MahaRERA Application

General Information

Other Than Individual

Organization

Shagun Manav Spaces LLP
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

Shagun Developers, Office No. 501, 5th Floor,
Royal Spaces, Opp. My World Society,
Balewadi High Street,
Baner
My World Society
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411045

Organization Contact Details

02026051702

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Perfect 10 Phase IResidentialNA1436.50Survey No 38 Balewadi38 Hissa No 2A, 2B, 31682017-06-302017-03-10
2Perfect 10 Phase IIResidentialNA1238.33S No 38 BalewadiS No 38 Hissa No 2A 2B 31862019-03-312018-04-20
3Perfect 10 Phase IIIResidentialNA1181.98S NO 38 BalewadiS No 38 Hissa No 2A 2B 31862019-10-312018-12-27

Member Information

Member Name Designation Photo
Rinku Rajkumar Shewani Authorized Signatory View Photo
Rinku Rajkumar Shewani Partner View Photo
Rupesh Suhas Banthia Authorized Signatory View Photo
Rupesh Suhas Banthia Partner View Photo

Project

Perfect 10 Phase IV
New Project
30/12/2025
No
Residential
Yes
Survey No 38, Hissa No 2A, 2B and 3, Balewadi
Survey No 38 Hissa No 4 Balewadi
Survey No 38 Hissa No 1 Balewadi
Proposed Building No B7 and B8 of Perfect 10
Building No B3 and B4 of Perfect 10
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
Balewadi Road
Balewadi
411045
823.59
1
1
0
2491.43

FSI Details

0
7094.51
7094.51

Bank Details

HDFC Bank
HDFC0000007

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Perfect 10 Phase IV Bhoomi Shashwat Estate Pvt Ltd Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 90 78 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Drive ways
Water Conservation, Rain water Harvesting : YES 40 As per Consultants Drawings
Energy management : YES 0 Solar Water heating System as per norms
Fire Protection And Fire Safety Requirements : YES 40 As per Fire norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 40 As per MSEDCL norms
Aggregate area of recreational Open Space : YES 100 As per Consultants Drawings
Open Parking : NO 0 NA
Water Supply : YES 40 PMC/Borwell/Tanker as per agreement
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 40 As per Consultants Drawings
Storm Water Drains : YES 0 As per Consultants Drawings
Landscaping & Tree Planting : YES 0 As per Consultants Drawings
Street Lighting : YES 0 As per Consultants Drawings
Community Buildings : YES 100 Club House common for all phases
Treatment And Disposal Of Sewage And Sullage Water : YES 40 As per Consultants Drawings
Solid Waste Management And Disposal : YES 40 As per Consultants Drawings

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Perfect 10 Phase IV B5-B6 31/12/2024 0 1 0 13 2 0 92
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 61.87 87 78
2 1BHK 45.89 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 74
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 11
11 Overall Percentage of Completion of the work done For the entire Building /Wing 39

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Vikas Achalkar NA Architect
Shree Manibhadra Construction NA Contractor
Kirtane & Pandit LLP NA Chartered Accountant
V L Jain & Co NA Chartered Accountant
KPCA & Co NA Chartered Accountant
Premkumar Somani NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other