MahaRERA Application

General Information

Other Than Individual

Organization

A G SUPERSTRUCTURES PVT LTD
Company
NA
Do you have any Past Experience ?
Yes

Address Details

115
MAKER CHAMBER III
NARIMAN POINT
NARIMAN POINT
VIDHAN BHAVAN
MAHARASHTRA
Konkan
Mumbai City
Mumbai City
Mumbai City
400021

Organization Contact Details

02243439900

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1SAMRIDDHIResidentialNA14454INDRALOK LAYOUT BHAYANDER EAST 401105184 1 2 185 1246282017-12-312021-06-25

Member Information

Member Name Designation Photo
ASHISH GIRDHARILAL VAID Managing Director View Photo
SUNIL NARAINDAS LALWANI Director View Photo

Project

WINDERMERE BUILDING NO 1 TO 6
New Project
31/12/2027
No
Residential
Yes
NEW S. NO./OLD S. NO./ H.NO. 221/564/1,3,4A,4B,8. NEW S. NO/OLD S. NO/ H.NO/220/565/1,4,6,7,8,9,10. NEW S. NO/OLD S. NO/H.NO/267/567/1,2/1. NEW S. NO/OLD S. NO/245/579/1A,1B,2,3A,3B,3C,4,5,6,7,8. NEW S. NO/OLD S.NO/H.NO. 222/580/1,2,6
PLOT NO 220
PLOT NO 244
PLOT NO 266
18 M ROAD
MAHARASHTRA
Konkan
Thane
Thane
Mira-Bhayandar (M Corp.)
NEAR PLATINA COMPLEX
BHAYANDER WEST
401101
6042
6
6
0
538.36

FSI Details

8848.10
0
8848.10

Bank Details

ICICI BANK LTD
ICIC0000376

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
WINDERMERE BUILDING NO 1 TO 6 SPAN DEVELOPERS Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 124 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 CONCRETE WITH PAVERS
Water Conservation, Rain water Harvesting : YES 0 COLLECTION TANK OUTSIDE BUILDING LINE
Energy management : YES 0 LED FITTINGS WILL BE USED
Fire Protection And Fire Safety Requirements : YES 0 AS PER MBMC CFO NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 ONLY METER ROOM WILL BE PROVIDED
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : YES 0 NA
Water Supply : YES 0 MBMC SUPPLY LINE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 CONNECTION TO MBMC LINE
Storm Water Drains : YES 0 CONNECTION TO MBMC
Landscaping & Tree Planting : YES 0 SOFT AND HARD SCOPE
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 STP OUTSIDE BUILDING LINE
Solid Waste Management And Disposal : YES 0 Common Garbage Disposal System

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 WINDERMERE BUILDING NO 1 TO 6 WINDERMERE BUILDING NO 1 31/12/2027 0 1 0 7 1 8 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 46.45 28 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 65
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 4
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 36.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 WINDERMERE BUILDING NO 1 TO 6 WINDERMERE BUILDING NO 2 31/12/2027 0 1 0 7 1 8 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 46.45 28 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 75
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 4
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 37.9
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 WINDERMERE BUILDING NO 1 TO 6 WINDERMERE BUILDING NO 3 31/12/2027 0 1 0 7 1 8 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 46.45 28 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 80
2 X number of Basement(s) and Plinth 90
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 10
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 27
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 WINDERMERE BUILDING NO 1 TO 6 WINDERMERE BUILDING NO 4 31/12/2027 0 1 0 7 1 4 24
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 46.45 28 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 25
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 32.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 WINDERMERE BUILDING NO 1 TO 6 WINDERMERE BUILDING NO 5 31/12/2027 0 1 0 7 1 0 14
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 46.45 14 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 35
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 WINDERMERE BUILDING NO 1 TO 6 WINDERMERE BUILDING NO 6 31/12/2027 0 1 0 7 1 2 26
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 46.45 28 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 50
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 35

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
CONNECTFOUR NA Architect
SACHIN SHIRKE NA Engineer
SBP AND ASSOCIATES NA Chartered Accountant
PUNIT B GUPTA AND ASSOCIATES NA Chartered Accountant
VISHNU BALKISHAN AGRAWAL A51800028609 Real Estate Agent
Tejas Prakash Shah A51700003382 Real Estate Agent
HEMANT CHAMPALAL GADRI A51700034895 Real Estate Agent
Kalpesh Manilal Nagda A51700042431 Real Estate Agent
SANTOSH KUMAR RAMJI KANNAUJIYA A99000041163 Real Estate Agent
JIGNESH MAHENDRAKUMAR BHOJAK A51700030844 Real Estate Agent
Deepak Singh A51900009974 Real Estate Agent
JAVARAJI SAVAJI PARMAR A51700030686 Real Estate Agent
RAVINDRA MOURYA A51700037897 Real Estate Agent
DWARAKA REALTY A51700034368 Real Estate Agent
YOGENDRA GIRISH HARSORA A51800006947 Real Estate Agent
Jitendra Ghanshyam Purohit A51700022857 Real Estate Agent
Square Yards Consulting Private Limited A09600037017 Real Estate Agent
RATANLAL CHAMPALAL GADRI A51700030311 Real Estate Agent
GIRISH KHEMSHANKAR CHATURVEDI A51700013244 Real Estate Agent
Propvilla Realty Pvt Ltd A51700007597 Real Estate Agent
MUKESH UDAL YADAV A51700019290 Real Estate Agent
KAMAL KISHINCHAND KUKREJA A51700013551 Real Estate Agent
Vinod Champalal Gadri A51700000639 Real Estate Agent
GIRISH SHANTILAL VARAIYA A51700023032 Real Estate Agent
RAJENDRA PATHAK A51700031420 Real Estate Agent
DATTATRAY JAGANNATH GOLE A51700027720 Real Estate Agent
LALITKUMAR DAHYALAL RAVAL A51700044237 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 a Details of encumbrances concerned to Finance
2 a Details of encumbrances concerned to Finance
3 a Details of encumbrances concerned to Finance
4 a Details of encumbrances concerned to Finance
5 a Details of encumbrances concerned to Finance
6 a Details of encumbrances concerned to Finance
7 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
2 b Details of encumbrances concerned to Legal
3 b Details of encumbrances concerned to Legal
4 b Details of encumbrances concerned to Legal
5 b Details of encumbrances concerned to Legal
6 b Details of encumbrances concerned to Legal
7 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
2 CERSAI details
3 CERSAI details
4 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
2 Disclosure of Interest in Other Real Estate Organizations
3 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
2 Deviation Report with respect to model copy of Agreement
3 Deviation Report with respect to model copy of Agreement
4 Deviation Report with respect to model copy of Agreement
5 Deviation Report with respect to model copy of Agreement
6 Deviation Report with respect to model copy of Agreement
7 Deviation Report with respect to model copy of Agreement