MahaRERA Application

General Information

Other Than Individual

Organization

Om Sai Infra & Om Sai Group
Others
Joint Venture
Do you have any Past Experience ?
No

Address Details

A/301
Glacia Apartment
Edulji Road
Tembhi Naka
Near Jain Mandir
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400601

Organization Contact Details

02225443741

Past Experience Details

Other Organization Type Member Information

Name Member Type
MAHESH PATEL Individual
OM SAI INFRA Partnership

Project

SAI KANISHK PHASE I
On-Going Project
29/02/2016
31/05/2018
Yes
Residential
No
5/5B,9
PLOT BEARING NO 5 HISSA NO 3
PLOT NO 5 HISSA NO 6
PLOT BEARING NO 5 HISSA NO 11
PLOT BEARING NO 5 HISSA NO 4
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400612
488.61
3
3
0
0

FSI Details

0
2738.54
2738.54

Bank Details

AXIS BANK
UTIB0000004

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 32 0 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 30 IN PROCESS
Energy management : YES 90 SOLAR WATER HEATER
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 30 SUB STATION COMMON FOR LAYOUT
Aggregate area of recreational Open Space : YES 70 COMMON FOR LAYOUT 1824.8 SQ.MTR
Open Parking : YES 50 IN PROCESS
Water Supply : YES 30 TMC WATER CONNECTION
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 30 SEPTIC TANK ONLY
Storm Water Drains : YES 50 IN PROCESS
Landscaping & Tree Planting : YES 70 IN PROCESS
Street Lighting : NO 0 NA
Community Buildings : YES 50 CLUB HOUSE COMMON FOR LAYOUT
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 SAI KANISHK PHASE I B1 0 1 0 8 1 10 8
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 22.58 28 28
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 89
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 SAI KANISHK PHASE I B2 31/05/2018 0 1 0 8 1 10 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 31.96 28 19
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 89
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 SAI KANISHK PHASE I B3 0 1 0 8 1 10 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 31.96 28 23
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 89

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SAMEER S LOTKE & ASSOCIATES NA Architect
SAI SQUARE CONSTRUCTION NA Contractor
LIMBANI ENERPRISES NA Contractor
SWARAJ CONSTRUCTION NA Contractor
BHAWANI ENTERPRISE NA Contractor
ENVIRO CON NA Other Professional
S S CONS NA Engineer
CHIDAMBARAM ANANTHRAMAN NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Architect’s Certificate on Completion of Project (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other