MahaRERA Application

General Information

Other Than Individual

Organization

SAI ESSEN PROPERTIES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

ABC CLASSIC
G BLOCK
TELCO ROAD
CHINCHWAD
MIDC, THERMAX CHOWK
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
411019

Organization Contact Details

02027481199
www.aishwaryam.net

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1AISHWARYAM COURTYARD PHASE IResidentialNA11162.84Newale vasti Chikhli Vitthal Nagar Pune 412114GAT NO 1169, 117083362012-06-302012-10-31
2Aishwaryam MelodyResidentialNA4922.44Plot No 3 Sector No 32A Ravet PCMC Pune 411033Plot no 3, Sector No 32A2842015-03-312016-03-31

Member Information

Member Name Designation Photo
SURENDRA BHIMSEN AGARWAL Partner View Photo
DEEPAK ASHOK MANE Partner View Photo
ASHOK RAGHUNATH MANE Partner View Photo
NARENDRA BHIMSEN AGARWAL Authorized Signatory View Photo
NARENDRA BHIMSEN AGARWAL Partner View Photo

Project

AISHWARYAM COURTYARD II
On-Going Project
31/03/2020
31/03/2020
Yes
Residential
No
GAT NO 1169 1170 1171 1172 AND 1241
BY GAT NO 1173
BY GAT NO 1240 1243
green belt
BY PHASE I OF THE PROJECT GAT NO 1173 and 1242
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
AKURDI-CHIKHALI ROAD
CHIKHALI
412114
20126.28
6
5
1
1882.95

FSI Details

6990.94
21703.03
28693.97

Bank Details

HDFC BANK
HDFC0000185

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 409 158 70

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 -
Water Conservation, Rain water Harvesting : YES 0 -
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 -
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 -
Aggregate area of recreational Open Space : YES 0 -
Open Parking : YES 0 -
Water Supply : YES 0 -
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 90 STP
Storm Water Drains : YES 0 -
Landscaping & Tree Planting : YES 0 -
Street Lighting : YES 0 -
Community Buildings : YES 0 -
Treatment And Disposal Of Sewage And Sullage Water : YES 0 -
Solid Waste Management And Disposal : YES 0 -

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 AISHWARYAM COURTYARD II A 31/03/2020 0 1 1 16 0 17 90
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 77.06 1 1
2 1 RK 25.92 1 0
3 2BHK 47.17 2 2
4 2BHK 49.13 13 11
5 2BHK 51.17 4 3
6 2BHK 47.63 26 17
7 2BHK 48.68 13 9
8 2BHK 50.26 47 37
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 70
4 Stilt Floor 0
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 65
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 51.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 AISHWARYAM COURTYARD II B 31/03/2020 0 1 1 16 0 15 93
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 45.67 12 11
2 2BHK 45.51 1 1
3 2BHK 48.43 12 10
4 2BHK 45.48 12 11
5 2BHK 45.49 5 4
6 2BHK 45.33 2 2
7 2BHK 51.55 12 7
8 2BHK 48.59 12 10
9 2BHK 45.80 24 22
10 2BHK 48.28 16 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 70
4 Stilt Floor 0
5 X number of Slabs of Super Structure 81
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 65
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 AISHWARYAM COURTYARD II C 31/03/2020 0 1 0 15 1 78 84
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 32.48 5 5
2 1BHK 33.28 5 5
3 1BHK 29.33 1 1
4 1BHK 32.8 5 5
5 1BHK 31.55 5 5
6 1BHK 36.2 2 2
7 1BHK 29.4 1 1
8 1BHK 29.68 7 5
9 1BHK 31.04 1 1
10 1BHK 33.44 21 19
11 1BHK 30.87 109 92
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 86
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 57
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 86
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 42.9
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 AISHWARYAM COURTYARD II A1 31/03/2020 0 1 1 16 0 4 76
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 67.99 26 17
2 2BHK 46.03 14 0
3 2BHK 46.18 14 6
4 2.5BHK 54.50 26 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 AISHWARYAM COURTYARD II D 31/03/2020 0 1 1 16 0 42 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 47.72 56 14
2 2BHK 45.65 26 15
3 2BHK 45.73 26 15
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 AISHWARYAM COURTYARD II COMMERCIAL 0 1 0 1 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 18.63 7 0
2 SHOP 17.03 1 0
3 SHOP 15.06 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
VIKAS ACHILKAR AND MANOJ TATOOSKAR NA Architect
GA BHILARE NA Structural Engineer
MS SHIVAM CONSTRUCTIONS NA Contractor

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
AISHWARYAM COURTYARD II CHIEF JUDICIAL MAGISTRATE PUNE 3230/2014 Criminal No Appeal 2014 ORDER PASSED
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other