MahaRERA Application

General Information

Other Than Individual

Organization

AASHRAY INFRA
Partnership
NA
Do you have any Past Experience ?
No

Address Details

SHOP NO 11
SAINIKETAN CHS
PLOT NO 9A
SECTOR 20
NR JALVAYU VIHAR PHASE II
MAHARASHTRA
Konkan
Raigarh
Panvel
Kharghar
410210

Organization Contact Details

09867926925

Past Experience Details

Member Information

Member Name Designation Photo
JAYESH PATEL Authorized Signatory View Photo
RAHUL PATEL Partner View Photo
SUNIL PATEL Partner View Photo
RAMESHBHAI PATEL Partner View Photo
RAJESHKUMAR DHOLU Partner View Photo
MITESHKUMAR PATEL Partner View Photo
NIKUNJ PATEL Authorized Signatory View Photo
RAHUL PATEL Partner View Photo
PANKAJ DHOLU Partner View Photo
PARESHKUMAR PATEL Partner View Photo
HIMMAT PATEL Partner View Photo
KISHAN POKAR Partner View Photo
VITHAL PATEL Partner View Photo

Project

AASHRAY AANAND
On-Going Project
31/05/2022
31/05/2022
No
Residential
Yes
140/2A AND 141/1B
SY NO 140 PART
SY NO 141 PART
BOUNDARY OF ULHASNAGAR
SY NO 140 PART
MAHARASHTRA
Konkan
Thane
Ambarnath
Ambarnath (R)
421501
5470
6
6
0
547

FSI Details

0
5907
5907.00

Bank Details

BANK OF BARODA
BARB0KHARGA

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
AASHRAY AANAND MADHUKAR SHANKAR GAIKWAD Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
AASHRAY AANAND VIJAY BALIRAM GAIKWAD Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
AASHRAY AANAND NANDU BALIRAM GAIKWAD Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
AASHRAY AANAND KIRAN ASHOK GAIKWAD Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
AASHRAY AANAND SANJAY BALIRAM GAIKWAD Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 WORK YET NOT STARTED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WORK YET NOT STARTED
Aggregate area of recreational Open Space : YES 0 WORK YET NOT STARTED
Open Parking : NO 0 NA
Water Supply : YES 0 AFTER OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WORK YET NOT STARTED
Storm Water Drains : YES 0 WORK YET NOT STARTED
Landscaping & Tree Planting : YES 0 ONLY TREE PLANTATION WILL PROVIDE
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 AASHRAY AANAND A WING 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 24.62 4 0
2 RESIDENTIAL 19.86 4 0
3 RESIDENTIAL 31.73 8 0
4 RESIDENTIAL 43.19 1 0
5 RESIDENTIAL 28.46 1 0
6 RESIDENTIAL 20.33 1 0
7 RESIDENTIAL 44.12 1 0
8 RESIDENTIAL 21.37 4 0
9 RESIDENTIAL 22.24 8 0
10 RESIDENTIAL 30.82 4 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 AASHRAY AANAND B WING 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 28.46 1 0
2 RESIDENTIAL 20.33 1 0
3 RESIDENTIAL 43.19 1 0
4 RESIDENTIAL 44.12 1 0
5 RESIDENTIAL 21.37 4 0
6 RESIDENTIAL 22.24 8 0
7 RESIDENTIAL 30.82 4 0
8 RESIDENTIAL 24.62 4 0
9 RESIDENTIAL 19.86 4 0
10 RESIDENTIAL 31.73 8 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 AASHRAY AANAND C WING 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 28.66 1 0
2 RESIDENTIAL 22.7 16 0
3 RESIDENTIAL 19.83 4 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 AASHRAY AANAND D WING 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 38.05 1 0
2 RESIDENTIAL 28.66 2 0
3 RESIDENTIAL 20.37 2 0
4 RESIDENTIAL 22.7 12 0
5 RESIDENTIAL 29.35 4 0
6 RESIDENTIAL 19.83 12 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 040
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 54
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 AASHRAY AANAND E WING 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 24.13 4 0
2 RESIDENTIAL 25.42 4 0
3 RESIDENTIAL 22.7 4 0
4 RESIDENTIAL 19.21 8 0
5 RESIDENTIAL 23.46 4 0
6 RESIDENTIAL 23.92 4 0
7 RESIDENTIAL 28.66 2 0
8 RESIDENTIAL 29.25 1 0
9 RESIDENTIAL 22.65 2 0
10 RESIDENTIAL 42.15 1 0
11 RESIDENTIAL 19.32 8 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 AASHRAY AANAND F WING 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 RESIDENTIAL 28.66 3 0
2 RESIDENTIAL 29.97 1 0
3 RESIDENTIAL 28.62 1 0
4 RESIDENTIAL 22.7 24 0
5 RESIDENTIAL 24.01 4 0
6 RESIDENTIAL 23.25 4 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 20
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 14

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SPACE DESIGNERS NA Architect
K K PATEL NA Engineer
RAMAN PATEL NA Contractor
Santosh Bhagwan Mahajan A51700001695 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other