MahaRERA Application

General Information

Other Than Individual

Organization

GOOD LUCKDEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OPP BHARAT GEAR COMPANY
COMPOUND KHARDI ROAD
S D COMPOUND
KAUSA, MUMBRA
KAUSA, MUMBRA
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400612

Organization Contact Details

02224521452

Past Experience Details

Member Information

Member Name Designation Photo
NOORUDDIN LATIF NAIK Authorized Signatory View Photo
SHEREZADE NOORUDDIN NAIK Partner View Photo

Project

HARMONY COMPLEX - C - WING
On-Going Project
31/12/2021
30/06/2022
Yes
Residential
Yes
141-1/A, 141-1/B
141-B
KALWA JAMA MASJID TRUST
MUNAF SIDDIQUI
SURME
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400612
3009.56
1
1
0
1293.93

FSI Details

0
4993.43
4993.43

Bank Details

DCB BANK
DCBL0000029

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
HARMONY COMPLEX - C - WING PARVEZ HAROON KHAN Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
HARMONY COMPLEX - C - WING AZIZUDDIN KHAN Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 UNDERCONSTRUCTION
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 UNDERCONSTRUCTION
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 UNDERCONSTRUCTION
COMPOUND WALL AND GATE : YES 0 UNDERCONSTRUCTION
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 UNDERCONSTRUCTION
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 UNDERCONSTRUCTION
Storm Water Drains : YES 0 UNDERCONSTRUCTION
Landscaping & Tree Planting : YES 0 UNDERCONSTRUCTION
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 HARMONY COMPLEX - C - WING HARMONY COMPLEX - C - WING 0 1 1 13 10 0 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 1392.22 45 4
2 2BHK 1012.18 24 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 38
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 33.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RAKESH J DESHAWARE NA Architect

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
HARMONY COMPLEX - C - WING BOMBAY HIGH COURT 80/2014 Civil No Arbitration Petition 2014 UNDERGOING
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other