MahaRERA Application

General Information

Other Than Individual

Organization

SHRUSHTI DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

GUT NO. 123 & 18
SHRUSTI DEVELOPERS
VALIVALI
BARVI DAM ROAD
BADLAPUR (W)
MAHARASHTRA
Konkan
Thane
Ambarnath
Badlapur (M Cl)
421503

Organization Contact Details

91766393783

Past Experience Details

Member Information

Member Name Designation Photo
NARSINHBHAI VELJIBHAI PATEL Partner View Photo
ARVINDKUMAR CHHAGANBHAI PATEL Partner View Photo
MAYANK ARVINDBHAI PATEL Partner View Photo
SHAILESHKUMAR DHIRAJBHAI PATEL Partner View Photo
PARESH LALJI RUDANI Partner View Photo
DHAVAL ARVINDBHAI PATEL Authorized Signatory View Photo
DHAVAL ARVINDBHAI PATEL Partner View Photo

Project

SHRUSHTI PRARAMBH
New Project
31/12/2021
No
Others
Yes
SURVEY NO.5 HISSA NO.3/3
SURVEY NO 7A-2-1
6 MTR WIDE ROAD AND HISSA NO 3-2
HISSA NO 2 AND HISSA NO 3-3
6 MTR WIDE INTERNAL ACCESS ROAD AND HISSA NO 4
MAHARASHTRA
Konkan
Thane
Ambarnath
Badlapur (M Cl)
SURVEY NO.5/3/3, BELAVALI
BADLAPUR
421503
2900
3
3
0
0

FSI Details

00
3478.11
3478.11

Bank Details

ICICI BANK LTD
ICIC0001030

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SHRUSHTI PRARAMBH RAMESH HARISHCHANDRA KARALE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SHRUSHTI PRARAMBH SUDAM HARISHCHANDRA KARALE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 33 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 NOT STARTED. WILL BE PROVIDED AS PER KBMC NORMS
Water Conservation, Rain water Harvesting : NO 0 NA
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 NOT STARTED. WILL BE PROVIDED AS PER KBMC NORMS
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 NOT STARTED. WILL BE PROVIDED AS PER KBMC NORMS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 NOT STARTED. WILL BE PROVIDED AS PER KBMC NORMS
Storm Water Drains : YES 0 NOT STARTED. WILL BE PROVIDED AS PER KBMC NORMS
Landscaping & Tree Planting : YES 0 NOT STARTED. WILL BE PROVIDED AS PER KBMC NORMS
Street Lighting : YES 0 NOT STARTED. WILL BE PROVIDED AS PER KBMC NORMS
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 SHRUSHTI PRARAMBH WING - A 31/12/2021 0 1 0 5 0 0 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 8.20 1 0
2 SHOP 8.58 1 0
3 SHOP 9.44 1 0
4 SHOP 9.68 1 0
5 SHOP 9.98 1 0
6 SHOP 10.07 2 0
7 SHOP 10.18 1 0
8 SHOP 10.43 1 0
9 1 BHK 27.21 1 0
10 1 BHK 29.84 1 0
11 2 BHK 40.14 4 0
12 SHOP 9.99 6 1
13 1.5 BHK 30.25 3 1
14 1 BHK 27.02 4 4
15 1 BHK 28.21 4 3
16 1 BHK 31.86 2 1
17 2 BHK 37.15 3 1
18 2 BHK 38.12 4 2
19 2 BHK 39.73 6 3
20 2 BHK 41.38 4 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 20
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 00
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 SHRUSHTI PRARAMBH WING - B 31/12/2021 0 1 0 5 0 0 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 18.47 1 0
2 1 RK 18.52 4 0
3 1 RK 18.54 1 0
4 1 BHK 26.38 6 4
5 1 BHK 26.45 2 0
6 1 BHK 26.47 1 0
7 1 BHK 26.52 12 1
8 1 RK 18.45 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 00
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 SHRUSHTI PRARAMBH WING - C 31/12/2021 0 1 0 5 0 0 3
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 18.84 1 0
2 1 RK 18.90 1 0
3 1 RK 20.29 1 0
4 1 BHK 26.79 1 0
5 1 BHK 26.83 2 0
6 1 BHK 28.17 1 0
7 1 BHK 28.22 2 0
8 1 BHK 26.81 3 1
9 1 BHK 28.24 1 1
10 1 BHK 28.27 1 1
11 1 RK 16.92 1 1
12 1 RK 17.17 2 2
13 1 RK 17.18 6 3
14 1 RK 17.26 1 1
15 1 RK 17.32 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 52

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
MEERA ENTERPRISES throgh Partner KAPIL LALJI RUDANI NA Contractor
K R PATEL & ASSOCIATES NA Structural Engineer
Piyush C Parvadiya NA
DESTINATION ARCHITECTURE INTERIOR DESIGNS NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other