MahaRERA Application

General Information

Other Than Individual

Organization

SAI PREM DEVELOPERS PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
No

Address Details

SURVEY NO.109/1
ARCH GARDENS
GHODBUNDER
VINAY NAGAR
VINAY NAGAR
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401107

Organization Contact Details

02242664830

Past Experience Details

Member Information

Member Name Designation Photo
ANIL GOVINDPRASAD LOHIA Chairperson View Photo

Project

ARCH GARDENS I AND II
On-Going Project
31/12/2017
31/12/2018
31/12/2019
No
Residential
No
109/1
SURVEY NUMBER 110 PT AND 109
SURVEY NUMBER 104 AND 109
SURVEY NUMBER 110 PT
SURVEY NUMBER 109
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
401101
1703
3
3
0
252.98

FSI Details

3228
4
3232.00

Bank Details

BANK OF BARODA
BARB0SIRPMR

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 6 2 70

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 90 RING WELL CONSTRUCTED
Energy management : YES 50 SOLAR WH
Fire Protection And Fire Safety Requirements : YES 60 AS PER MBMC FIRE NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 60 CIVIL WORK COMPLETED
Aggregate area of recreational Open Space : YES 0 TO COMPLETE AFTER OTHER SITE WORK
Open Parking : YES 40 WIP
Water Supply : YES 0 BY MBMC AFTER OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 80 WIP
Storm Water Drains : YES 50 CONNECTING TO MUNICIPAL DRAIN
Landscaping & Tree Planting : YES 20 TO COMPLETE AFTER OTHER SITE WORK
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ARCH GARDENS I AND II ARCH GARDENS I COMMERCIAL 0 1 0 3 0 1 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 COMMERCIAL 13.14 2 2
2 COMMERCIAL 13.05 1 1
3 COMMERCIAL 11.52 1 1
4 COMMERCIAL 64.19 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ARCH GARDENS I AND II ARCH GARDENS II A WING 31/12/2018 0 1 0 10 1 7 3
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 COMMERICAL 10.59 2 0
2 COMMERCIAL 15.63 1 0
3 COMMERCIAL 11.61 1 1
4 COMMERCIAL 14.77 1 0
5 COMMERCIAL 11.43 1 1
6 COMMERCIAL 16.35 1 1
7 RESIDENTIAL 51.74 9 5
8 RESIDENTIAL 35.58 17 15
9 COMMERCIAL 12.63 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 ARCH GARDENS I AND II ARCH GARDENS II B WING 31/12/2018 0 1 0 11 1 7 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 COMMERCIAL 14.31 1 0
2 COMMERCIAL 25.08 1 0
3 COMMERCIAL 18.49 1 0
4 COMMERCIAL 45.61 1 0
5 COMMERCIAL 36.13 4 0
6 RESIDENTIAL 22.82 1 0
7 COMMERCIAL 30.94 1 0
8 COMMERCIAL 20.90 1 0
9 COMMERCIAL 25.27 2 0
10 COMMERCIAL 9.75 1 1
11 RESIDENTIAL 36.13 34 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
NARSINH CHHAGANLAL PATEL CIVIL LABOUR CONTRACTOR NA Contractor
ANIL MOTIRAMANI LICENSE SURVEYOR REGISTERED WITH MBMC NA Architect
ANIL MOTIRAMANI LICENSE SURVEYOR REGISTERED WITH MBMC NA Engineer
ASHOK KAILASHNATH KHANDELWAL A51700004792 Real Estate Agent
Raj kishor R Tiwari A51700004535 Real Estate Agent
AJITESH P VISHWAKARMA A51700000172 Real Estate Agent
Propvilla Realty Pvt Ltd A51700007597 Real Estate Agent
RAKESH U SINGH A51700000288 Real Estate Agent
Rahul Singh A51700009268 Real Estate Agent
DINESH SARVARIA A51700001121 Real Estate Agent
GOPAL BOGHABHAI KALSARIYA A51700001181 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement