MahaRERA Application

General Information

Other Than Individual

Organization

Ranawat Properties
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Shop No -15 and 16
Center Point
Mitramandal Chowk
Parvati Paytha
Above Vodafone Store
MAHARASHTRA
Pune
Pune
Haveli
Parvati
411009

Organization Contact Details

02024424151
www.ranawatgroup.in

Past Experience Details

Member Information

Member Name Designation Photo
Maitrik Shrenik Parmar Partner View Photo
Prince Prakash Kankariya Partner View Photo
Pravin Kantilal Jain Partner View Photo
Sandeep Shantilal Kuwad Partner View Photo
Vishal Vilas Jain Partner View Photo
Sushil Vilas Jain Partner View Photo
Sonal Rohit Oswal Partner View Photo
Dinesh Kantilal Jain Partner View Photo

Project

Aura Waters Phase -I
New Project
31/12/2026
Yes
Residential
Yes
Survey No. 13/1A/2 & Survey No. 10/1
Adjoining Survey No 13-1 Part
Adjoining Survey No - 9
Adjoining Survey No 13 -1 Part and Adjoining River
Adjoining Survey No - 10 Part
MAHARASHTRA
Pune
Pune
Haveli
Wadgaon Bk
Anand Nagar
Anand Nagar, Vadgaon Budruk, Pune
411051
2898.59
2
2
0
290.59

FSI Details

15736.22
199.06
15935.28

Bank Details

HDFC Bank
HDFC0005527

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Aura Waters Phase -I Nitin Tukaram Shelke & 28 Others Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Aura Waters Phase -I Prakash Vasant Pathak Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Aura Waters Phase -I Shripad Bhalchandra Limaye Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Aura Waters Phase -I Anup Dnyanoba Shelke Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Aura Waters Phase -I Bhushan Ratanlal Jain Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 254 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per Approved Plan
Water Conservation, Rain water Harvesting : YES 0 As per Approved Plan
Energy management : YES 0 Solar Water System
Fire Protection And Fire Safety Requirements : YES 0 As per Norms
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Only Electric Room
Aggregate area of recreational Open Space : YES 0 As per Approved Plan
Open Parking : NO 0 NA
Water Supply : YES 0 As per Approved Plan
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Chamber Lines STP
Storm Water Drains : YES 0 As per Approved Plan
Landscaping & Tree Planting : YES 0 As per Approved Plan
Street Lighting : YES 0 Light Poles
Community Buildings : YES 0 As per approved Plan
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per approved Plan
Solid Waste Management And Disposal : YES 0 Organic Waste Convertor

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Aura Waters Phase -I A Wing 31/12/2026 1 1 3 23 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 59.21 22 0
2 2BHK 71.56 64 39
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 15
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 41.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Aura Waters Phase -I B Wing 31/12/2026 1 1 3 23 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 100.04 39 33
2 3BHK 101.14 21 16
3 3BHK 101.41 1 1
4 3BHK 101.42 19 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 5
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Pinnac Consulting Pvt. Ltd. NA Architect
Sunil Matalik and Associates NA Engineer
CA GOLESHA & COMPANY NA Chartered Accountant
Bhimashankar Ravindra Kanade A52100024018 Real Estate Agent
RASUL ABBAS SHAIKH A52100021838 Real Estate Agent
Mahadev Vilas Wadikar A52100008970 Real Estate Agent
SANKALP SANJAY BHANDARE A52100032764 Real Estate Agent
Shubhangi Dilip Gore A53000036212 Real Estate Agent
Manjiri Kulkarni A52100039534 Real Estate Agent
ONKAR BUDDHISAGAR JADHAV A52100034147 Real Estate Agent
Susmit Sandesh Hingmire A52600025868 Real Estate Agent
Arvind Waman Randive A52100017710 Real Estate Agent
GANESH MADHUKAR AVHAD A52100045498 Real Estate Agent
AVINASH SHANTARAM BAMGUDE A52100041450 Real Estate Agent
Deepa Amol Kalamkar A52100034349 Real Estate Agent
Murlidhar Dattatray Phadatre A52100025616 Real Estate Agent
SHASHANK MANOHAR MESHRAM A52100029109 Real Estate Agent
RAMESH ASARAM DHANGUDE A52100042436 Real Estate Agent
Pravin Ramesh Kadam A52100031921 Real Estate Agent
LEO LANDS A52100045934 Real Estate Agent
RERA Easy NA Other Professional
Namdev Sopan Nirwal NA Engineer
Milan Shah & Co NA Chartered Accountant

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Aura Waters Phase -I Supreme Court 30364 Civil No Appeal NA 2017 Pending
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 a Details of encumbrances concerned to Finance
2 a Details of encumbrances concerned to Finance
3 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
2 b Details of encumbrances concerned to Legal
3 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement