MahaRERA Application

General Information

Other Than Individual

Organization

Arvel Developers
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Shop no -5
Swastik
Temhode Road
Girish Nagar
Nea to Holly Spirit School
MAHARASHTRA
Konkan
Palghar
Palghar
Palghar
401404

Organization Contact Details

02525659444

Past Experience Details

Member Information

Member Name Designation Photo
Rajiv Janardan Patil Authorized Signatory View Photo
Shialesh Jayantilal Bafna Partner View Photo
Heena Rakesh Shah Partner View Photo
Nipa Jainendra Shah Partner View Photo
Sanjay Babulal Ladhani Partner View Photo
Vijay Babulal Ladhani Partner View Photo

Project

PALM SPRINGS PHASE - I
New Project
31/12/2022
No
Residential
Yes
446, 447, 447/3, 447/4, 447/5
445
446
PALGHAR-MAHIM ROAD
436
MAHARASHTRA
Konkan
Palghar
Palghar
palghar
ALIYALI VILLAGE
401404
5844.76
10
10
0
540.60

FSI Details

0.00
5746.71
5746.71

Bank Details

VASAI VIKAS SAHKARI BANK LTD
VVSB0000005

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
PALM SPRINGS PHASE - I ARVEL DEVELOPERS Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Upload Agreement / MoU Copy
13 Upload Agreement / MoU Copy
14 Upload Agreement / MoU Copy
15 Upload Agreement / MoU Copy
16 Upload Agreement / MoU Copy
17 Upload Agreement / MoU Copy
18 Upload Agreement / MoU Copy
19 Upload Agreement / MoU Copy
20 Upload Agreement / MoU Copy
21 Upload Agreement / MoU Copy
22 Upload Agreement / MoU Copy
23 Upload Agreement / MoU Copy
24 Upload Agreement / MoU Copy
25 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 9 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 WBM
Water Conservation, Rain water Harvesting : YES 0 RAIN WATER HARWESTING
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 PROVISION
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 MSEB
Aggregate area of recreational Open Space : YES 0 GARDEN
Open Parking : NO 0 NA
Water Supply : YES 0 BORE WELL
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 SEPTIC TANK
Storm Water Drains : YES 0 RCC GUTTER
Landscaping & Tree Planting : YES 0 TREE PLANTATION
Street Lighting : YES 0 STREET LIGHTS
Community Buildings : YES 0 CLUB HOUSE
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 PALM SPRINGS PHASE - I C-TYPE BUILDING 31/12/2022 0 1 0 8 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 39.84 30 0
2 2 BHK a 65.62 15 0
3 2 BHK b 60.74 15 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 80
2 X number of Basement(s) and Plinth 30
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 11
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 PALM SPRINGS PHASE - I TYPE D BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE D BUNGLOW 182.97 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 PALM SPRINGS PHASE - I TYPE E8 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E BUNGLOW 133.64 8 0
2 TYPE E BUNGLOW 1069.18 8 0
3 TYPE E1 BUNGLOW 133.64 1 0
4 TYPE E2 BUNGLOW 133.64 1 0
5 TYPE E3 BUNGLOW 133.64 1 0
6 TYPE E4 BUNGLOW 133.64 1 0
7 TYPE E5 BUNGLOW 133.64 1 0
8 TYPE E6 BUNGLOW 133.64 1 0
9 TYPE E7 BUNGLOW 133.64 1 0
10 TYPE E8 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 PALM SPRINGS PHASE - I TYPE E1 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E1 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 PALM SPRINGS PHASE - I TYPE E2 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E2 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 00
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 PALM SPRINGS PHASE - I TYPE E3 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E3 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 PALM SPRINGS PHASE - I TYPE E4 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E4 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 PALM SPRINGS PHASE - I TYPE E5 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E5 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 40
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 PALM SPRINGS PHASE - I TYPE E6 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E6 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 40
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 PALM SPRINGS PHASE - I TYPE E7 BUNGLOW 31/12/2022 0 1 0 2 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 TYPE E7 BUNGLOW 133.64 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 90
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 40
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 30
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
YOGESH MAHTRE NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other