MahaRERA Application

General Information

Other Than Individual

Organization

STAYWELL HOMES PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
No

Address Details

2007
DADHE RUIKAR HOUSE
-
SADASHIV PETH
TILAK ROAD
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411030

Organization Contact Details

02024478086
www.akshaygroup.in

Past Experience Details

Member Information

Member Name Designation Photo
HASMUKH MANGILAL BAFNA Authorized Signatory View Photo
PRAKASH JAVERCHAND OSWAL Managing Director View Photo

Project

FORTUNA D
On-Going Project
31/07/2024
31/07/2024
No
Residential
No
S NO 178, 182-1-2-3, DHAYARI
18-27-16-89 TO 73-48-25-65
18-27-14-64 TO 73-48-16-44
18-27-16-14 TO 73-48-19-81
18-27-14-92 TO 73-48-19-89
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411041
296.44
1
1
0
0

FSI Details

1512
378.51
1890.51

Bank Details

BANK OF BARODA
BARB0SUBHAS

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 10 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 AS PER AGREEMENT
Water Conservation, Rain water Harvesting : YES 0 AS PER AGREEMENT
Energy management : YES 0 AS PER AGREEMENT
Fire Protection And Fire Safety Requirements : YES 0 AS PER AGREEMENT
Electrical Meter Room, Sub-Station, Receiving Station : YES 25 AS PER AGREEMENT
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 AS PER AGREEMENT
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 AS PER AGREEMENT
Storm Water Drains : NO 0 NA
Landscaping & Tree Planting : YES 100 AS PER AGREEMENT
Street Lighting : YES 80 AS PER AGREEMENT
Community Buildings : YES 80 AS PER AGREEMENT
Treatment And Disposal Of Sewage And Sullage Water : YES 0 AS PER AGREEMENT
Solid Waste Management And Disposal : YES 0 AS PER AGREEMENT

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 FORTUNA D FORTUNA D 0 1 0 4 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 81.68 2 0
2 2BHK 79.85 2 0
3 2BHK 81.70 1 0
4 2BHK 79.67 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ABHAY JOSHI NA Architect
SANTOSH PATIL NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other