MahaRERA Application

General Information

Other Than Individual

Organization

Shantee Housing
Partnership
NA
Do you have any Past Experience ?
No

Address Details

ground floor
shreenath bhavan
60ft road
KT village
near indu hospital
MAHARASHTRA
Konkan
Palghar
Vasai
Vasai-Virar City (M Corp)
401202

Organization Contact Details

02502331171

Past Experience Details

Member Information

Member Name Designation Photo
niyaz abdul samad pathan Partner View Photo
Raaz abdul samad pathan Authorized Signatory View Photo

Project

SARGAM RESIDENCY
New Project
31/12/2021
No
Others
Yes
S.NO. 121 H.NO. 4,5,6 S.NO. 119 H.NO. 4
OPEN SPACE
ROAD
BUNGLOW
OPEN SPACE
MAHARASHTRA
Konkan
Palghar
Vasai
Chandrapada
Jhuchandra-Bapane Road
NAIGAON
401208
7640
3
3
0
0

FSI Details

5836
2664.31
8500.31

Bank Details

THE COSMOS CO-OP BANK LTD
COSB0000116

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SARGAM RESIDENCY GOPIKISAN GOPINATH PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 27 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 WIP
Water Conservation, Rain water Harvesting : YES 0 WIP
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 WIP Bldg 01
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WIP Sub-Station & Receiving Station Not Applicable
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 AS APPLICABLE
Water Supply : YES 0 BOREWEL
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WIP
Storm Water Drains : YES 0 WIP
Landscaping & Tree Planting : YES 0 WIP
Street Lighting : YES 0 WIP
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 0 ON POSSESION

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 SARGAM RESIDENCY SARGAM RESIDENCY BLDG NO 1 31/12/2021 0 1 0 15 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 41.85 14 6
2 2BHK 44.19 13 3
3 1RK 19.73 42 20
4 SHOP 150.86 11 1
5 1BHK 29.22 85 37
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 46
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 SARGAM RESIDENCY SARGAM RESIDENCY BLDG NO 2 31/08/2020 0 1 0 5 1 0 6
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 43.02 4 2
2 1BHK 29.22 10 8
3 1RK 24.33 5 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 15
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 SARGAM RESIDENCY SARGAM RESIDENCY BLDG NO 3 31/08/2020 0 1 0 5 1 0 3
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1RK 26.67 1 0
2 1BHK 102.84 4 0
3 1RK 64.88 4 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Sanjay Maloo & Associates NA Architect
Jay Shree Krishna Consulting Engineer NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other