MahaRERA Application

General Information

Other Than Individual

Organization

GOEL GANGA INDIA PVT LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

3RD FLOOR
SAN MAHU COMPLEX
5 BUND GARDEN ROAD
CAMP
OPP. POONA CLUB
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411001

Organization Contact Details

02026140251
www.goelganga.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1GANGA GLITZResidentialNA10926.39Survey No 16 P AND Survey No 17 P Village Undri Taluka Haveli District Pune 411 060SR NO 16 P AND 17 P21922018-04-022017-04-29
2GANGA SPARSHResidentialNA6472.18Survey No 16Pand 17 P Village Undri Taluka Haveli District Pune SR NO 16 P AND 17 P21542014-04-012013-11-16
3GANGA ARCADIAOthersRESIDENTIAL AND COMMERCIAL4279.49Survey No. 22 Hissa No 2 situated at Village Kharadi Taluka Haveli District Pune 411 014 SR NO 22/211202015-12-012015-10-31
4AMRUTGANGAOthersRESIDENTIAL AND COMMERCIAL40000VADGAON BK PUNE Sy No- 35/1,36,37/2A,38/1,39/1B,40/1B Plot No-196112013-12-302013-10-28
5GANGA ARCADIA OthersRESIDENTIAL AND COMMERCIAL2257.41SR NO 22 Hissa No 2 Village Kharadi Taluka Haveli District Pune 411014 SR NO 22 Hissa No 21282017-06-302017-06-28

Member Information

Member Name Designation Photo
JAIPRAKASH RAMRATAN BAJARI Authorized Signatory View Photo
NIRAJ KUMAR GUPTA Authorized Signatory View Photo
MOHNISH ANIL KHANDELWAL Authorized Signatory View Photo

Project

GANGA LEGEND A4 AND B1..
On-Going Project
30/12/2020
30/06/2023
Yes
Residential
Yes
Sr No 305 P , 306 P and 339 P , Village Bavdhan Budruk, Taluka Mulashi District Pune
Sr No 339 P
SR No 339 P 338 307 306 P
Nala 339 P 305 P
18 meter wide D P Road
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
DSK Ranwara Internal Road Ram Nagar
Bavdhan
411021
10800.77
4
4
0
1080.07

FSI Details

0
21550.67
21550.67

Bank Details

IndusInd Bank
INDB0000002

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
GANGA LEGEND A4 AND B1.. Gulab Namdeo Dagade & Others Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 555 352 65

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 AS PER ARCHITECT CERTIFICATE
Water Conservation, Rain water Harvesting : YES 0 AS PER ARCHITECT CERTIFICATE
Energy management : YES 0 AS PER ARCHITECT CERTIFICATE
Fire Protection And Fire Safety Requirements : YES 100 AS PER ARCHITECT CERTIFICATE
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AS PER ARCHITECT CERTIFICATE
Aggregate area of recreational Open Space : YES 0 AS PER ARCHITECT CERTIFICATE
Open Parking : NO 0 NA
Water Supply : YES 100 AS PER ARCHITECT CERTIFICATE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS PER ARCHITECT CERTIFICATE
Storm Water Drains : YES 100 AS PER ARCHITECT CERTIFICATE
Landscaping & Tree Planting : YES 96 AS PER ARCHITECT CERTIFICATE
Street Lighting : YES 0 AS PER ARCHITECT CERTIFICATE
Community Buildings : YES 100 AS PER ARCHITECT CERTIFICATE
Treatment And Disposal Of Sewage And Sullage Water : YES 100 AS PER ARCHITECT CERTIFICATE
Solid Waste Management And Disposal : YES 90 AS PER ARCHITECT CERTIFICATE

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 GANGA LEGEND A4 AND B1.. A4 1-11 FLOORS 30/12/2022 2 1 1 11 1 0 98
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 46.27 14 14
2 1 BHK 36.60 27 27
3 2 BHK 45.99 22 22
4 1 BHK 33.39 8 8
5 1 BHK 33.54 4 4
6 2BHK 42.57 2 2
7 2 BHK 42.01 6 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 92
11 Overall Percentage of Completion of the work done For the entire Building /Wing 99.2
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 GANGA LEGEND A4 AND B1.. A4 12-23 FLOORS 30/12/2022 0 0 0 12 0 0 93
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.60 1 1
2 1 BHK 38.46 3 3
3 2 BHK 42.57 24 24
4 1 BHK 33.54 23 23
5 1 BHK 33.39 18 18
6 2 BHK 42.01 24 24
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 99
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 96
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 97
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 86
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.6
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 GANGA LEGEND A4 AND B1.. B1 1-11 FLOORS 30/12/2022 2 1 1 11 1 0 172
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 60.29 1 1
2 2BHK 67.91 10 10
3 3BHK 97.27 10 10
4 3BHK 97.45 4 4
5 3 BHK 94.81 1 1
6 2BHK 60.39 16 16
7 2BHK 54.85 5 5
8 2BHK 63.27 5 5
9 3BHK 92.97 1 1
10 3 BHK 94.26 6 6
11 2BHK 62.30 7 7
12 2BHK 54.75 2 2
13 2BHK 60.20 18 18
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 99
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 98.7
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 GANGA LEGEND A4 AND B1.. B1 12-23 FLOORS 30/12/2022 0 0 0 12 0 0 192
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 54.85 23 23
2 2BHK 60.39 1 1
3 3 BHK 97.27 1 1
4 3 BHK 94.81 11 11
5 3 BHK 94.26 12 12
6 2 BHK 62.30 12 12
7 2 BHK 54.75 24 24
8 2BHK 63.27 12 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 98
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 96
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

92
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 84
11 Overall Percentage of Completion of the work done For the entire Building /Wing 56.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Direction Next Design Studio NA Architect
HARISHCHANDRA JADHAV ELECTRICALS NA Contractor
G M INFRATECH NA Contractor
P. L. VISHWAKARAMA Electricals NA Contractor
SKY CONSTRUCTIONS NA Contractor
SHANKAR CHAUDHARI NA Contractor
D D SHARMA CONTRACTOR NA Contractor
SHRADDHA ENTERPRISES NA Contractor
M/S ABHINAV SINGH NA Contractor
RAMRAJ CONSTRUCTION NA Contractor
S S ENTERISES (PROP. SOBRAN SINGH) NA Contractor
INDUSTRIAL PLANT AND WASTE TREATMENT CORPORATION NA Contractor
Chandrashekhar Design Inc NA Architect
VIKAS & NILIMA BHOSEKAR NA Other Professional
AMAR ENTERPRISES (PROP. AMARNATH MOURYA) NA Contractor
GANGAPRASAD K VARMA NA Contractor
AJAY KUMAR GUPTA NA Contractor
Unicorn MEP services Consultants Pvt Ltd NA Other Professional
M/S G.A Bhilare Consulants Pvt Ltd .GABCPL NA Other Professional
Gaurav Shah NA Engineer
ANIKET SOLANKI AND CO NA Chartered Accountant

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
GANGA LEGEND A4 AND B1.. CIVIL COURT PUNE 522 Civil No Suit 2011 PENDING
NA
GANGA LEGEND A4 AND B1.. CIVIL COURT PUNE 1338 Civil No Suit 2007 PENDING
NA
GANGA LEGEND A4 AND B1.. CIVIL COURT PUNE 880 Civil No Suit 2012 PENDING
NA
GANGA LEGEND A4 AND B1.. CIVIL COURT PUNE 1300 Civil No Suit 2012 PENDING
NA
GANGA LEGEND A4 AND B1.. HIGH COURT BOMBAY 464 Civil No Appeal 2014 Disposed off in favor of Promoter
NA
GANGA LEGEND A4 AND B1.. CIVIL COURT PUNE 1192 Civil No Suit 2012 PENDING
NA
GANGA LEGEND A4 AND B1.. CIVIL COURT PUNE 1025 Civil No Suit 2012 PENDING
NA
GANGA LEGEND A4 AND B1.. NGT 39 Others No Suit 2015 PENDING
NA
GANGA LEGEND A4 AND B1.. Additional Commissioner Pune 21 Civil No Appeal 2017 PENDING
NA
GANGA LEGEND A4 AND B1.. SDO PUNE 444 Civil No Appeal 2015 Disposed off in favor of Promoter
NA
GANGA LEGEND A4 AND B1.. SDO PUNE 842 Civil No Appeal 2012 DISPOSED OFF
NA
GANGA LEGEND A4 AND B1.. SDO PUNE 727 Civil No Appeal 2012 DISPOSED OFF IN FAVOR OF PROMOTER
NA
GANGA LEGEND A4 AND B1.. JDR 4135 Others No Other 2017 DISPOSED OFF
NA
GANGA LEGEND A4 AND B1.. CJJD 1663 Civil No Suit 2017 PENDING
NA
GANGA LEGEND A4 AND B1.. HON DISTRICT JUDGE PUNE 4 Civil No Appeal 2018 DISPOSED OFF
NA
GANGA LEGEND A4 AND B1.. NGT 116 Civil No Appeal 2018 PENDING
NA
GANGA LEGEND A4 AND B1.. ADDITIONAL COLLECTOR 813 Civil No Appeal 2017 DISPOSED OFF IN FAVOUR OF GOEL GANGA INDIA PVT LTD
NA
GANGA LEGEND A4 AND B1.. HIGH COURT MUMBAI 3282 Others No Writ Petition 2019 PENDING
NA
GANGA LEGEND A4 AND B1.. HIGH COURT MUMBAI 4163 Others No Writ Petition 2019 PENDING
NA
GANGA LEGEND A4 AND B1.. CJSD 470 Civil No Suit 2019 PENDING
NA
GANGA LEGEND A4 AND B1.. HIGH COURT MUMBAI 356 Civil No Other 2019 DISPOSED OFF
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Certificates of Architect (Form 4)
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other
Other
Other