MahaRERA Application

General Information

Other Than Individual

Organization

Sheltrex Karjat Pvt. Ltd.
Company
NA
Do you have any Past Experience ?
No

Address Details

NA
NA
off. Kondiwade Road
Akurle - Shirse Village
Adjacent to Ulhas River
MAHARASHTRA
Konkan
Raigarh
Karjat
Karjat
401201

Organization Contact Details

02261873333

Past Experience Details

Member Information

Member Name Designation Photo
SURESH SINGH Director View Photo
SURESH SINGH Authorized Signatory View Photo

Project

Sheltrex Smart Phone City Project 1 - Phase II
On-Going Project
23/10/2009
31/12/2020
Yes
Others
No
Survey No. 7/B1 to 7/B14
15 M Wide Road
Phase IV buildings and Ulhas River
Amenity space
Mall
MAHARASHTRA
Konkan
Raigarh
Karjat
shirase
410201
10377.38
40
12
28
49129

FSI Details

125000
13067.74
138067.74

Bank Details

HDFC
HDFC0001573

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 75 As per approved layout
Water Conservation, Rain water Harvesting : YES 95 As per design
Energy management : YES 0 Solar panel to take partial load in common areas
Fire Protection And Fire Safety Requirements : YES 40 As per Fire NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 95 As per power suppliers specification
Club House and Swimming Pool : YES 0 Private and Payable Facility
School : YES 0 For All
Shopping Mall : YES 0 For All
Aggregate area of recreational Open Space : YES 0 As per approved layout
Open Parking : YES 0 As per approved layout
Water Supply : YES 100 Bore Well
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Temporary arrangement with collection tank is done
Storm Water Drains : YES 100 As per design
Landscaping & Tree Planting : YES 75 As per design
Street Lighting : YES 80 As per design
Community Buildings : YES 0 Common club house & swimming pool for Project-1&2
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per design
Solid Waste Management And Disposal : YES 0 As per design

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Sheltrex Smart Phone City Project 1 - Phase II G8 0 1 0 3 0 40 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 57.32 2 0
2 SHOP 48.75 2 0
3 SHOP 11.16 1 1
4 1BHK 26.26 14 12
5 1BHKR 35.23 2 2
6 SHOP 46.91 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Sheltrex Smart Phone City Project 1 - Phase II G7 0 1 0 3 0 60 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 21 17
2 1BHKR 35.23 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Sheltrex Smart Phone City Project 1 - Phase II H9 0 1 0 3 0 40 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 46.91 2 0
2 SHOP 57.32 2 0
3 SHOP 76.85 2 0
4 SHOP 48.75 2 0
5 1BHK 26.26 22 20
6 1BHKR 35.23 2 2
7 SHOP 11.16 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Sheltrex Smart Phone City Project 1 - Phase II H8 0 1 0 3 0 60 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 33 24
2 1BHKR 35.23 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 Sheltrex Smart Phone City Project 1 - Phase II I2 0 1 0 3 0 90 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 33 23
2 1BHKR 35.23 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 Sheltrex Smart Phone City Project 1 - Phase II I3 0 1 0 3 0 90 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 33 18
2 1BHKR 35.23 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 Sheltrex Smart Phone City Project 1 - Phase II I4 0 1 0 3 0 90 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 33 19
2 1BHKR 35.23 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
8 Sheltrex Smart Phone City Project 1 - Phase II I5 0 1 0 3 0 60 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 46.91 2 0
2 SHOP 57.32 2 0
3 SHOP 76.85 2 0
4 SHOP 48.75 2 0
5 1BHK 26.26 22 19
6 1BHKR 35.23 2 2
7 SHOP 11.76 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
9 Sheltrex Smart Phone City Project 1 - Phase II J1 0 1 0 3 0 60 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 21 21
2 1BHKR 35.23 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
10 Sheltrex Smart Phone City Project 1 - Phase II J2 0 1 0 3 0 60 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 21 18
2 1BHKR 35.23 3 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
11 Sheltrex Smart Phone City Project 1 - Phase II J3 0 1 0 3 0 60 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.26 21 21
2 1BHKR 35.23 3 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
12 Sheltrex Smart Phone City Project 1 - Phase II J4 0 1 0 3 0 40 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 46.91 2 0
2 SHOP 57.32 2 0
3 SHOP 48.75 2 0
4 1BHK 26.26 14 14
5 1BHKR 35.23 2 2
6 SHOP 11.26 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
13 Sheltrex Smart Phone City Project 1 - Phase II PNS-1 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
14 Sheltrex Smart Phone City Project 1 - Phase II PNS-2 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
15 Sheltrex Smart Phone City Project 1 - Phase II PNS-3 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
16 Sheltrex Smart Phone City Project 1 - Phase II PNS-5 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
17 Sheltrex Smart Phone City Project 1 - Phase II PNS-6 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
18 Sheltrex Smart Phone City Project 1 - Phase II PNS-7 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
19 Sheltrex Smart Phone City Project 1 - Phase II PNS-8 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
20 Sheltrex Smart Phone City Project 1 - Phase II PNS-9 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
21 Sheltrex Smart Phone City Project 1 - Phase II PNS-10 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
22 Sheltrex Smart Phone City Project 1 - Phase II PNS-11 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
23 Sheltrex Smart Phone City Project 1 - Phase II PNS-12 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
24 Sheltrex Smart Phone City Project 1 - Phase II PNS-13 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
25 Sheltrex Smart Phone City Project 1 - Phase II PNS-14 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
26 Sheltrex Smart Phone City Project 1 - Phase II PNS-15 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
27 Sheltrex Smart Phone City Project 1 - Phase II PNS-16 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
28 Sheltrex Smart Phone City Project 1 - Phase II PNS-17 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
29 Sheltrex Smart Phone City Project 1 - Phase II PNS-18 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
30 Sheltrex Smart Phone City Project 1 - Phase II PNS-19 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
31 Sheltrex Smart Phone City Project 1 - Phase II PNS-20 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
32 Sheltrex Smart Phone City Project 1 - Phase II PNS-21 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
33 Sheltrex Smart Phone City Project 1 - Phase II PNS-22 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
34 Sheltrex Smart Phone City Project 1 - Phase II PNS-23 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
35 Sheltrex Smart Phone City Project 1 - Phase II PNS-24 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
36 Sheltrex Smart Phone City Project 1 - Phase II PNS-25 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
37 Sheltrex Smart Phone City Project 1 - Phase II PNS-4 Proposed but not sanctioned 0 1 0 18 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 4480 120 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
38 Sheltrex Smart Phone City Project 1 - Phase II TT Building Proposed but not sanctioned 0 1 0 3 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Residential 1000 24 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
39 Sheltrex Smart Phone City Project 1 - Phase II Commercial/Amenity Building Proposed but not sanctioned 0 1 0 4 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Mix Use 4645 0 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
40 Sheltrex Smart Phone City Project 1 - Phase II II Proposed but not sanctioned 0 1 0 12 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Resi Apt 8000 144 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Rahul Shivaji Agaj NA Architect

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Sheltrex Smart Phone City Project 1 - Phase II Alibaug District Consumer Court 175/2017 Others No Suit 2017 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Alibaug District Consumer Court 180/2017 Others No Suit 2017 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Jr Civil Court Karjat 34/2009 Civil No Suit 2009 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Sub Divisional Officer Karjat 153/2016 Civil No Suit 2016 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Jr Civil Court Karjat 47/2016 Civil No Suit 2016 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 598/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 402/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Alibaug District Consumer Court 99/2017 Others No Suit 2017 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 123/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 96/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 95/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 126/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 64/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 59/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 66/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 239/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 625/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Alibaug District Consumer Court 471/2016 Others No Suit 2016 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 639/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 575/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 580/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 581/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 583/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 642/2018 Others No Suit 2018 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Alibaug District Consumer Court 10/2017 Others No Suit 2017 Pending
NA
Sheltrex Smart Phone City Project 1 - Phase II Mumbai State Commission Consumer Court 57/2018 Others No Suit 2018 Pending
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other