Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
|
VIGHNAHAR COMPOSITE
|
|
0
|
1
|
0
|
19
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
24.99 |
190 |
190 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
85
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
85
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
85
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
85
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
85
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
85
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
61
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
|
NAVBHARAT R/C OM SAI RAM R/C SAIDHAM R/C - SALE / REHAB COMPOSITE
|
|
2
|
2
|
0
|
31
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
24.99 |
280 |
280 |
2 |
1BHK |
52.77 |
2 |
2 |
3 |
1BHK |
73.76 |
1 |
1 |
4 |
1BHK |
52.40 |
1 |
1 |
5 |
1BHK |
72.84 |
1 |
1 |
6 |
COMMERCIAL |
418.06 |
1 |
1 |
7 |
COMMERCIAL |
650.32 |
1 |
1 |
8 |
COMMERCIAL |
1068.40 |
1 |
1 |
9 |
COMMERCIAL |
43.13 |
84 |
84 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
|
LA ESTRELLA RESIDENCY / COMMERCIAL
|
|
2
|
1
|
3
|
32
|
32 |
0 |
32 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
SHOP |
154.84 |
12 |
12 |
2 |
1BHK |
52.40 |
54 |
54 |
3 |
2BHK |
73.76 |
24 |
24 |
4 |
2BHK |
72.84 |
81 |
81 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
|
SHRADDHA SABURI / OM SAI RAM / PAP / SAIDHAM - RESIDENTIAL / COMMERCIAL - SALE / REHAB COMPOSITE
|
|
1
|
1
|
0
|
28
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
24.99 |
112 |
112 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
RABINDRANATH TAGORE ABHASHAN PRAKALP LAYOUT
|
LARIENA RESIDENCY / COMMERCIAL
|
|
1
|
1
|
1
|
27
|
1 |
0 |
1 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
47.38 |
24 |
24 |
2 |
1BHK |
37.40 |
24 |
24 |
3 |
1BHK |
37.57 |
24 |
24 |
4 |
2BHK |
57.11 |
21 |
21 |
5 |
2BHK |
56.60 |
24 |
24 |
6 |
MPROOM |
40.92 |
3 |
3 |
7 |
COMMERCIAL |
113.71 |
2 |
2 |
8 |
SHOP |
380.32 |
4 |
4 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
50
|
2
|
X number of Basement(s) and Plinth
|
43
|
3
|
X number of Podiums
|
43
|
4
|
Stilt Floor
|
43
|
5
|
X number of Slabs of Super
Structure
|
43
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
40
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
25
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
43
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
43
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
15
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
38.8
|
|