MAHA-RERA Application

General Information

Other Than Individual

Organization

St. Angelo's VNCT Ventures Pvt. Ltd.
Company
NA
Do you have any Past Experience ?
No

Address Details

6 FLOOR, C-WING
JYOTI PLAZA
S.V.ROAD
KANDIVALI(W)
ABOVE BANK OF BARODA
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400067

Organization Contact Details

02267899000
www.savvglobal.com

Past Experience Details

Member Information

Member Name Designation Photo
AGNELORAJESH NAZARETH ATHAIDE Managing Director View Photo
SUGRA AGNELORAJESH ATHAIDE Authorized Signatory View Photo
CHIDAMBARAM NAGAPPAN Authorized Signatory View Photo
GEETHA NAGAPPAN Authorized Signatory View Photo

Project

THE WHITE VILLAS
On-Going Project
31/12/2020
31/12/2020
No
Residential
No
420/1
REMAINING PROPERTY OF GAT NO 420 PT
LAYOUT OF GAT NO 418 AND OTHERS
PROPERTY OF GAT NO 422A
LAYOUT OF GAT NO 418 AND OTHERS
MAHARASHTRA
Konkan
Thane
Shahapur
Kalamgaon
420601
8000
43
43
0
800

FSI Details

0
7200
7200.00

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 43 19 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 WIP
Water Supply : YES 0 WIP
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WIP
Storm Water Drains : YES 0 WIP
Landscaping & Tree Planting : YES 0 WIP
Street Lighting : YES 0 WIP
Electrical Meter Room, Sub-Station, Receiving Station : YES 90 WIP
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Community Buildings : YES 30 WIP
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WIP
Solid Waste Management And Disposal : YES 0 WIP
Water Conservation, Rain water Harvesting : YES 0 WIP
Energy management : YES 0 WIP
Fire Protection And Fire Safety Requirements : NO 0 NA

Building Details

Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 THE WHITE VILLAS ZEUS VILLA NO 1 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 THE WHITE VILLAS ATLANTIS VILLA NO 2 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 THE WHITE VILLAS APHRODITE VILLA NO 3 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 THE WHITE VILLAS APOLLO VILLA NO 4 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 THE WHITE VILLAS ARTEMIS VILLA NO 5 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 THE WHITE VILLAS ASTRAEA VILLA NO 6 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 THE WHITE VILLAS ATHENA VILLA NO 7 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 THE WHITE VILLAS ATLAS VILLA NO 8 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 THE WHITE VILLAS ATTIS VILLA NO 9 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 THE WHITE VILLAS BIA VILLA NO 10 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 THE WHITE VILLAS CASTOR VILLA NO 11 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 71.93 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
12 THE WHITE VILLAS CERUS VILLA NO 12 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
13 THE WHITE VILLAS KETO VILLA NO 13 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
14 THE WHITE VILLAS CLIO VILLA NO 14 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
15 THE WHITE VILLAS CRONUS VILLA NO 15 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
16 THE WHITE VILLAS CYBELE VILLA NO 16 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
17 THE WHITE VILLAS DEMETER VILLA NO 17 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
18 THE WHITE VILLAS ELECTRA VILLA NO 18 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
19 THE WHITE VILLAS EOS VILLA NO 19 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
20 THE WHITE VILLAS ERATO VILLA NO 20 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
21 THE WHITE VILLAS EROS VILLA NO 21 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
22 THE WHITE VILLAS GAIA VILLA NO 22 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
23 THE WHITE VILLAS HARMONIA VILLA NO 23 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 20
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
24 THE WHITE VILLAS ZEPHYR VILLA NO 24 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 43
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
25 THE WHITE VILLAS HELIOS VILLA NO 25 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 43
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
26 THE WHITE VILLAS HEMERA VILLA NO 26 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
27 THE WHITE VILLAS HERA VILLA NO 27 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
28 THE WHITE VILLAS URANIA VILLA NO 28 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 42
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
29 THE WHITE VILLAS HERMES VILLA NO 29 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 42
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
30 THE WHITE VILLAS HESPERUS VILLA NO 30 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
31 THE WHITE VILLAS TRITON VILLA NO 31 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 10
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
32 THE WHITE VILLAS IRIS VILLA NO 33 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
33 THE WHITE VILLAS KRATOS VILLA NO 34 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
34 THE WHITE VILLAS MAIA VILLA NO 35 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
35 THE WHITE VILLAS METIS VILLA NO 36 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
36 THE WHITE VILLAS THALIA VILLA NO 37 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
37 THE WHITE VILLAS NYX VILLA NO 38 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
38 THE WHITE VILLAS OCEANUS VILLA NO 39 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.02 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 50
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 5
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
39 THE WHITE VILLAS PHEME VILLA NO 40 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 80.29 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 50
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 5
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
40 THE WHITE VILLAS PLUTUS VILLA NO 41 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 87.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 20
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 22.5
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
41 THE WHITE VILLAS RHEA VILLA NO 42 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 86.53 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 10
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 5
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 21.5
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
42 THE WHITE VILLAS SELENE VILLA NO 43 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 64.71 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 50
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 5
Sr.No. Project Name Name Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
43 THE WHITE VILLAS STYX VILLA NO 44 0 1 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 79.85 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 50
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SSPR GROUP INTERNATIONAL NA Contractor
TANGENT ARCHITECTS NA Architect
H M RAJE STRUCTURAL CONSULTANTS PRIVATE LTD NA Structural Engineer
AECON PROJECTS NA Other
SUSSANNE KHAN HOUSE OF DESIGN NA Other

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates
Other