MahaRERA Application

General Information

Other Than Individual

Organization

SRI DEVELOPER
Partnership
NA
Do you have any Past Experience ?
No

Address Details

0,
NEAR KAMBARE POWER HOUSE,
SHAHAPUR-MURBAD ROAD,
SHAHAPUR
NEAR KAMBARE POWER HOUSE,
MAHARASHTRA
Konkan
Thane
Shahapur
Kambare
421601

Organization Contact Details

22225425569

Past Experience Details

Member Information

Member Name Designation Photo
SUDHIR DATTATRAY TELAVANE Partner View Photo
VILAS THAKURSINGH PATIL Partner View Photo
SUDHIR DATTATRAY TELAVANE Authorized Signatory View Photo
VILAS THAKURSINGH PATIL Authorized Signatory View Photo

Project

SAI LANDMARK
On-Going Project
31/12/2022
30/06/2024
No
Residential
Yes
341/1,347,348,350,351,360
343
361
364
79
MAHARASHTRA
Konkan
Thane
Shahapur
Kambare
421601
17560
3
3
0
1756

FSI Details

0
13088.25
13088.25

Bank Details

IDBI BANK LTD
IBKL0001486

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SAI LANDMARK JANARDAN NARAYAN BHOIR Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SAI LANDMARK SADANAND MOTIRAM PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SAI LANDMARK SANJAY HARCHAND PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 60 WORK IN PROGRESS
Water Conservation, Rain water Harvesting : YES 0 NA
Energy management : YES 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 NA
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : YES 0 NA
Water Supply : YES 0 NA
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 20 WORK IN PROGRESS
Storm Water Drains : YES 50 WORK IN PROGRESS
Landscaping & Tree Planting : YES 50 WORK IN PROGRESS
Street Lighting : YES 30 WORK IN PROGRESS
Community Buildings : YES 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 SAI LANDMARK LILY 0 1 0 5 2 2 2
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 13259.76 38 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 SAI LANDMARK TULSI 0 1 0 5 2 2 2
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 13259.76 38 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 20
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 32
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 SAI LANDMARK SAI PLAZA 0 1 0 5 2 2 2
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL.COMMERCI 13348.84 46 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SANJAY WADILE NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other