MahaRERA Application

General Information

Other Than Individual

Organization

Kumar Construction and Properties Pvt Ltd
Company
NA
Do you have any Past Experience ?
Yes

Address Details

2413
KUMAR CAPITAL
EAST STREET
CAMP
NEAR AXIS BANK
MAHARASHTRA
Pune
Pune
Pune City
Pune (CB)
411001

Organization Contact Details

02030069300

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1PEBBLE PARK BResidentialNA1804HADAPSAR5512402014-06-052014-06-05
2Kumar PrincevilleResidentialNA3989.23Moshi Pimpri ChinchwadGAT no 9731342017-03-032017-03-03

Member Information

Member Name Designation Photo
KEWALKUMAR KESARIMAL JAIN Director View Photo
MANISH VIMALKUMAR JAIN Director View Photo
RAJAS VIMALKUMAR JAIN Authorized Signatory View Photo

Project

Princeville - A2, C2 and Conv Shop 2
New Project
25/06/2023
No
Others
No
Sr. No. 97P
18 M wide Road
24 M wide Road
Adjoining GAT no 97
Adjoining GAT No 97
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
Moshi Shiv Road
Moshi
412105
3338.98
3
3
0
333.89

FSI Details

6162.30
1050.07
7212.37

Bank Details

HDFC Bank Ltd
HDFC0000148

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 67 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Trimix Concrete Road
Internal Roads & Footpaths : YES 0 Trimix Concrete Road
Internal Roads & Footpaths : YES 0 Trimix Concrete Road
Water Conservation, Rain water Harvesting : YES 0 Low flow fixtures & RWH Pits
Water Conservation, Rain water Harvesting : YES 100 Low flow fixtures & RWH Pits
Energy management : YES 0 Solar Water Heating System & LED in Common Areas
Energy management : YES 100 Solar Water Heating System & LED in Common Areas
Fire Protection And Fire Safety Requirements : YES 0 FF Tank with Pumps Hose Reel Wet Risers
Fire Protection And Fire Safety Requirements : YES 100 FF Tank with Pumps Hose Reel Wet Risers
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Meter Room to be provided
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Meter Room to be provided
Aggregate area of recreational Open Space : YES 100 Already Completed
Open Parking : YES 0 Paver Blocks
Water Supply : YES 0 Municipal Water & Ground Water with WTP without RO
Water Supply : YES 100 Municipal Water & Ground Water with WTP without RO
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP to be installed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 STP to be installed
Storm Water Drains : YES 0 RCC Pipes with Inspection Chambers
Storm Water Drains : YES 100 RCC Pipes with Inspection Chambers
Landscaping & Tree Planting : YES 0 Plantation as per PCMC guidelines
Landscaping & Tree Planting : YES 100 Plantation as per PCMC guidelines
Street Lighting : YES 0 On electric / solar supply
Street Lighting : YES 100 On electric / solar supply
Community Buildings : YES 0 Club House already completed with Swimming Pool
Community Buildings : YES 100 Club House already completed with Swimming Pool
Community Buildings : YES 97 Club House already completed with Swimming Pool
Treatment And Disposal Of Sewage And Sullage Water : YES 0 STP treated water to be used for Landscaping
Treatment And Disposal Of Sewage And Sullage Water : YES 100 STP treated water to be used for Landscaping
Solid Waste Management And Disposal : YES 0 OWC for Wet Waste & Dry waste disposed by Agency
Solid Waste Management And Disposal : YES 100 OWC for Wet Waste & Dry waste disposed by Agency

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Princeville - A2, C2 and Conv Shop 2 A2 15/04/2023 0 1 0 12 1 14 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 63.20 2 2
2 2BHK 58.10 20 20
3 2BHK 60.50 20 20
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Princeville - A2, C2 and Conv Shop 2 C2 23/06/2023 0 1 0 13 1 8 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 82.40 2 2
2 3BHK 86.00 11 10
3 3BHK 85.70 12 11
4 3BHK 81.60 10 9
5 3BHK 81.10 12 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Princeville - A2, C2 and Conv Shop 2 Conv Shop 2 28/04/2021 0 1 0 1 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop Type 2 20.22 1 1
2 Shop Type 1 17.90 4 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
2 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement