk 71.17 24 17
3 3 bhk 71.45 20 10
4 2bhk 51.44 24 24
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 00
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
11 Overall Percentage of Completion of the work done For the entire Building /Wing 69.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Leisure Town Phase 1 D3 31/12/2021 0 1 0 12 1 0 78
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 bhk 29.41 86 82
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 00
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Leisure Town Phase 1 B1 31/12/2021 0 1 0 14 1 0 122
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2bhk 48.8 19 11
2 2 bhk 49.06 24 12
3 2 bhk 50.7 24 14
4 2bhk 50.19 20 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 00
4 Stilt Floor 100
5 X number of Slabs of Super Structure 60
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 15
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

00
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00
11 Overall Percentage of Completion of the work done For the entire Building /Wing 43.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Leisure Town Phase 1 B3 31/12/2021 0 1 0 14 1 0 122
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 bhk 49.06 24 10
2 2bhk 48.8 19 8
3 2bhk 50.7 24 22
4 2bhk 50.19 20 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 00
4 Stilt Floor 100
5 X number of Slabs of Super Structure 40
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

00
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 Leisure Town Phase 1 J1 31/12/2021 0 1 0 14 1 0 140
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 bhk 49.94 19 6
2 2 bhk 50.31 24 6
3 3bhk 66.33 20 10
4 3bhk 66.11 24 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 00
3 X number of Podiums 00
4 Stilt Floor 00
5 X number of Slabs of Super Structure 8
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 00
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 8
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

00
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00
11 Overall Percentage of Completion of the work done For the entire Building /Wing 11.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 Leisure Town Phase 1 C1 31/12/2021 0 1 0 14 1 0 128
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2bhk 52.61 12 0
2 2bhk 52.27 9 0
3 2 bhk 48.62 24 0
4 2 bhk 49.44 12 0
5 2bhk 47.9 20 0
6 2 bhk 49.23 10 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 00
3 X number of Podiums 00
4 Stilt Floor 00
5 X number of Slabs of Super Structure 00
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 00
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 00
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

00
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Deshpande Dixit and associates NA Architect
GA Bhilare consultants pvt ltd NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other