MahaRERA Application

General Information

Other Than Individual

Organization

PLATINUM ENTERPRISES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OFFICE NO - 84, 8TH FLOOR, B-WING.
AGGARWAL TRADE CENTRE
PLOT NO- 62, SECTOR- 11
C.B.D. BELAPUR
OPP. B.P. MARINE ACADEMY
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400614

Organization Contact Details

02241276677

Past Experience Details

Member Information

Member Name Designation Photo
DHARAMSHI DEVJI PATEL Partner View Photo
JESHA BACHU PATEL Partner View Photo
PREMJI KHIMJI PATEL Partner View Photo
JIGNESH VIRCHAND VISARIA Partner View Photo
NANALAL CHATRABHUJ DOSHI Partner View Photo
BHOGILAL CHATRABHUJ DOSHI Partner View Photo
GIRISH JADHAVJI CHHEDA Partner View Photo
GIRISH JADHAVJI CHHEDA Authorized Signatory View Photo

Project

PLATINUM ESCASO
On-Going Project
31/12/2018
31/12/2019
No
Others
No
PLOT NO - 86, SECTOR -21, ULWE, NAVI MUMBAI
PLOT NO - 87
24 m wide road
30 m wide road
PLOT NO - 84 AND 85
MAHARASHTRA
Konkan
Raigarh
Panvel
Ulawe
410206
3499.51
1
1
0
901.43

FSI Details

0
5248.90
5248.90

Bank Details

DENA BANK
BKDN0471168

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 81 0 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 PROVIDED ONLY DRIVE WAY
Water Conservation, Rain water Harvesting : YES 0 NA
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 AS PER FIRE NOC PROVIDED BY CIDCO
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 ELECTRIC METER ROOM IS PROVIDED
FITNESS CENTRE : YES 100 IS PPROVIDED
SOCIETY OFFICE : YES 100 IS PROVIDED
Aggregate area of recreational Open Space : YES 100 WORK COMPLETED
Open Parking : NO 0 NA
Water Supply : YES 100 PROVIDED BY CIDCO
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 CHAMBERS
Storm Water Drains : NO 0 LINES IS PROVIDED
Landscaping & Tree Planting : YES 100 NA
Street Lighting : NO 0 35 NO. OF TREES & LANDSCAPE ON PART 3RD FLOOR
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 PLATINUM ESCASO PLATINUM ESCASO 31/12/2019 0 1 3 9 1 9 81
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 32.43 1 0
2 SHOP 27.63 1 1
3 2BHK 43.81 2 2
4 SHOP 26.39 4 4
5 2BHK 32.5 2 2
6 2BHK 38.32 8 8
7 SHOP 28.29 3 3
8 2BHK 36.67 16 13
9 3BHK 54.30 14 12
10 SHOP 68.33 1 1
11 SHOP 27.61 1 1
12 SHOP 25.59 4 4
13 SHOP 23.6 1 1
14 SHOP 36.18 1 1
15 SHOP 33.63 1 1
16 2BHK 36.58 3 2
17 2BHK 40.30 8 7
18 SHOP 24.02 6 6
19 2BHK 40.21 8 7
20 2BHK 40.68 8 8
21 2BHK 33.2 6 6
22 2BHK 37.63 7 6
23 2BHK 44.19 2 2
24 2BHK 32.26 2 2
25 2BHK 38.76 3 3
26 2BHK 39.81 7 5
27 3BHK 56.04 4 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ATUL PATEL ARCHITECTS NA Architect
A G GOKHALE & ASSOCIATES NA Structural Engineer
D C ENTERPRISES NA Contractor
MITHUN SHANKAR DUNDALE A51700010030 Real Estate Agent
Balgovind Rameshwar Gupta A52000004095 Real Estate Agent
JANAK KISHOR SINGH A52000009133 Real Estate Agent
SUMA MANOJ A51700006487 Real Estate Agent
NARENDRA BAUBHAI CHAUHAN A51700001297 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other