MahaRERA Application

General Information

Other Than Individual

Organization

BHARAT INFRASTRUCTURE & ENGINEERING PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

1
BHARAT CORPORATE AVENUE
CLOSE TO LINK ROAD
ANDHERI WEST
D N NAGAR
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400053

Organization Contact Details

02226378000
www.bharatinfra.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Redevelopment of Park Darshan CHSL ParkvistasResidentialNA2194Lallu Bhai Park Andheri West Mumbai Maharashtra 400058CTS No 575 of Village Vile Parle1642015-12-312016-08-20
2Ecovistas Building C2 Moorfield Phase IResidentialNA30600Shilphata Junction ThaneSurvey No 67 Hissa No 2A 3A 3B11342016-12-312017-04-03
3Ecovistas Building D1 Fairfield Phase IResidentialNA30600Shilphata Junction ThaneSurvey No 67 Hissa No 2A 3A 3B11222016-12-312017-04-03
4Redevelopment of Godi Kamgar Building C2 Phase IIResidentialNA10998D N Nagar Andheri WestCTS No 195 part S No 106A part1892014-04-172014-04-17
5Redevelopment of God Kamgar Building C3 Wing A Skyvistas Skyz Phase IIOthersResidential and Commercial10998D N Nagar Andheri WestCTS No 195 part S No 106A part1922016-09-072016-09-07

Member Information

Member Name Designation Photo
Dhaval Atul Barot Authorized Signatory View Photo
Atul Ambalal Barot Managing Director View Photo

Project

Redevelopment of Malad Swing CHSL
On-Going Project
31/12/2018
30/06/2022
No
Others
No
CTS No 629, 629/ 1 to 8
CTS 628
CTS 630
Girdhar Road
CTS 672
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400064
3334
1
1
0
637

FSI Details

0
7915
7915.00

Bank Details

Kotak Mahindra Bank Ltd
KKBK0001384

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 164 164 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Completed
Water Conservation, Rain water Harvesting : YES 100 Completed
Energy management : YES 100 Completed
Fire Protection And Fire Safety Requirements : YES 100 Completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Completed
Aggregate area of recreational Open Space : YES 100 Completed
Open Parking : YES 100 Completed
Water Supply : YES 100 Completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Completed
Storm Water Drains : YES 100 Completed
Landscaping & Tree Planting : YES 100 Completed
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Redevelopment of Malad Swing CHSL Malad Swing CHSL Bharat Optimus 31/12/2021 1 1 2 22 1 12 164
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 98.57 1 1
2 3.5 BHK 105.17 2 2
3 2 BHK 60.39 1 1
4 3 BHK 78.50 1 1
5 3 BHK 84.54 1 1
6 3 BHK 88.24 1 1
7 3 BHK 98.33 6 6
8 8 BHK 408.07 1 1
9 3.5 BHK 105.36 3 3
10 3 BHK 87.66 4 4
11 2 BHK 63.60 1 1
12 3 BHK 81.20 6 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
M/s SHREE BALAJI CONSTRUCTION NA Contractor
S. P. Associates. NA Architect
J+W Consultant NA Engineer
Deepak Nagwani A51900000182 Real Estate Agent
Vasant B Pissay NA Architect
AJAY P RANGWALA A51800004069 Real Estate Agent
Nandlal Purshottamdas Kakad A51800001629 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other