General Information

Other Than Individual

Organization

B & G DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

250/251
BRAMHA HOUSE
M.G. ROAD CAMP PUNE
CAMP PUNE
NEAR KOHINOOR RESTAURANT
MAHARASHTRA
Pune
Pune
Pune City
Pune (CB)
411001

Organization Contact Details

02026330485
WWW.BRAMHAREALTY.IN

Past Experience Details

Member Information

Member Name Designation Photo
SURENDRAKUMAR BRAMHADUTT AGARWAL Partner View Photo
VISHAL SURENDRAKUMAR AGARWAL Authorized Signatory View Photo
JASPREETTSINGH JAGJITSINGH RAJPAL Authorized Signatory View Photo
MRS HARMINDERKAUR FATHESINGH HORA Partner View Photo

Project

BRAMHA SKY ONE
On-Going Project
30/06/2018
31/12/2019
30/12/2021
No
Others
No
SURVEY 59, HISSA 1A/5, 1B ,1A/2
BY SURVEY NO 59
BY PUBLIC ROAD
BY SURVEY NO 59
BY SURVEY NO 59
MAHARASHTRA
Pune
Pune
Haveli
UNDRI
UNDRI
UNDRI
411060
4300
1
1
0
422.03

FSI Details

5205
0
5205.00

Bank Details

INDIAN BANK
IDIB000P680

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 123 50 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 completed
Water Conservation, Rain water Harvesting : YES 100 completed
Energy management : YES 100 completed
Fire Protection And Fire Safety Requirements : YES 100 completed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 completed
Club House : YES 100 COMMON FOR PROJECT
GYM : YES 100 COMMON FOR PROJECT
Aggregate area of recreational Open Space : YES 100 COMMON FOR PROJECT
Open Parking : YES 100 SCOOTER AND CYCLE
Water Supply : YES 100 completed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 completed
Storm Water Drains : YES 100 completed
Landscaping & Tree Planting : YES 100 completed
Street Lighting : YES 100 COMMON FOR PROJECT
Community Buildings : YES 100 COMMON COMMUNITY BUILDING FOR THE PROJECT
Treatment And Disposal Of Sewage And Sullage Water : YES 100 completed
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 BRAMHA SKY ONE BRAMHA SKYONE 31/12/2019 0 1 0 13 1 187 00
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2.5 BHK 59.38 9 8
2 2 BHK 53.48 1 0
3 Showroom 15.97 1 1
4 Showroom 22.14 1 0
5 Showroom 27.95 1 0
6 1.5 BHK 48.29 1 1
7 Showroom 21.78 1 1
8 Showroom 24.45 1 0
9 Showroom 25.24 1 0
10 Showroom 24.18 2 0
11 2 BHK 50.06 1 0
12 1.5 BHK 49.11 1 0
13 Showroom 30.86 1 0
14 Showroom 15.91 1 1
15 1.5 BHK 46.73 1 0
16 2.5 BHK 62.82 1 0
17 Showroom 20.74 1 1
18 Showroom 17.03 1 1
19 Showroom 13.02 1 1
20 Showroom 24.33 1 0
21 Showroom 21.21 1 0
22 Showroom 21.25 1 0
23 1 BHK 35 1 1
24 Showroom 14.78 1 0
25 Showroom 14 1 1
26 2 BHK 54.14 1 1
27 2 BHK 49.06 1 1
28 1 BHK 39.94 1 1
29 1 BHK 39.79 1 1
30 Showroom 16.61 1 1
31 2 BHK 49.55 9 5
32 1 BHK 39.78 9 9
33 2 BHK 50.71 11 5
34 2 BHK 49.57 1 1
35 2 BHK 48.97 9 8
36 1 BHK 35.29 21 21
37 1.5 BHK 48.93 8 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
MR VENKATESH RAMLU RATHOD NA Contractor
JW CONSULTANTS LLP CONTACT PERSON SANJAY THIGALE NA Engineer
IMRAN MOHAMMAD ABBAS SHAIKH LIASONING ARCHITECT NA Architect
MAHAMMAD REZA HASSAN KABUL NA Architect
SARTHAK EARTHMOVERS PROF HANUMANT V MASAL NA Contractor
TECH PROOF SOLUTION PROF MOHAMAD ARIF QURESHI NA Contractor
NTEGRATED CONSULTANT CONTACT PERSON ABHAY NARAYAN PIMPALKHARE NA Other Professional
J S RATHOD WORK DEVELOPMENT NA Contractor
MOHAMMED HANIF S DEGOAN WORK BLOCK WORK PLASTER WORK NA Contractor
Riyaz Ishak Tamboli A52100007758 Real Estate Agent
RICHARD SUBHASH HASNALY A52100003512 Real Estate Agent
PROPWHISTLE REALITIES AND CONSULTANCY PRIVATE LIMITED A52100008253 Real Estate Agent
sayed Ali Arabian A52100001163 Real Estate Agent
MINT LIFESPACES A52100007639 Real Estate Agent
Thomas C Abraham A52100000927 Real Estate Agent
Hasan Khujema Nadir A52100003157 Real Estate Agent
Shrinivas Venkateshwar Dashetty A52100005682 Real Estate Agent
Parag Madhukar Kamble A52100008547 Real Estate Agent
ABDUR RAHMAN NA Contractor
AVIGNA WATERPROOFING NA Contractor
NIRMAL NAYAK NA Contractor
A V ENGINEERS & CONTRACTORS NA Contractor
RAJESH KUMAR CHAUHAN NA Contractor
Shakruddin Mujawar A52100000742 Real Estate Agent
RAMEEZ JILANI SHAIKH A52100017224 Real Estate Agent
MUBASHSHIR KABIR SYED A52100019640 Real Estate Agent
Epcot Downtown Ventures Private Limited A52100017049 Real Estate Agent
BUY INDIA HOMES DIGITAL PRIVATE LIMITED A52100019166 Real Estate Agent
SATVINDER SINGH IQBAL SINGH WASU a52100000162 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
5 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
4 Certificates of CA (Form 5)
5 Certificates of CA (Form 5)
6 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement