MahaRERA Application

General Information

Other Than Individual

Organization

Dhaval Developers
Others
Association of Persons
Do you have any Past Experience ?
Yes

Address Details

401
Centerpoint
Jn. of Juhu Tara Rd & SV Rd
Santacruz West
Above Standard Chartered Bank
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400054

Organization Contact Details

02265025054
www.dhavalgroup.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Spring View CHSLResidentialNA586.40Parekh Nagar Kandivali West1104/41142003-02-242003-02-24
2Sunrise Orlem Tower 1ResidentialNA242.11Sunder Lane Malad westCTS no 438 etc1282012-12-142012-12-14
3Sunville CHSLResidentialNA6698th Rd JVPD Scheme Vile Parle WestCTS no 231182006-10-202006-10-20
4Sunrise KandivaliResidentialNA172.78Near Adukia School Kandivali WestCTS no 349/A/B/A11242006-08-102006-08-10

Other Organization Type Member Information

Name Member Type
Sanjaykumar Kanakrai Parekh Individual
Hiralal Jethalal Parikh Partnership

Project

Sunrise Orlem 2A Phase 1
On-Going Project
31/12/2016
31/12/2019
Yes
Residential
Yes
CTS no 438A, 438B, 438D, 438E, 439
Sunrise Orlem 2B
CTS no 438k
Sunrise Orlem Tower 1
Rehab Building SRA
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400097
1046.85
1
1
0
0

FSI Details

200
4109.61
4309.61

Bank Details

The Bharat Cooperative Bank Ltd
BCBM0000016

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 39 11 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 0
Water Conservation, Rain water Harvesting : YES 80 Common for the layout
Energy management : NO 0 The STP plant will be ready before possession
Fire Protection And Fire Safety Requirements : YES 0 As per CFO NOC; to be handed over before possessio
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 to be handed over before possession
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 will be completed before possession for phase 1
Water Supply : YES 0 As per MCGM
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Common for the layout
Storm Water Drains : YES 10 South& west side WIP; as per remarks
Landscaping & Tree Planting : YES 10 Common for the layout
Street Lighting : YES 0 Will be handed before possession
Community Buildings : NO 0 as per SWDremark
Treatment And Disposal Of Sewage And Sullage Water : YES 0 will be completed before final possession
Solid Waste Management And Disposal : NO 0 the final layout will comprise of internal street

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Sunrise Orlem 2A Phase 1 Sunrise Orlem 2A 0 1 5 23 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK Type 1 103.00 12 5
2 3 BHK type 2 102.68 21 4
3 DUPLEX TYPE 1 148.91 1 0
4 Duplex Type 2 138.73 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 25
2 X number of Basement(s) and Plinth 25
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 12
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 79
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 34.1

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
JM Financial Products Limited A51900000277 Real Estate Agent
RAJESH KANAKRAI PAREKH A51800005302 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
Shree Ramdev Enterprises NA Contractor
Sanjay Neve NA Architect
Design Studio Ahmedabad NA Architect
Hiren Tanna NA Structural Engineer
Rajesh Parekh NA Other

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Sunrise Orlem 2A Phase 1 City Civil Court 202013 of 2015 Civil No Suit 2015 No Restraining Order has been passed
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Declaration in FORM B
Commencement Certificates
Building Plan Approval (IOD)
Commencement Certificates
Building Plan Approval (IOD)
Status of Conveyance
Certificates of Architect (Form 4)
Other
Status of Formation of Legal Entity (Society/Co Op etc.)