MahaRERA Application

General Information

Other Than Individual

Organization

VEDBHUMI BUILDERS AND DEVELOPERS PVT. LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

1 ST FLOOR
BHUMI ARCADE
PATIDAR BHAWAN ROAD
LAKADGANJ
NEAR LAKADGANJ GARDEN
MAHARASHTRA
Nagpur
Nagpur
Nagpur (Urban)
Nagpur (M Corp.)
440008

Organization Contact Details

07122760512
WWW.VEDBHUMI.COM

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1BHUMI ARCADEOthersCOMMERCIAL AND RESIDENTIAL19000PLOT NO 70 & 71 LAKADGANJ NAGPUR 1301452014-09-012014-09-01

Member Information

Member Name Designation Photo
VIJAY RAMKRUSHAN PAWAR Managing Director View Photo
YOGESH MAGANBHAI CHAWDA Authorized Signatory View Photo

Project

VATSALYABHUMI
On-Going Project
30/10/2019
30/10/2019
No
Others
No
34
ROAD
NALA
NALA AND LAND OF SABINA HOUSING SOCIETY
LAND OF SHRI MALGADE
MAHARASHTRA
Nagpur
Nagpur
Nagpur (Urban)
Nagpur (M Corp.)
440008
21000
6
6
0
0

FSI Details

0
0
0.00

Bank Details

NAGPUR NAGARIK SAHAKARI BANK LTD
NGSB0000006

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 63 80
Covered Parking ( In Numbers) 248 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 C.C. ROADS COMPLITED
Water Conservation, Rain water Harvesting : YES 80 WILL BE DONE IN DUE COURSE
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 65 WILL BE CARRIED OUR ASPER NMC FIRE DEPARTMENT APR
Electrical Meter Room, Sub-Station, Receiving Station : YES 40 WILL BE DONE IN DUE COURSE
Aggregate area of recreational Open Space : YES 70 WILL BE DONE IN DUE COURSE
Open Parking : YES 80 WILL BE DONE IN DUE COURSE
Water Supply : YES 80 WATER SUPPLY FROM CORPORATION AND FROM BOREWELL
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 80 WILL BE CONECTED TO CORPORATION SEWERAGE LINE
Storm Water Drains : YES 80 WIP
Landscaping & Tree Planting : YES 80 TREE WILL BE PLANTED ON COMPLITION
Street Lighting : YES 95 WIP
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 80 WILL BE DONE IN DUE COURSE
Solid Waste Management And Disposal : YES 80 WILL BE DONE IN DUE COURSE

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 VATSALYABHUMI INDRAPRASTH A A1 A2 30/10/2019 0 1 0 2 0 8 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RHA 1 2 3 4 5 6 7 8 71.57 8 8
2 RHA1 1 2 3 4 5 6 7 8 71.57 8 7
3 RHA2 1 2 3 4 5 6 7 8 71.57 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 VATSALYABHUMI GOKUL 30/10/2019 0 1 0 9 0 32 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 GOKUL101 201 301 401 56.324 4 0
2 GOKUL501 601 701 801 56.32 4 0
3 GOKUL102 202 302 402 52.61 4 0
4 GOKUL502 602 702 802 52.61 4 0
5 GOKUL103 203 303 403 57.48 4 0
6 GOKUL503 603 703 803 57.48 4 0
7 GOKUL104 204 304 404 56.11 4 0
8 GOKUL504 604 704 804 56.11 4 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 80
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
11 Overall Percentage of Completion of the work done For the entire Building /Wing 67
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 VATSALYABHUMI MATHURA 30/10/2019 0 1 0 9 0 32 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 MATHURA 401 501 601 71.49 3 0
2 MATHURA 701 801 71.49 2 0
3 MATHURA 102 202 302 71.49 3 0
4 MATHURA 402 502 602 71.49 3 0
5 MATHURA 702 802 71.49 2 0
6 MATHURA 103 203 303 71.49 3 0
7 MATHURA 403 503 603 71.49 3 0
8 MATHURA 703 803 71.49 2 0
9 MATHURA 104 204 304 71.49 3 0
10 MATHURA 404 504 604 71.49 3 0
11 MATHURA 704 804 71.49 2 0
12 MATHURA 101 201 301 71.49 3 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 80
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 VATSALYABHUMI VRINDAVAN 30/10/2019 0 1 0 9 0 32 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 VATSALYABHUMI SHRINATHJI 30/10/2019 0 1 0 8 0 56 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Flat 504 604 704 61.54 3 0
2 Flat505605705 61.54 3 2
3 Flat 102 202 302 402 61.54 4 4
4 Flat108208308408 61.54 4 1
5 Flat508608708 61.54 3 0
6 Flat 501 601 701 61.54 3 1
7 Flat 104 204 304 404 61.54 4 3
8 Flat506606706 61.54 3 1
9 Flat107207307407 61.54 4 3
10 Flat507607707 61.54 3 2
11 Flat105205305405 61.54 4 3
12 Flat106206306406 61.54 4 4
13 Flat 502 602 702 61.54 3 2
14 Flat 101 201 301 401 61.54 4 2
15 Flat 103 203 303 403 61.54 4 3
16 Flat 503 603 703 61.54 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 80
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

70
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
11 Overall Percentage of Completion of the work done For the entire Building /Wing 69.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 VATSALYABHUMI DWARKA 30/10/2019 0 1 0 7 0 72 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Dwarka110210310 53.96 3 2
2 Dwarka112212312 53.96 3 1
3 DWARKA KRISH OFF 101 91.23 1 0
4 Dwarka 405 505 605 53.96 3 0
5 Dwarka406506606 53.96 3 1
6 Dwarka 101 201 301 53.96 3 1
7 DWARKA KRISH SHOP002 11.85 1 0
8 DWARKA KIRSH SHOP003 16.02 1 0
9 Dwarka108208308 53.96 3 2
10 DWARKA KRISH SHOP004 18.28 1 0
11 DWARKA KRISH SHOP005 15.95 1 0
12 DWARKA KRISH SHOP006 16.10 1 0
13 Dwarka 104 204 304 53.96 3 2
14 DWARKA KRISH SHOP007 9.58 1 0
15 Dwarka107207307 53.96 3 1
16 Dwarka 412 512 612 53.96 3 1
17 Dwarka408508608 53.96 3 1
18 Dwarka109209309 53.96 3 2
19 Dwarka409509609 53.96 3 2
20 Dwarka 404 504 604 53.96 3 1
21 Dwarka 402 502 602 53.96 3 0
22 Dwarka 103 203 303 53.96 3 0
23 Dwarka 403 503 603 53.96 3 0
24 DWARKA KRISH OFF 202 40.63 1 0
25 DWARKA KRIS.SHOP 001 11.02 1 0
26 dwarka 105 205 305 53.96 3 1
27 Dwarka 106 206 306 53.96 3 1
28 Dwarka410510610 53.96 3 1
29 Dwarka111211311 53.96 3 2
30 Dwarka407507607 53.96 3 0
31 DWARKA KRISH OFF 102 40.63 1 0
32 Dwarka411511611 53.96 3 1
33 Dwarka 401 501 601 53.96 3 2
34 DWARKA KRISH OFF 201 91.23 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 80
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

50
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
11 Overall Percentage of Completion of the work done For the entire Building /Wing 59

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
LKC CONSTRUCTION NA Contractor
N GOUR INFRASTRUCTURE PVT LTD NA Contractor
PRABHA CONSTRUCTION NA Contractor
MATOSHRI PRABHA DEVELOPERS NA Contractor
M B MALEWAR DESIGNS PVT LTD NA Architect
P S PATANKAR NA Structural Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other