MahaRERA Application

General Information

Other Than Individual

Organization

Spenta Builders Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

3 A\B
Rajabahadur Mansion
20, Ambalal Doshi Marg
Fort
Opposite Bombay Stock Exchange
MAHARASHTRA
Konkan
Mumbai City
Ward ABCD
ABCD-400023
400023

Organization Contact Details

02261295555
www.spentacorporation.com

Past Experience Details

Member Information

Member Name Designation Photo
Shrivallabh Kashiprasad Rathi Authorized Signatory View Photo
Pankaj Lakhamshi Soni Authorized Signatory View Photo
Ashok Gudda Patkar Authorized Signatory View Photo
Dinesh Tukaram Mandavkar Authorized Signatory View Photo

Project

Palazzio
On-Going Project
31/12/2013
31/12/2018
No
Residential
Yes
832 B
CTS Nos 810 810-1 834 837 839 and 832A
CTS Nos 804 814 830 and 831
CTS Nos 805 806 and 807
CTS No 840
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400072
6482
4
4
0
1299

FSI Details

0
13366
13366.00

Bank Details

HDFC
HDFC0000001

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Palazzio Future Communications Ltd Company Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 100
Covered Parking ( In Numbers) 209 179 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 98 Restricted to Driveways. No footpaths.
Water Conservation, Rain water Harvesting : YES 94 As per MCGM Approval
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 97 As per MCGM Approval
Electrical Meter Room, Sub-Station, Receiving Station : YES 95 No receiving Station.
Aggregate area of recreational Open Space : YES 100 NA
Open Parking : YES 100 NA
Water Supply : YES 0 Will receive after Occupation Certificate
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 97 As per MCGM Approval
Storm Water Drains : YES 97 As per MCGM Approval
Landscaping & Tree Planting : YES 97 As per MCGM Approval
Street Lighting : YES 0 Restricted to Driveways within property
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 94 As per MCGM Approval
Solid Waste Management And Disposal : YES 94 As per MCGM Approval

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Palazzio Wing A 2 1 0 12 1 22 51
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 55.23 13 13
2 3BHK 73.52 7 7
3 3BHK 90.70 4 4
4 2BHK 70.96 4 4
5 2BHK 69.10 4 4
6 3BHK 93.69 4 4
7 3BHK 70.82 7 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Palazzio Wing B 2 1 0 12 1 6 46
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1.5BHK 43.78 13 13
2 2BHK 47.42 7 7
3 2BHK 49.43 7 7
4 2BHK 62.30 4 4
5 1.5BHK 55.97 4 4
6 1.5BHK 56.24 4 4
7 2BHK 61.16 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Palazzio Wing C 2 1 0 12 1 14 38
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 71.59 8 8
2 2BHK 69.08 8 8
3 2BHK 54.70 14 14
4 2BHK 54.93 13 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Palazzio Wing D 2 1 0 12 1 4 75
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.31 14 14
2 1BHK 37.35 6 6
3 3BHK 94.73 8 8
4 2BHK 61.12 8 8
5 1BHK 48.86 4 4
6 3BHK 77.66 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 83.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Shashikant Jadhav Spaceage Consultants NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Architect’s Certificate on Completion of Project (Form 4)
Architect’s Certificate on Completion of Project (Form 4)
Architect’s Certificate on Completion of Project (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other