MahaRERA Application

General Information

Other Than Individual

Organization

Puravankara Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

130/1
Puravankara Limited
Ulsoor Road
Yellappa Chetty Layout
HDFC Bank
KARNATAKA
Bangalore
560042

Organization Contact Details

08043439635

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Provident Sunworth IResidentialNA20000Nice Mysore Road Venkatapura Kengeri Hobli Bengaluru1 - 261514402015-11-302015-11-18

Member Information

Member Name Designation Photo
Ashish Puravankara Managing Director View Photo
Nani R Choksey Director View Photo

Project

Purva Clermont Wing C
New Project
30/06/2027
No
Residential
No
395, 3951, 3952, 3953, 3954, 3955, 3956, 3957, 3958, 3959, 39510
Lands in CTS 390 and 394
Other Phases of the Project
Other Phases of the Project
Lands in CTS 396 and 394
MAHARASHTRA
Konkan
Mumbai Suburban
Mumbai
DP Road
Ghatkopar Taluk, Deonar Village
400088
864.13
1
1
0
0

FSI Details

357.51
5005.52
5363.03

Bank Details

INDUSIND Bank
INDB0000008

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 92 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per sanction plan
Water Conservation, Rain water Harvesting : YES 0 As per sanction plan and NOC's
Energy management : YES 0 As per sanction plan and NOC's
Fire Protection And Fire Safety Requirements : YES 0 As per sanction plan and NOC's
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As per sanction plan and NOC's
Aggregate area of recreational Open Space : YES 0 As per sanction plan
Open Parking : YES 0 As per sanction plan
Water Supply : YES 0 As per sanction plan
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per sanction plan and NOC's
Storm Water Drains : YES 0 As per sanction plan and NOC's
Landscaping & Tree Planting : YES 0 As per sanction plan
Street Lighting : YES 0 As per sanction plan and NOC's
Community Buildings : YES 0 Clubhouse and amenities to be commenced
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per sanction plan and NOC's
Solid Waste Management And Disposal : YES 0 As per sanction plan and NOC's

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Purva Clermont Wing C Purva Clermont Wing C 31/12/2026 2 1 1 18 1 0 92
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 92.04 17 0
2 3BHK 87.99 14 0
3 3BHK 90.37 17 0
4 4BHK 117.68 1 0
5 3BHK 90.3 1 0
6 3BHK 87.99 1 0
7 3BHK 91.35 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 20

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Ingrain NA Architect
Sumit Ghogale NA Engineer
VDSR & Co LLP NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
4 Details of encumbrances
5 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement