MahaRERA Application

General Information

Other Than Individual

Organization

Vaijanath Realtors LLP
Others
Partnership
Do you have any Past Experience ?
No

Address Details

S N 13 H N 19
Barve
Godrej Hill
Barve Village
Near Oshadhara
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
421301

Organization Contact Details

Past Experience Details

Other Organization Type Member Information

Name Member Type
Inder Mohanlal Bhatia Individual
Prashant Inder Bhatia Individual
Mukesh Thakurdas Jaisinghani Individual
Rahul Mukesh Jaisinghani Individual
Raju Thakurdas Jaisinghani Individual
Mahima Infra Estate LLP Partnership

Project

The Residences
On-Going Project
31/12/2016
31/12/2018
No
Residential
No
S no 9/2 9/3 9/4 25/8 26/11
Open Plot
Riverdale
Riverdale Vista
Midtown Tower
MAHARASHTRA
Konkan
Thane
Kalyan
Kalyan
421301
558.88
2
2
0
0

FSI Details

0
8294.26
8294.26

Bank Details

Indian Bank
IDIB000U016

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 33 15 80

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 --
Water Conservation, Rain water Harvesting : YES 100 --
Energy management : YES 100 --
Fire Protection And Fire Safety Requirements : YES 100 --
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 --
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 Building under Construction
Water Supply : YES 0 --
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 --
Storm Water Drains : YES 100 --
Landscaping & Tree Planting : YES 100 --
Street Lighting : YES 0 --
Community Buildings : YES 100 --
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 The Residences Kings Court Wing A 0 1 0 17 1 5 17
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 56.87 17 5
2 2BHK 57.41 32 10
3 3BHK 73.28 17 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 The Residences Kings Court Wing A1 0 1 0 17 1 5 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 56.87 17 6
2 2BHK 57.41 32 5
3 3BHK 73.28 17 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
VITAN CONSULTANT NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other
Other
Other
Other
Other
Other