MahaRERA Application

General Information

Other Than Individual

Organization

Dhruva Woollen Mills Pvt Ltd
Company
NA
Do you have any Past Experience ?
Yes

Address Details

5th floor
Runwal and Omkar Esquare
Off Eastern Express Highway
Sion
Opp Sion Chunabhatti Signal
MAHARASHTRA
Konkan
Mumbai City
Ward FNorth
FNorth-400022
400022

Organization Contact Details

02261133000

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1RGC PHASE I TOWER IVY AND LILYResidentialNA2803.20Village Balkum District ThaneAs documented21382016-12-302016-04-28
2RGC PHASE IIResidentialNA6401.55Village Balkum District ThaneAs documented 53602014-05-312016-02-17

Member Information

Member Name Designation Photo
SANJAY DAGA Director View Photo
H A Visweswara Director View Photo

Project

RUNWAL EIRENE - PART I
On-Going Project
31/10/2021
30/06/2024
Yes
Residential
No
SURVEY NOS AS DOCUMENTED
30 MT WIDE DP ROAD
HIGHLAND PROPERTY
MUMBAI UNIVERSITY CAMPUS
20 MT WIDE DP ROAD
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400608
25095.54
11
11
0
3764.33

FSI Details

22961.00
48933.54
71894.54

Bank Details

ICICI BANK
ICIC0000740

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 928 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 YET TO BE STARTED
Water Conservation, Rain water Harvesting : YES 0 YET TO BE STARTED
Energy management : YES 0 YET TO BE STARTED
Fire Protection And Fire Safety Requirements : YES 0 YET TO BE STARTED
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 YET TO BE STARTED
Aggregate area of recreational Open Space : YES 0 YET TO BE STARTED
Open Parking : YES 0 YET TO BE STARTED
Water Supply : YES 0 YET TO BE STARTED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 YET TO BE STARTED
Storm Water Drains : YES 0 YET TO BE STARTED
Landscaping & Tree Planting : YES 0 YET TO BE STARTED
Street Lighting : YES 0 YET TO BE STARTED
Community Buildings : YES 0 YET TO BE STARTED
Treatment And Disposal Of Sewage And Sullage Water : YES 0 YET TO BE STARTED
Solid Waste Management And Disposal : YES 0 YET TO BE STARTED

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 RUNWAL EIRENE - PART I 6A 30/06/2024 1 1 2 42 1 0 78
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 34.92 40 0
2 2BHK 45.05 40 0
3 2BHK 48.34 73 0
4 1BHK 34.92 1 0
5 2BHK 44.53 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 RUNWAL EIRENE - PART I 6B 30/06/2024 1 1 2 42 1 0 78
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 35.02 2 2
2 1BHK 35.11 80 49
3 2BHK 48.34 73 36
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 40
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 4
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 RUNWAL EIRENE - PART I 6C 30/06/2024 1 1 2 42 1 0 78
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 48.34 73 35
2 1BHK 35.11 80 51
3 1BHK 35.02 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 70
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 7
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 RUNWAL EIRENE - PART I 6D 30/06/2024 1 1 2 42 1 0 78
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 45.05 40 0
2 2BHK 48.34 73 0
3 2BHK 44.53 1 0
4 1BHK 34.92 41 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 40
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 4
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 RUNWAL EIRENE - PART I 7 30/06/2024 0 1 2 36 1 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 35.09 29 0
2 1BHK 34.89 35 0
3 2BHK 48.20 68 43
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 RUNWAL EIRENE - PART I 8 30/06/2024 0 1 2 36 1 0 132
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 73.16 10 10
2 3BHK 73.21 9 9
3 2BHK 59.82 13 13
4 3BHK 68.89 24 19
5 3BHK 68.77 25 20
6 2BHK 55.37 51 45
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 54
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 4
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 56.8
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 RUNWAL EIRENE - PART I 9 30/06/2024 0 1 2 36 1 0 194
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 85.03 4 4
2 3BHK 85.08 13 13
3 2BHK 59.82 20 20
4 3BHK 80.39 24 11
5 3BHK 80.54 21 15
6 2BHK 55.37 50 42
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 54
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 4
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 56.8
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 RUNWAL EIRENE - PART I 10 30/06/2024 0 1 2 36 1 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.41 18 18
2 2BHK 46.80 21 21
3 2BHK 48.89 20 20
4 1BHK 34.66 17 14
5 2BHK 44.24 14 11
6 2BHK 48.14 42 34
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 RUNWAL EIRENE - PART I 11 30/06/2024 0 1 2 36 1 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.41 38 38
2 2BHK 48.89 34 34
3 1BHK 34.79 32 28
4 2BHK 47.95 28 16
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 RUNWAL EIRENE - PART I 12 30/06/2024 0 1 2 36 1 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.41 23 23
2 2BHK 46.80 18 18
3 2BHK 48.89 28 28
4 2BHK 44.78 17 15
5 1BHK 35.10 12 10
6 2BHK 47.90 34 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 RUNWAL EIRENE - PART I 13 30/06/2024 0 1 2 36 1 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 36.41 21 21
2 2BHK 48.89 12 12
3 2BHK 48.89 26 26
4 1BHK 34.66 14 12
5 2BHK 47.91 17 14
6 2BHK 47.52 42 39
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 57.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
CURRIE AND BROWN NA Architect
DT REALTORS A51700008479 Real Estate Agent
MS PROPERTY SOLUTION A51700009898 Real Estate Agent
SUMIT MADANJI JAIN A51700006243 Real Estate Agent
Coldwell Realty Private Limited A51800000194 Real Estate Agent
Dagadu Namdev Sabale A51700010774 Real Estate Agent
Royalti Real Estate Private Limited A51700003623 Real Estate Agent
Provident Capital A52000007945 Real Estate Agent
Prop Leader Realty A51700005043 Real Estate Agent
Basant Jalduram Kanojiya A51700008975 Real Estate Agent
RISING HOMES A51700004600 Real Estate Agent
IMCP Realty Pvt Ltd A51700003576 Real Estate Agent
4G INFO SOURCE LLP A51700001533 Real Estate Agent
Meenu Manik Sippy A51700004834 Real Estate Agent
DSP Realty A51700002295 Real Estate Agent
M M Properties A51700012250 Real Estate Agent
Mystic India Realtors & Consultant A51900006152 Real Estate Agent
Pyramid Homes A51700004003 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Harmony Infrasolutions Private Limited A51900003914 Real Estate Agent
HOUSEZINN PROPERTIES PRIVATE LIMITED A51700003041 Real Estate Agent
CRAFT FINANCIAL ADVISORS PVT LTD A51900000136 Real Estate Agent
FANM Property Services Pvt Ltd A52000000045 Real Estate Agent
MAHAVIR PRASAD TOSHNIWAL A51700003016 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
RUNWAL EIRENE - PART I High Court of Bombay 1794 Civil Yes Writ Petition 2015 Writ Petition is dismissed as withdrawn

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other