MahaRERA Application

General Information

Other Than Individual

Organization

SURAJ ESTATE DEVELOPERS PVT LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

15/B
MAHIM MATA BUILDING
SENAPATI BAPAT MARG
MARI NAGAR MAHIM
OPP MAHIM RAILWAY STATION
MAHARASHTRA
Konkan
Mumbai City
Ward GNorth
GNorth-400016
400016

Organization Contact Details

02224460707
www.surajestate.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1PARK SIDEResidentialNA681.44FP 888 DATTA RAUL ROAD DADAR WEST MUMBAI 400028FP 8881282010-07-152011-02-09
2ETERNITY APARTMENTResidentialNA221.57FP 469 MMC CROSS ROAD MAHIM WEST MUMBAI 400016FP 4691162011-08-062011-08-06
3HALLMARKResidentialNA339.47CS 104 BHIMWADI WADALA EAST MUMBAI CS 104172016-07-302016-11-30

Member Information

Member Name Designation Photo
THOMAS RAJAN Managing Director View Photo
RAHUL THOMAS Authorized Signatory View Photo

Project

TRANQUIL BAY
On-Going Project
30/06/2012
31/12/2018
31/12/2019
Yes
Residential
No
FP 1181-1182
CADEL PLAZA
3 MTR WIDE INTERNAL ROAD
KASHINATH DHURU ROAD
FP 1183
MAHARASHTRA
Konkan
Mumbai City
Ward GNorth
GNorth-400028
400028
795.90
1
1
0
0

FSI Details

200
2425.32
2625.32

Bank Details

AXIS BANK
UTIB0000060

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 20 20 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 COMPLETED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 75 WIP
Electrical Meter Room, Sub-Station, Receiving Station : YES 75 WIP
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 100 COMPLETED
Water Supply : YES 0 0
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 COMPLETED
Storm Water Drains : YES 100 COMPLETED
Landscaping & Tree Planting : YES 100 COMPLETED
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 TRANQUIL BAY TRANQUIL BAY 31/12/2018 0 1 1 21 1 1 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 DUPLEX 185.38 1 0
2 1BHK 41.20 2 2
3 1BHK 42.14 2 2
4 1BHK 38.19 1 1
5 2BHK 74.16 1 1
6 2BHK 93.79 1 1
7 2BHK 61.29 1 1
8 1RK 32.25 1 1
9 3BHK 122.45 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 60
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 87

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SUNIL AMBRE AND ASSOCIATES NA Architect
DR KELKAR DESIGNS PVT LTD NA Structural Engineer

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
TRANQUIL BAY CITY CIVIL COURT MUMBAI 968 OF 2011 Civil No Suit 2011 PENDING
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other