MAHA-RERA Application

General Information

Other Than Individual

Organization

Oberoi Constructions Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

3rd Floor,
Commerz
International Business Park, Oberoi Garden City
Goregaon (E)
Oberoi Garden City
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400063

Organization Contact Details

02266773333
www.oberoirealty.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Grande Splendor ComplexResidentialNA1043.29Grande Splendor Complex JVLR Jogeshwari East Mumbai 4000601/B pt of Village Majas11572014-01-312013-09-21

Member Information

Member Name Designation Photo
Rajesh Gaonkar Authorized Signatory View Photo
Rajendra Chandorkar Authorized Signatory View Photo
Saumil Daru Authorized Signatory View Photo

Project

Eternia Towers A to D
On-Going Project
31/03/2021
31/12/2021
Yes
Residential
No
CTS No 543 pt of Village Nahur
CTS No 543 pt of Village Nahur
CTS No 543 pt of Village Nahur
CTS No 543 pt of Village Nahur
CTS No 543 pt of Village Nahur
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400080
3367.08
4
4
0
0

FSI Details

100438
51562.88
152000.88

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) NA NA 0
Covered Parking ( In Numbers) 3335 NA 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Will be provided
Water Supply : YES 0 Will be provided
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Will be provided
Storm Water Drains : YES 0 Will be provided
Landscaping & Tree Planting : YES 0 Will be provided
Street Lighting : YES 0 Will be provided
Open Parking : NO 0 NA
Community Buildings : YES 0 Common Clubhouse for all residential development
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Will be provided
Solid Waste Management And Disposal : YES 0 Will be provided
Ground floor and 1st floor of Tower D is below actual ground level : YES 0 Due to natural topography of Larger Property
Water Conservation, Rain water Harvesting : YES 0 Will be provided
Energy management : YES 0 Will be provided
Fire Protection And Fire Safety Requirements : YES 0 Will be provided
Prop Public Parking to be handed over to MCGM at any location in LargerProperty incl under RE Proj : YES 0 Approval in process
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Will be provided as necessary
Aggregate area of recreational Open Space : YES 0 To be provided as per provisions of DCR
Ground Floor of Tower C is below actual ground level : YES 0 Due to natural topography of Larger Property

Building Details

Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Eternia Towers A to D Tower A 3 1 8 66 2 0 850
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK Supreme Zone 1 84.80 42 24
2 3BHK Supreme Zone 2 86.66 60 0
3 3BHK Luxury Zone 1 97.53 102 52
4 3BHK Luxury Zone 2 101.43 136 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 95
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 24.5
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Eternia Towers A to D Tower B 3 1 8 66 2 0 843
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK Supreme Zone 1 84.80 44 23
2 3BHK Supreme Zone 2 86.66 63 0
3 3BHK Luxury Zone 1 97.53 86 58
4 3BHK Luxury Zone 2 101.43 136 0
5 3BHK Luxury Ext 111.90 7 0
6 3BHKLuxuryTerraceApt 98.67 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 25
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Eternia Towers A to D Tower C 1 1 10 66 2 0 810
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK Supreme Zone 1 84.80 40 23
2 3BHK Supreme Zone 2 86.66 58 0
3 3BHK Luxury Zone 1 97.53 82 56
4 3BHK Luxury Zone 2 101.43 136 0
5 3BHK Luxury Ext 111.90 7 0
6 3BHKLuxuryTerraceApt 98.67 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 1
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 25.1
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Eternia Towers A to D Tower D 1 1 10 66 2 0 832
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK Supreme Zone 1 84.80 41 18
2 3BHK Supreme Zone 2 86.66 62 0
3 3BHK Luxury Zone 1 97.53 94 42
4 3BHK Luxury Zone 2 101.43 136 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 2
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20.2

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Larsen & Toubro Limited (Civil Contractor) NA Contractor
Architect Sunil Arora NA Architect
Leslie E. Robertson Associates Consulting Engineers (India) Pvt Ltd NA Structural Engineer
Ted Jacob  Engineering Group NA Other
Rowan Williams Davies & Irwin, Inc. NA Other
Langan International, LLC NA Other
Walker Parking Consultants NA Other
Fortune Consultants Ltd. (FCL) NA Other
En3 Sustainability Solutions Pvt. Ltd. NA Other
A.A. Nayak Constructions Pvt. Ltd. NA Other
MEP and Fire Fighting Contractor (To be appointed) NA Other
Façade Consultant (To be appointed) NA Other
Elevators Contractor (To be appointed) NA Other
Windows Contractor (To be appointed) NA Other

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Eternia Towers A to D Bombay High Court PIL No 48 Civil No Writ Petition 2017 Pending
NA

Uploaded Documents

Document Name Uploaded Document
Declaration in FORM B
Details of encumbrances
Commencement Certificates
Building Plan Approval (IOD)
Copy of the legal title report
Proforma of the allotment letter and agreement for sale
Other
Copy of Layout Approval (in case of layout)